RG-MH-08597 · RERA P52100001538 · Last updated on MahaRERA portal: 12 Dec 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 40 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 48 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Dreams Solace D E F wings is a Residential / Group Housing project by Dreams Construction Pvt. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100001538 on 28 Jul 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 48 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameDreams Solace D E F wings
- TypeResidential / Group Housing
- Location
- Hadapsar
- Haveli
- Pune
- 411028
- Pincode411028
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100001538
- ReraGenie IDRG-MH-08597
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on28 Jul 2017
- Promised completion30 Jun 2023
- Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2019)
- Buildings4 building records
- Documents filed38 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D wing | NA | 13 | 0 | 0 | 0 | 0 |
| E wing | NA | 6 | 0 | 0 | 0 | 0 |
| F wing | NA | 6 | 0 | 0 | 0 | 0 |
| Club House | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 12 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
D wing91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E wing41%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
F wing82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Club House91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 12 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 60% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 65% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 60% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 60% |
Parking filed70
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| D wing | 16 | 11 | 27 |
| E wing | 8 | 13 | 21 |
| F wing | 8 | 14 | 22 |
Land and ownership6
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Pankaj Builders | Hadapsar | Pune |
| Lahu Hiraman Magar | Hadapsar | Pune |
| Piraji Baban Magar | Mundhawa | Pune |
| Maruti Hanumant Magar | Mundhawa | Pune |
| Kaluram Baburao Tupe | Hadapsar | Pune |
| Vishwas Kaluram Tupe | Hadapsar | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Shripad Padhye |
| Engineer | Cicom Consultants |
| Partner | Role in project |
|---|---|
| Dreams Construction Pvt. Ltd. | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have completed D wing and got the occupancy certificate which is uploaded. Now we have starting construction activity in F wing. Out of 16 flats in E & F building we have registered 10 no of flats. Remaining 5 flats are cancelled. So we are requesting to get project expiry date to extended till 31/12/2022.
Reason as filed by the promoterDue to duel effect of Demonetisation and GST, the cash flow was badly hampered...
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000022018 | RAHUL BHARAT VEDPATHAK | DREAMS CONSTRUCTION PVT LTD | 19/11/2018 |
| CC005000000106571 | Ashutosh Ashok Abnave | Dreams Constructions Pvt Ltd | 15/02/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 12 Dec 2023
Documents filed38
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Dreams Solace E F sold Booked Inventory .pdf | 12 Dec 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for | 12 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate solace.pdf | 5 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_s Certificate.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate for Quality Assurance 2022.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate for Quality Assurance 2023.pdf | 5 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory.pdf | 5 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Annual Report on Statement of Account 2022.pdf | 5 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Annual report on Statement of Account 2023.pdf | 5 Dec 2023 |
| Other - FinanceFile: Dreams Rajaram NOCs (2).pdf | 1 Sep 2022 |
| Other - FinanceFile: Dreams Rajaram Release Deed_11zon.pdf | 1 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual report on statement of accounts FY 2018-19.pdf | 29 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual report on statement of accounts FY 2019-20.pdf | 29 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual report on statement of accounts FY 2020-21.pdf | 29 Jan 2022 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 28 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Certificate 1.pdf | 28 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 28 Jan 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate of D Wing.pdf | 24 Jan 2022 |
| Certificates of CA (Form 5)File: Dreams Solace Form5.pdf | 25 Jul 2019 |
| Building plan approvalFile: Solace sanctioned plan 2.pdf | 12 Jul 2017 |
| Building plan approvalFile: Solace sanctioned plan 3.pdf | 12 Jul 2017 |
| Building plan approvalFile: Solace sanctioned plan 4.pdf | 12 Jul 2017 |
| Building plan approvalFile: Solace sanctioned plan 5.pdf | 12 Jul 2017 |
| Layout approvalFile: Solace sanctioned layout 1.pdf | 12 Jul 2017 |
| PAN CardFile: Pan Card of Dreams Construction Pvt Ltd-1.pdf | 12 Jul 2017 |
| Copy of the legal title reportFile: Search Report.pdf | 12 Jul 2017 |
| Details of encumbrancesFile: encumbrances documents.pdf | 12 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Solace sanctioned layout 1.pdf | 12 Jul 2017 |
| Building Plan Approval (IOD)File: Solace sanctioned plan 2.pdf | 12 Jul 2017 |
| Building Plan Approval (IOD)File: Solace sanctioned plan 3.pdf | 12 Jul 2017 |
| Building Plan Approval (IOD)File: Solace sanctioned plan 4.pdf | 12 Jul 2017 |
| Building Plan Approval (IOD)File: Solace sanctioned plan 5.pdf | 12 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Solace CC .pdf | 12 Jul 2017 |
| Declaration in FORM BFile: Affidavit Cum Declaration - from Promoters.pdf | 12 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Solace Ar Certificate ( form 1 ).pdf | 12 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEERS CERTIFICATE - SOLACE - JUNE 2017.pdf | 12 Jul 2017 |
| Certificates of CA (Form 3)File: Solace Form 3.pdf | 12 Jul 2017 |
| Proforma of Allotment letterFile: Dreams Solace - MahaRERA - DRAFT of Agreement for Sale .pdf | 12 Jul 2017 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Dreams Rachana A B wings | S no 304 1 Hadapsar Tal Haveli Dist Pune 411028 | 74 | Completed | Sep 2014 | Late, Apr 2015 |
| Dreams Sankalp A to H wings | Gat no 862 P Wagholi Tal Haveli Dist Pune | 336 | Completed | Jun 2014 | Late, Dec 2016 |
| Dreams Camellia A1 A2 D | S No 268 Bavdhan Budruk Tal Mulshi Dist Pune 411021 | 29 | Completed | Jul 2013 | Late, Aug 2014 |
| Dreams Solace A to C wings | S no 69 6C 2 1 Hadapsar Tal haveli dist Pune 411028 | 72 | Completed | Aug 2012 | Late, Sep 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 38 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Dreams Solace D E F wings on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hadapsar13,700+ in Pune
Filed coordinates, straight-line distance. 93 registered projects within 2 km.
Amanora Arbano Towers 73,74,75 and 76
City Corporation Limited
Astrana
Dilip Baburao Tupe
Leisure Town Phase 1
Sai Proviso Homes
ARV Newtown Phase III
Vedant Infracon
Kumar Parc Residences - A2
Kumar Properties Infratech Developers Pvt
Kumar Parc residences - A1
Kumar Properties Infratech Developers Pvt
Builder: Dreams Construction Pvt. Ltd.
Dreams Construction Pvt. Ltd. has 3 registrations on MahaRERA, including Dreams Sankalp L M wings and Dreams Rachana C D wings. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Dreams Solace D E F wings shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Dreams Solace D E F wings is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Dreams Solace D E F wings?
The registered promoter entity is Dreams Construction Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Dreams Solace D E F wings?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Dreams Solace D E F wings?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Dreams Solace D E F wings?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Dreams Solace D E F wings?
The professionals named in the filing: Architect: Ar Shripad Padhye; Engineer: Cicom Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Dreams Solace D E F wings?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback