Dreams Construction Pvt. Ltd.: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Dreams Construction Pvt. Ltd. has 3 registrations in this build, including Dreams Sankalp L M wings and Dreams Rachana C D wings. Its filings disclose 5 earlier MahaRERA projects: 0 of 5 past projects completed on time.

3Registrations in this build
5Past projects disclosed
+6 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Dreams Sankalp L M wingsPune, Maharashtra--Registration lapsed
Dreams Rachana C D wingsPune, Maharashtra--Registration lapsed
Dreams Solace D E F wingsPune, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Solace A to C wings
31 Aug 20123 Sep 2012On time
Dreams Solace A to C wings
31 Aug 20123 Sep 2012On time
Dreams Camellia A1 A2 D
31 Jul 201320 Aug 2014+13 months
Dreams Sankalp A to H wings
30 Jun 20146 Dec 2016+29 months
Dreams Rachana A B wings
30 Sep 20144 Apr 2015+6 months

Frequently asked questions

How do I verify Dreams Construction Pvt. Ltd. as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Dreams Construction Pvt. Ltd.?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.