Home / Browse projects / Mumbai Suburban, Maharashtra / DPS GREENS
DPS GREENS
By DPS BUILDCON CONSTRUCTIONS LLP
RG-MH-43167 · RERA P51800034638 · Last updated on MahaRERA portal: 20 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 24 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DPS GREENS is a Residential / Group Housing project by DPS BUILDCON CONSTRUCTIONS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800034638 on 20 Apr 2022. Possession was promised by 1 Oct 2024 and is now 24 months past that date. The completion date has moved by 6 months from the original filing. 23 of the 48 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameDPS GREENS
- TypeResidential / Group Housing
- Location
- ASHOK NAGAR
- KANDIVALI EAST
- Borivali
- Mumbai Suburban
- 400101
- Pincode400101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800034638
- ReraGenie IDRG-MH-43167
Builder
- NameDPS BUILDCON CONSTRUCTIONS LLP
- Entity typePartnership
- PartnersBIPIN RAVINDRA SINGH, VIPUL PRAVINCHANDRA SHAH
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on20 Apr 2022
- Promised completion1 Oct 2024
- Revised completionRevised to 1 Oct 2024 (originally 1 Apr 2024)
- Buildings1 building record
- Documents filed118 files
Current status
Figures as on 20 Jun 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DPS GREENS | NA | 18 | 15 | 44 | 4 | 48 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
DPS GREENS: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 20 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Entrance Gate | Yes | 100% |
Parking filed46
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SHANT MANOR CO-OP HOUSING SOCIETY LTD | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CHIRAG S RAYANI |
| Engineer | MAHENDRA A MANE |
| Engineer | TEJAS DINESHKUMAR SHAH |
| Chartered Accountant | MEENESH SHETTY |
| Chartered Accountant | SURESH YADAV |
| Partner | Role in project |
|---|---|
| DPS BUILDCON CONSTRUCTIONS LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterContractor unable to complete the projects on the given date .
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Apr 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 29 Jan 2025
Documents filed118
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHANT MANOR FORM 1 RERA DEC 2024.pdf | 20 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHANT MANOR FORM 1 RERA MAR 2025.pdf | 20 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 20 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan.pdf | 20 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 20 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 4.pdf | 20 Jun 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: chirags rayani (3).pdf | 29 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - DPS Green's.pdf | 29 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: chirags rayani (1).pdf | 30 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf | 22 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: chirags rayani.pdf | 8 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DPS GREENS FORM 1 RERA.pdf | 28 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3dps buildcon.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 DPS GREEN.pdf | 28 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5dps buildcon.pdf | 28 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 DPS Green (2).pdf | 12 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DPS Greens RERA Engineer Cert.pdf | 12 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 BUILDCON.pdf | 12 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9724 SANT MANOR FORM 1 RERA (1).pdf | 23 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DPS Greens RERA Engineer FORM 2.pdf | 23 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DPS Buildcon from3.pdf | 23 Apr 2024 |
| Declaration in FORM BFile: Affidavit.pdf | 4 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold.pdf | 4 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Full CC - DPS Green's.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 30 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DPS Greens RERA Engineer Cert.pdf | 30 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 dps buildcon .pdf | 30 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 DPS buildcon .pdf | 24 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SANT MANOR FORM 1 RERA.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DPS Greens RERA Engineer Cert.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 24 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SANT MANOR FORM 1 RERA.pdf | 22 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 22 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A DPS buildcon construction LLP.pdf | 22 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate SANT MANOR FORM 1 RERA.pdf | 24 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DPS Greens RERA Engineer Cert.pdf | 24 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 24 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 _compressed.pdf | 27 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shant Manor Rera Certificate .pdf | 24 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DPS Greens RERA Engineer Cert .pdf | 24 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 .pdf | 2 Dec 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DPS BUILDCON CON LLP Chq2.pdf | 2 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT LETTER from 1 dps greens (1).pdf | 1 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 1 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 dps greens.pdf | 1 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHANT MANOR.pdf | 20 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHANT MANOR.pdf | 20 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 20 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE .pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 1-5.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 6-10.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 11-15.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 16-20.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 21-25.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed26-30.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 31-35.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 36-40.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 41-45.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 46-50.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 51-55.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 56-60.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed61-65.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 66-70.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 71-75.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed76-80.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed81-85.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 86-90.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 91-95.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 96-100.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed101 -105.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed106-110.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed111-115.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 116-120.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 121-125.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed 126-130.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed131-135.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed136-140.pdf | 13 Apr 2022 |
| OtherFile: Shant Manor DA_compressed141-145.pdf | 13 Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 118 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep DPS GREENS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KANDIVALI EAST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 115 registered projects within 2 km.
Sheetal Uptown
SIDHESHWAR LIFESPACES PRIVATE LIMITED
ENSO SANZA
Sai Aastha Developers
SPRINGWOODS
PRATIK CONSTRUCTION
Godrej Nest
Shivam Megastructures Pvt Ltd
PATON TOWERS
PRAVIN VIRAM SATRA
Godrej Bliss
SHIVAM DEVELOPERS
See every Mumbai Suburban project, with the district possession charts
Builder: DPS BUILDCON CONSTRUCTIONS LLP
DPS BUILDCON CONSTRUCTIONS LLP has 1 registration on MahaRERA, including DPS GREENS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that DPS GREENS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DPS GREENS is delayed beyond 1 Oct 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DPS GREENS?
The registered promoter entity is DPS BUILDCON CONSTRUCTIONS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DPS GREENS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DPS GREENS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DPS GREENS?
The professionals named in the filing: Architect: CHIRAG S RAYANI; Engineer: MAHENDRA A MANE; Engineer: TEJAS DINESHKUMAR SHAH; Chartered Accountant: MEENESH SHETTY; Chartered Accountant: SURESH YADAV. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DPS GREENS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback