Completed No litigation declared Residential / Group Housing project

DP STAR TRILOK

By DP BUILDHOMES LLP

RG-MH-26310 · RERA P51800003937 · Last updated on MahaRERA portal: 30 Mar 2024

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
6Complaints at MahaRERAon this registration
Jump to the 203 documents Report an error

DP STAR TRILOK is a Residential / Group Housing project by DP BUILDHOMES LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003937 on 7 Aug 2017. The registration is recorded completed; possession was promised by 14 Dec 2023. The completion date has moved by 12 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameDP STAR TRILOK
  • TypeResidential / Group Housing
  • Location
    • Datta Mandir Road
    • Bhandup West
    • Kurla
    • Mumbai Suburban
    • 400078
  • Pincode400078
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003937
  • ReraGenie IDRG-MH-26310

Builder

  • NameDP BUILDHOMES LLP
  • Entity typePartnership
  • PartnersSomraj Trilok Dua, Surinderkumar Bansilal Sharma
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Aug 2017
  • Promised completion14 Dec 2023
  • Revised completionRevised to 14 Dec 2023 (originally 15 Dec 2022)
  • Buildings1 building record
  • Documents filed203 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DP STAR TRILOKNA220000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

DP STAR TRILOK: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 30 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed49

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots49
Closed/Covered49

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,091 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4125.79
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchROAD NO 22 WAGLE IND ESTATE THANE WEST 400604

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerRanjan Chandrakant Tipnis
Chartered AccountantShripati Gandhi Choudhari & Co
Chartered AccountantPravin Jayanti & Associates
PartnerRole in project
DP BUILDHOMES LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012896Dec 2022 → Dec 2023

Reason as filed by the promoterAs per the letter attached

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC12500859RAJESH ASHOK WAKLEDP BUILDHOMES LLP12/03/2025
CC12500898PARSHURAM SURESH DABHOLKARDP BUILDHOMES LLP15/03/2025
CC12500934SWATI SUHAS PATKARDP BUILDHOMES LLP17/03/2025
CC12500904MANISHA SUBHASH BILOREDP BUILDHOMES LLP15/03/2025
CC12500943ATUL VILAS PARKHEDP BUILDHOMES LLP18/03/2025
CC12501003CHETAN RAMESH SOLANKIDP BUILDHOMES LLP22/03/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Jul 2023

Documents filed203

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 203 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Trilok Mar 23.pdf30 Mar 2024
Certificates of CA (Form 3)File: Form 3 Trilok June 23.pdf28 Nov 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 for Trilok.pdf9 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Trilok Mar 23.pdf30 Sep 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - Trilok.pdf29 Jul 2023
Declaration about Commencement CertificateFile: Declaration about CC Trilok.pdf23 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: 2365053_FurtherCC_signed.pdf20 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure Sold Booked Inventory Trilok.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Trilok.pdf17 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2 Trilok.pdf17 Jun 2023
Certificates of CA (Form 3)File: Trilok Rera Form 3 March 23.pdf17 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM -1 Trilok Dec22.pdf25 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2 Trilok Dec22.pdf25 Feb 2023
Certificates of CA (Form 3)File: Trilok Form 3 Dec 22.pdf25 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA FROM- 5 - 2021 TRILOK.pdf7 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA FROM- 5 TRILOK 2022 pdf.pdf7 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form-5 Trilok Mar 19.pdf30 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form-5 Trilok Mar 20.pdf30 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form -1 Trilok.pdf17 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Trilok.pdf17 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Trilok.pdf17 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: A Wing-Form2A-1st Quarter.pdf17 Nov 2022
Disclosure of sold/ booked inventoryFile: Discolsure Trilok.pdf17 Nov 2022
Certificates of CA (Form 3)File: DP Buildhomes LLP_Trilok.pdf17 Nov 2022
Certificates of CA (Form 3)File: Form 3 Trilok Sep 22.pdf17 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arhitects Certificates - Trilok A Wing.pdf18 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Form-2 Trilok A Wing.pdf18 Jul 2022
Certificates of CA (Form 3)File: Trilok Form 3 Mar 22-1-5.pdf11 Jul 2022
Certificates of CA (Form 3)File: Trilok Form 3 Mar 22-6-10.pdf11 Jul 2022
Disclosure of sold/ booked inventoryFile: Trilok- Diclosure of Sold_Booked Inventory Dec 2021.pdf11 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf29 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1- Trilok Oct-Dec-21.pdf22 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2 - Trilok Oct-Dec-21.pdf22 Mar 2022
Certificates of CA (Form 3)File: Trilok_Form 3_Dec21-1-3.pdf22 Mar 2022
Certificates of CA (Form 3)File: Trilok_Form 3_Dec21-4-6.pdf22 Mar 2022
Certificates of CA (Form 3)File: Trilok_Form 3_Dec21-7-10.pdf22 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf11 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Trilok Sep 21.pdf3 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Trilok Sep 21.pdf3 Nov 2021
Certificates of CA (Form 3)File: Form 3 Sep 21- Trilok.pdf30 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 - Trilok.pdf22 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form - 2 Trilok.pdf22 Sep 2021
Certificates of CA (Form 3)File: Form 3_June 21_Trilok.pdf22 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Final Form - 2A_A Wing_Trilok_till 30 September 20.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Final Form - 2A_A Wing_Trilok_till 31 December 20.pdf23 Aug 2021
Form 2AFile: Form 2A Trilok A Wing March 2020.pdf21 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Trilok A Wing June 2020.pdf21 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Trilok A Wing March 2021.pdf21 Aug 2021
Certificates of CA (Form 3)File: Trilok Form 3 Mar 2021.pdf12 Aug 2021
Declaration about Commencement CertificateFile: DECLARATION of CC- TRILOK.pdf22 Jul 2021
Disclosure of sold/ booked inventoryFile: TRILOK- Diclosure of Sold_Booked Inventory.pdf22 Jul 2021
Certificates of CA (Form 3)File: Trilok Form 3 Dec 20.pdf23 Jun 2021
Layout approvalFile: 1 OF 10.pdf28 Apr 2021
Layout approvalFile: 2 OF 10.pdf28 Apr 2021
Layout approvalFile: 3 OF 10.pdf28 Apr 2021
Layout approvalFile: 4 OF 10.pdf28 Apr 2021
Layout approvalFile: 5 OF 10.pdf28 Apr 2021
Layout approvalFile: 6 OF 10.pdf28 Apr 2021
Layout approvalFile: 7 OF 10.pdf28 Apr 2021
Layout approvalFile: 8 OF 10.pdf28 Apr 2021
Layout approvalFile: 9 OF 10.pdf28 Apr 2021
Layout approvalFile: 10 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 1 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 2 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 3 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 4 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 5 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 6 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 7 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 8 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 9 OF 10.pdf28 Apr 2021
Copy of Layout Approval (in case of layout)File: 10 OF 10.pdf28 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC.pdf28 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form - 1 - Trilok.pdf16 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form - 2 - Trilok.pdf16 Apr 2021
Certificates of CA (Form 3)File: Final_TRILOK.pdf5 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Trilok - Architect Certificate.pdf23 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Trilok - Engineers Certificate.pdf23 Feb 2021
Proforma of Allotment letterFile: Agreement For Sale.pdf21 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 Trilok Architect Certificate.pdf24 Oct 2020

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DP STAR TRILOK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhandup West6,700+ in Mumbai Suburban

2 kmDP STAR TRILOKCompleted 52Lapsed / revoked 34Other 91Dot size: filed unitsN

Filed coordinates, straight-line distance. 177 registered projects within 2 km.

Builder: DP BUILDHOMES LLP

DP BUILDHOMES LLP has 4 registrations on MahaRERA, including DP STAR TRILOK and DP STAR TRINETRA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if DP STAR TRILOK is delayed beyond 14 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DP STAR TRILOK?

The registered promoter entity is DP BUILDHOMES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DP STAR TRILOK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DP STAR TRILOK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DP STAR TRILOK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DP STAR TRILOK?

The professionals named in the filing: Engineer: Ranjan Chandrakant Tipnis; Chartered Accountant: Shripati Gandhi Choudhari & Co; Chartered Accountant: Pravin Jayanti & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DP STAR TRILOK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DP STAR TRILOK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DP STAR TRILOK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.