DOWNTOWN
RG-MH-76653 · RERA P52100018235 · Last updated on MahaRERA portal: 4 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- 7 complaints at MahaRERA
- Completion date moved by 53 months
- 4 extensions taken
- Rs 0.09 crore secured on the land, in favour of Ganesh Balwadkar, Kedar Kulkarni and 1 more
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DOWNTOWN is a Residential / Group Housing project by SAMARTTHA BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100018235 on 16 Oct 2018. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 53 months from the original filing. 34 of the 71 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete. 7 complaints are on record with the regulator.
At a glance
Project
- NameDOWNTOWN
- TypeResidential / Group Housing
- Location
- OFF NATIONAL HIGHWAY NO 4 BYE PASS
- MAHALUNGE
- Mulshi
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100018235
- ReraGenie IDRG-MH-76653
Builder
- NameSAMARTTHA BUILDCON
- Entity typePartnership
- PartnersSHIVRAJ ASHOK BALWADKAR, Mahesh Hiraman Barne
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on16 Oct 2018
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 11 Apr 2022)
- Buildings2 building records
- Documents filed95 files
Current status
Figures as on 4 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AB | NA | 5 | 0 | 31 | 0 | 31 |
| CD | NA | 5 | 0 | 40 | 0 | 40 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 90%.
AB73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 45% |
CD90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 75% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed53
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| AB | 22 | 15 | 37 |
| CD | 1 | 15 | 16 |
Land and ownership3
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| BABURAO CHINDHU MOHOL | Mahalunge | Pune |
| YOGESH NARAYAN MOHOL | Mahalunge | Pune |
| RANJIT SURESH MOHOL | Mahalunge | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| CD | NA | Rs 5.95 cr | Rs 5.65 cr |
| AB | NA | Rs 5.41 cr | Rs 3.07 cr |
| - | NA | Rs 1.21 cr | Rs 96.46 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SWAPNIL P KSHIRSAGAR |
| Engineer | G A BHILARE |
| Engineer | Sagar Uttam Gaikwad |
| Chartered Accountant | O.R.Tonape & Co |
| Partner | Role in project |
|---|---|
| SAMARTTHA BUILDCON | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Promoter could not complete the project due to the Covid 19 pandemic which arose all over the Country. The promoter has speeded up the work and will complete the work in an extended period. Requesting to grant us an extension.
Reason as filed by the promoterFirstly, due to Covid-19 pandemic the project work was stop for a longer period, and then due to change of road alignment by PMRDA the project got delayed, which took time to resolve. As of today the CD Building is 100% complete and we are in process of getting Part Completion Certificate. Further, the AB Building is about approx. 75% completed. Thus to complete the reaming work, we require an extension. Requesting to kindly permit us to extend the project registration.
Reason as filed by the promoterThe promoter has completed the major construction work and obtained a part occupancy certificate on 14/03/2024. Due to the Covid-19 pandemic, which affected the entire world, there were labor and material shortages that led to delays in the project's completion. The promoter is now seeking an extension to complete the construction work and requests your kind consideration for granting this extension.
Reason as filed by the promoterThe project was delayed initially due to COVID-19. When work resumed subsequently, we encountered issues regarding finances and labor. The project was restarted once again after that; it is now 80 % complete, and an extension period will be required to the finalize the remaining work.
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000117029 | Vishal V Tendulkar | Samarttha Buildcon | 23/05/2022 |
| CC005000000310479 | Sandeep Chavan | Mahesh Hiraman Barne, Shivraj Ashok Balwadkar | 25/02/2024 |
| CC12401126 | Avinash Dilipbhai Tondle | SAMARTTHA BUILDCON | 14/12/2024 |
| CC12401127 | Ajinkya Jaysing Jadhav | SAMARTTHA BUILDCON | 14/12/2024 |
| CC12401142 | Shalaka Harshal Dhole | SAMARTTHA BUILDCON | 16/12/2024 |
| CC12401131 | Debarati Rajendra Chatterjee | SAMARTTHA BUILDCON | 14/12/2024 |
| CC12501332 | Aasawari Bhairu Yejare | SAMARTTHA BUILDCON | 22/04/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Oct 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Feb 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Feb 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Apr 2024
Documents filed95
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Q4 25-26.pdf | 4 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Q4.pdf | 4 Jul 2026 |
| Withdrawal Update Form 3File: form 3 Q4.pdf | 4 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Q3 25-26.pdf | 3 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 Q3 25-26.pdf | 3 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 Q3 25-26.pdf | 3 Jul 2026 |
| Form 5 (FY 2025-2026)File: Form 5 25-26.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 Q2 25-26.pdf | 3 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 Q2 25-26.pdf | 3 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 Q2 25-26.pdf | 3 Apr 2026 |
| Form 1File: Form 1 .pdf | 29 Nov 2025 |
| Form 2File: Form 2 .pdf | 29 Nov 2025 |
| Form 3File: Form 3 .pdf | 29 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold inventry .pdf | 29 Nov 2025 |
| Withdrawal Update Form 1File: form 1 2025.pdf | 29 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 Fy 25.pdf | 29 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 .pdf | 29 Nov 2025 |
| Certificates of CA (Form 3)File: Quarter 1 (1).pdf | 19 Jun 2025 |
| Certificates of CA (Form 3)File: Quarter 2 (1).pdf | 19 Jun 2025 |
| Certificates of CA (Form 3)File: Quarter 3 (1).pdf | 19 Jun 2025 |
| Certificates of CA (Form 3)File: Quarter 4 (1).pdf | 19 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5 Fy 24-25.pdf | 19 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 - Quarter 1.pdf | 10 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 - Quarter 2.pdf | 10 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 - Quarter 3.pdf | 10 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 - Quarter 4.pdf | 10 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 fy 23-24.pdf | 8 May 2025 |
| Certificates of CA (Form 3)File: Form 3 Fy 24-25.pdf | 8 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Fy 23-24.pdf | 8 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Fy 24-25.pdf | 8 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Fy 23-24.pdf | 8 May 2025 |
| Architects certificate March 2025 | 29 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold unsold inventory March 2025.pdf | 29 Apr 2025 |
| Layout approvalFile: Plan 1 of 7 _ Layout.pdf | 21 Feb 2025 |
| Building plan approvalFile: Plan 2 of 7.pdf | 21 Feb 2025 |
| Building plan approvalFile: Plan 3 of 7.pdf | 21 Feb 2025 |
| Building plan approvalFile: Plan 4 of 7.pdf | 21 Feb 2025 |
| Building plan approvalFile: Plan 5 of 7.pdf | 21 Feb 2025 |
| Building plan approvalFile: Plan 6 of 7.pdf | 21 Feb 2025 |
| Copy of Layout Approval (in case of layout)File: Plan 1 of 7 _ Layout.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-07-2023.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-10-2023.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-01-2024.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-04-2024.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-07-2024.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-10-2024.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-01-2025.pdf | 21 Feb 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 21-02-2022.pdf | 21 Feb 2025 |
| Building Plan Approval (IOD)File: Plan 4 of 7.pdf | 21 Feb 2025 |
| Building Plan Approval (IOD)File: Plan 6 of 7.pdf | 21 Feb 2025 |
| Building Plan Approval (IOD)File: Plan 5 of 7.pdf | 21 Feb 2025 |
| Building Plan Approval (IOD)File: Plan 3 of 7.pdf | 21 Feb 2025 |
| Building Plan Approval (IOD)File: Plan 2 of 7.pdf | 21 Feb 2025 |
| Declaration about Commencement CertificateFile: Format D- Declaration to CC.pdf | 21 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Ending 2023.pdf | 21 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_ Ending 2024.pdf | 21 Feb 2025 |
| Declaration in FORM BFile: Form B - Affidavit Cum Declaration 11-02-2025.pdf | 11 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-07-2023.pdf | 11 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-10-2023.pdf | 11 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-01-2024.pdf | 11 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-04-2024.pdf | 11 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-07-2024.pdf | 11 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-10-2024.pdf | 11 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-01-2025.pdf | 11 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion-DownTown -Mhalunge 14-03-2024.pdf | 30 Apr 2024 |
| Declaration in FORM BFile: Form B.pdf | 10 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I.pdf | 10 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 A _ Annexure C.pdf | 10 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 10 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5.pdf | 10 Jun 2023 |
| Declaration about Commencement CertificateFile: Format D - Declaration of CC.pdf | 27 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From I - Architech Certificate.pdf | 27 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf | 27 Apr 2022 |
| CERSAI detailsFile: CERSAI Report Dated 27-04-2022 S No 6.pdf | 27 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Sold n Unsold.pdf | 27 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - FY 2018-19.pdf | 27 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 2019-20.pdf | 27 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020-21.pdf | 27 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Rera R.pdf | 10 Oct 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mhalunge RED.pdf | 10 Oct 2020 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| SHANTAI PARKP52100006559 | Thergaon, Pune | 42 | Aug 2017 | Ongoing | Dec 2022Registered original: Jan 2019 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 95 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DOWNTOWN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAHALUNGE13,700+ in Pune
Filed coordinates, straight-line distance. 235 registered projects within 2 km.
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: SAMARTTHA BUILDCON
SAMARTTHA BUILDCON has 1 registration on MahaRERA, including DOWNTOWN. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if DOWNTOWN is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DOWNTOWN?
The registered promoter entity is SAMARTTHA BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DOWNTOWN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DOWNTOWN?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DOWNTOWN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DOWNTOWN?
The professionals named in the filing: Architect: SWAPNIL P KSHIRSAGAR; Engineer: G A BHILARE; Engineer: Sagar Uttam Gaikwad; Chartered Accountant: O.R.Tonape & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DOWNTOWN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback