Registered No litigation declared Residential / Group Housing project

DOWNTOWN

By SAMARTTHA BUILDCON

RG-MH-76653 · RERA P52100018235 · Last updated on MahaRERA portal: 4 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 53 months
  • 4 extensions taken
  • Rs 0.09 crore secured on the land, in favour of Ganesh Balwadkar, Kedar Kulkarni and 1 more
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
16 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 90%
37 of 71Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 95 documents Report an error

DOWNTOWN is a Residential / Group Housing project by SAMARTTHA BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100018235 on 16 Oct 2018. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 53 months from the original filing. 34 of the 71 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • NameDOWNTOWN
  • TypeResidential / Group Housing
  • Location
    • OFF NATIONAL HIGHWAY NO 4 BYE PASS
    • MAHALUNGE
    • Mulshi
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018235
  • ReraGenie IDRG-MH-76653

Builder

  • NameSAMARTTHA BUILDCON
  • Entity typePartnership
  • PartnersSHIVRAJ ASHOK BALWADKAR, Mahesh Hiraman Barne
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredOct 2018First promiseApr 2022Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Oct 2018
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 11 Apr 2022)
  • Buildings2 building records
  • Documents filed95 files

Current status

48%34 of 71 units booked
77.1%Work done, per cost certificate

Figures as on 4 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ABNA5031031
CDNA5040040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 90%.

AB73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%
CD90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes75%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed53

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots53
Closed/Covered23
Open Space30
BuildingClosed/CoveredOpen SpaceTotal
AB221537
CD11516

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofGanesh Balwadkar, Kedar Kulkarni, Tanujay Properties LLP
Secured amountRs 0.09 crore
CERSAI search filedYes
Declared on4 Nov 2025
LandownerVillageDistrict
BABURAO CHINDHU MOHOLMahalungePune
YOGESH NARAYAN MOHOLMahalungePune
RANJIT SURESH MOHOLMahalungePune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI4028.0
Proposed, not sanctioned3,471 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBALEWADI
Estimated costRs 12.56 cr
Cost incurredRs 9.68 cr
Work done77.12%
BuildingWingEstimatedIncurred
CDNARs 5.95 crRs 5.65 cr
ABNARs 5.41 crRs 3.07 cr
-NARs 1.21 crRs 96.46 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSWAPNIL P KSHIRSAGAR
EngineerG A BHILARE
EngineerSagar Uttam Gaikwad
Chartered AccountantO.R.Tonape & Co
PartnerRole in project
SAMARTTHA BUILDCON-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011737Apr 2022 → Apr 2023

Reason as filed by the promoterThe Promoter could not complete the project due to the Covid 19 pandemic which arose all over the Country. The promoter has speeded up the work and will complete the work in an extended period. Requesting to grant us an extension.

EXT52100016678Apr 2022 → Apr 2024

Reason as filed by the promoterFirstly, due to Covid-19 pandemic the project work was stop for a longer period, and then due to change of road alignment by PMRDA the project got delayed, which took time to resolve. As of today the CD Building is 100% complete and we are in process of getting Part Completion Certificate. Further, the AB Building is about approx. 75% completed. Thus to complete the reaming work, we require an extension. Requesting to kindly permit us to extend the project registration.

EXT52100027422Apr 2022 → Jul 2025

Reason as filed by the promoterThe promoter has completed the major construction work and obtained a part occupancy certificate on 14/03/2024. Due to the Covid-19 pandemic, which affected the entire world, there were labor and material shortages that led to delays in the project's completion. The promoter is now seeking an extension to complete the construction work and requests your kind consideration for granting this extension.

EA03042620545Apr 2022 → Sep 2026

Reason as filed by the promoterThe project was delayed initially due to COVID-19. When work resumed subsequently, we encountered issues regarding finances and labor. The project was restarted once again after that; it is now 80 % complete, and an extension period will be required to the finalize the remaining work.

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC005000000117029Vishal V TendulkarSamarttha Buildcon23/05/2022
CC005000000310479Sandeep ChavanMahesh Hiraman Barne, Shivraj Ashok Balwadkar25/02/2024
CC12401126Avinash Dilipbhai TondleSAMARTTHA BUILDCON14/12/2024
CC12401127Ajinkya Jaysing JadhavSAMARTTHA BUILDCON14/12/2024
CC12401142Shalaka Harshal DholeSAMARTTHA BUILDCON16/12/2024
CC12401131Debarati Rajendra ChatterjeeSAMARTTHA BUILDCON14/12/2024
CC12501332Aasawari Bhairu YejareSAMARTTHA BUILDCON22/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Apr 2024

Documents filed95

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q4 25-26.pdf4 Jul 2026
Withdrawal Update Form 2File: Form 2 Q4.pdf4 Jul 2026
Withdrawal Update Form 3File: form 3 Q4.pdf4 Jul 2026
Withdrawal Update Form 1File: Form 1 Q3 25-26.pdf3 Jul 2026
Withdrawal Update Form 2File: FORM 2 Q3 25-26.pdf3 Jul 2026
Withdrawal Update Form 3File: FORM 3 Q3 25-26.pdf3 Jul 2026
Form 5 (FY 2025-2026)File: Form 5 25-26.pdf3 Jun 2026
Withdrawal Update Form 1File: FORM 1 Q2 25-26.pdf3 Apr 2026
Withdrawal Update Form 2File: FORM 2 Q2 25-26.pdf3 Apr 2026
Withdrawal Update Form 3File: FORM 3 Q2 25-26.pdf3 Apr 2026
Form 1File: Form 1 .pdf29 Nov 2025
Form 2File: Form 2 .pdf29 Nov 2025
Form 3File: Form 3 .pdf29 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold inventry .pdf29 Nov 2025
Withdrawal Update Form 1File: form 1 2025.pdf29 Nov 2025
Withdrawal Update Form 2File: Form 2 Fy 25.pdf29 Nov 2025
Withdrawal Update Form 3File: Form 3 .pdf29 Nov 2025
Certificates of CA (Form 3)File: Quarter 1 (1).pdf19 Jun 2025
Certificates of CA (Form 3)File: Quarter 2 (1).pdf19 Jun 2025
Certificates of CA (Form 3)File: Quarter 3 (1).pdf19 Jun 2025
Certificates of CA (Form 3)File: Quarter 4 (1).pdf19 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5 Fy 24-25.pdf19 Jun 2025
Certificates of CA (Form 3)File: Form 3 - Quarter 1.pdf10 Jun 2025
Certificates of CA (Form 3)File: Form 3 - Quarter 2.pdf10 Jun 2025
Certificates of CA (Form 3)File: Form 3 - Quarter 3.pdf10 Jun 2025
Certificates of CA (Form 3)File: Form 3 - Quarter 4.pdf10 Jun 2025
Certificates of CA (Form 3)File: Form 3 fy 23-24.pdf8 May 2025
Certificates of CA (Form 3)File: Form 3 Fy 24-25.pdf8 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Fy 23-24.pdf8 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Fy 24-25.pdf8 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Fy 23-24.pdf8 May 2025
Architects certificate March 202529 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold unsold inventory March 2025.pdf29 Apr 2025
Layout approvalFile: Plan 1 of 7 _ Layout.pdf21 Feb 2025
Building plan approvalFile: Plan 2 of 7.pdf21 Feb 2025
Building plan approvalFile: Plan 3 of 7.pdf21 Feb 2025
Building plan approvalFile: Plan 4 of 7.pdf21 Feb 2025
Building plan approvalFile: Plan 5 of 7.pdf21 Feb 2025
Building plan approvalFile: Plan 6 of 7.pdf21 Feb 2025
Copy of Layout Approval (in case of layout)File: Plan 1 of 7 _ Layout.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-07-2023.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-10-2023.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-01-2024.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-04-2024.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-07-2024.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-10-2024.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE DT 01-01-2025.pdf21 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 21-02-2022.pdf21 Feb 2025
Building Plan Approval (IOD)File: Plan 4 of 7.pdf21 Feb 2025
Building Plan Approval (IOD)File: Plan 6 of 7.pdf21 Feb 2025
Building Plan Approval (IOD)File: Plan 5 of 7.pdf21 Feb 2025
Building Plan Approval (IOD)File: Plan 3 of 7.pdf21 Feb 2025
Building Plan Approval (IOD)File: Plan 2 of 7.pdf21 Feb 2025
Declaration about Commencement CertificateFile: Format D- Declaration to CC.pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Ending 2023.pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_ Ending 2024.pdf21 Feb 2025
Declaration in FORM BFile: Form B - Affidavit Cum Declaration 11-02-2025.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-07-2023.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-10-2023.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-01-2024.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-04-2024.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-07-2024.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-10-2024.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory 01-01-2025.pdf11 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion-DownTown -Mhalunge 14-03-2024.pdf30 Apr 2024
Declaration in FORM BFile: Form B.pdf10 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I.pdf10 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 A _ Annexure C.pdf10 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf10 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5.pdf10 Jun 2023
Declaration about Commencement CertificateFile: Format D - Declaration of CC.pdf27 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From I - Architech Certificate.pdf27 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf27 Apr 2022
CERSAI detailsFile: CERSAI Report Dated 27-04-2022 S No 6.pdf27 Apr 2022
Disclosure of sold/ booked inventoryFile: Sold n Unsold.pdf27 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - FY 2018-19.pdf27 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 2019-20.pdf27 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020-21.pdf27 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Rera R.pdf10 Oct 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mhalunge RED.pdf10 Oct 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SHANTAI PARKP52100006559Thergaon, Pune42Aug 2017OngoingDec 2022Registered original: Jan 2019Not delivered

How this compares with Pune

48%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 53 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DOWNTOWN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAHALUNGE13,700+ in Pune

2 kmDOWNTOWNCompleted 101Lapsed / revoked 43Other 91Dot size: filed unitsN

Filed coordinates, straight-line distance. 235 registered projects within 2 km.

Builder: SAMARTTHA BUILDCON

SAMARTTHA BUILDCON has 1 registration on MahaRERA, including DOWNTOWN. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if DOWNTOWN is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DOWNTOWN?

The registered promoter entity is SAMARTTHA BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DOWNTOWN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DOWNTOWN?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DOWNTOWN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DOWNTOWN?

The professionals named in the filing: Architect: SWAPNIL P KSHIRSAGAR; Engineer: G A BHILARE; Engineer: Sagar Uttam Gaikwad; Chartered Accountant: O.R.Tonape & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DOWNTOWN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DOWNTOWN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DOWNTOWN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.