Home / Browse projects / Pune, Maharashtra / SHANTAI PARK

Registration lapsed No litigation declared Residential / Group Housing project

SHANTAI PARK

By SAMARTTHA LANDMARK

RG-MH-21079 · RERA P52100006559 · Last updated on MahaRERA portal: 25 Jul 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 47 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 75%
5Complaints at MahaRERAon this registration
Jump to the 40 documents Report an error

SHANTAI PARK is a Residential / Group Housing project by SAMARTTHA LANDMARK in Pune, Maharashtra, registered with MahaRERA as P52100006559 on 14 Aug 2017. Possession was promised by 31 Dec 2022 and is now 46 months past that date. The completion date has moved by 47 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameSHANTAI PARK
  • TypeResidential / Group Housing
  • Location
    • Thergaon
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100006559
  • ReraGenie IDRG-MH-21079

Builder

  • NameSAMARTTHA LANDMARK
  • Entity typePartnership
  • PartnersMAHESH HIRAMAN BARNE, NILESH HIRAMAN BARNE

Key dates

46 months past promisethis monthRegisteredAug 2017First promiseJan 2019Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Aug 2017
  • Promised completion31 Dec 2022
  • Revised completionRevised to 31 Dec 2022 (originally 30 Jan 2019)
  • Buildings1 building record
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHANTAI PARKNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.

SHANTAI PARK: 68% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 25 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,643 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
VIJAY BABURAO BARNE AND OTHERSThergaonPune

Approvals and building plan

Permissible FSI2557.27
Proposed, not sanctioned2,557 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHERGAON PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIMAYA ASSOCIATES
EngineerG A BHILARE CONSULTANT
PartnerRole in project
SAMARTTHA LANDMARK-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100008652Jan 2019 → Dec 2021

Reason as filed by the promoterThe construction work of the existing buildings has been completed and some of the amenities/finishing work are remaining which we as a Promoter undertakes to expedite. We, the Promoter desire to utilize and consume FAR/FSI and obtain permissible TDR and apply for revision of the sanction plan to the competent authority, for which the Allottees of the project have given their consent to make necessary changes/alteration or addition in the sanctioned plans. Time is required for receiving the revised plan and to complete the revised construction work, which will then enable us to apply for a ful

EXT52100012192Jan 2019 → Dec 2022

Reason as filed by the promoterdue to revise sanction plan

EXT52100001378Jan 2019 → Jan 2020

Reason as filed by the promoter2There was procedural tussle regarding plot and that is because of change of development plan by Development Authority which leads cutting of some part of our plot for City Infrastructure Development work . However we had arrived at satisfactory solution with land owners who had offered and already settled plot dispute, hence we are now already overcome this hindrance and development activity is now started in full swing. One of our Customer ‘ Mrs. Preeti Duggad ‘ even after making her aware about facts mentioned in above point no. 2 had moved to RERA and filed case against us at ‘ Reconciliat

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC005000000011498SEEMA PRITESH DUGADSAMARTTHA LANDMARK05/05/2018
CC005000000033551Mr.Pritesh Prakash DugadSamarttha Landmark, a registered partnership firm through its partners Mr.Mahesh Hiraman Barne20/10/2019
CC005000000033554Mrs.Seema Pritesh DugadSamarttha Landmark a registred partnership firm through its partners20/10/2019
CC005000000095729MR PRITESH PRAKASH DUGADsamarttha landmark a regi partnership firm though its partners01/07/2021
CC005000000023311UMESH KASHINATH JOSHISAMARTTHA LANDMARK17/01/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed40

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CERSAI detailsFile: CERSAI_Search_Report_200242990548_For_Asset_Based_Search_25_07_2022_12_27_26_628.pdf25 Jul 2022
Layout approvalFile: 1_compressed.pdf2 Jul 2022
Building plan approvalFile: 2_compressed.pdf2 Jul 2022
Building plan approvalFile: 3_compressed.pdf2 Jul 2022
Building plan approvalFile: 4_compressed.pdf2 Jul 2022
Copy of Layout Approval (in case of layout)File: 1_compressed.pdf2 Jul 2022
Building Plan Approval (IOD)File: 2_compressed.pdf2 Jul 2022
Building Plan Approval (IOD)File: 3_compressed.pdf2 Jul 2022
Building Plan Approval (IOD)File: 4_compressed.pdf2 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: 0_compressed.pdf2 Jul 2022
Declaration about Commencement CertificateFile: Format D (4).pdf2 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: shantai park architect certificate_compressed.pdf2 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Shantai Park.pdf2 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 1 Form 2A.pdf2 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold (2).pdf2 Jul 2022
Certificates of CA (Form 3)File: Form 3_compressed (2).pdf2 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Samarttha Landmark_march 2019.pdf2 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Samarttha Landmark_march 2020.pdf2 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Samarttha Landmark_march 2021.pdf2 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch dec 19.pdf17 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg dec 19_compressed.pdf17 Dec 2019
Certificates of CA (Form 3)File: ca 19_compressed.pdf17 Dec 2019
Certificates of CA (Form 3)File: CA CERT.pdf17 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf16 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certiifcate_compressed.pdf16 Jul 2019
Form 2AFile: QULITY ENGINEERS CERTIFICARE 22-01-2019 PDF.pdf22 Jan 2019
Certificates of CA (Form 5)File: FORM 5.pdf22 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMICAMENT 15-compressed.pdf9 Mar 2018
Building plan approvalFile: LAYOUT.pdf31 Jul 2017
Layout approvalFile: LAYOUT.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf31 Jul 2017
Building Plan Approval (IOD)File: LAYOUT.pdf31 Jul 2017
Declaration in FORM BFile: FORM B 180.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARC LETTER.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA.pdf31 Jul 2017
PAN CardFile: Company Pan card.pdf30 Jul 2017
Copy of the legal title reportFile: TITLE SEARCH.pdf30 Jul 2017
Details of encumbrancesFile: Self Declaration.pdf30 Jul 2017
Proforma of Allotment letterFile: Agreement - Shantai Park.pdf30 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 47 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHANTAI PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thergaon13,700+ in Pune

2 kmSHANTAI PARKCompleted 21Lapsed / revoked 14Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 36 registered projects within 2 km.

Builder: SAMARTTHA LANDMARK

SAMARTTHA LANDMARK has 1 registration on MahaRERA, including SHANTAI PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SHANTAI PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHANTAI PARK is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHANTAI PARK?

The registered promoter entity is SAMARTTHA LANDMARK, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHANTAI PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHANTAI PARK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHANTAI PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHANTAI PARK?

The professionals named in the filing: Architect: KIMAYA ASSOCIATES; Engineer: G A BHILARE CONSULTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHANTAI PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHANTAI PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHANTAI PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.