Home / Browse projects / Pune, Maharashtra / SHANTAI PARK
SHANTAI PARK
RG-MH-21079 · RERA P52100006559 · Last updated on MahaRERA portal: 25 Jul 2022
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 46 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 47 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHANTAI PARK is a Residential / Group Housing project by SAMARTTHA LANDMARK in Pune, Maharashtra, registered with MahaRERA as P52100006559 on 14 Aug 2017. Possession was promised by 31 Dec 2022 and is now 46 months past that date. The completion date has moved by 47 months from the original filing. 5 complaints are on record with the regulator.
At a glance
Project
- NameSHANTAI PARK
- TypeResidential / Group Housing
- Location
- Thergaon
- Mulshi
- Pune
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100006559
- ReraGenie IDRG-MH-21079
Builder
- NameSAMARTTHA LANDMARK
- Entity typePartnership
- PartnersMAHESH HIRAMAN BARNE, NILESH HIRAMAN BARNE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion31 Dec 2022
- Revised completionRevised to 31 Dec 2022 (originally 30 Jan 2019)
- Buildings1 building record
- Documents filed40 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHANTAI PARK | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.
SHANTAI PARK: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Progress on shared amenities15
As on 25 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VIJAY BABURAO BARNE AND OTHERS | Thergaon | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KIMAYA ASSOCIATES |
| Engineer | G A BHILARE CONSULTANT |
| Partner | Role in project |
|---|---|
| SAMARTTHA LANDMARK | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe construction work of the existing buildings has been completed and some of the amenities/finishing work are remaining which we as a Promoter undertakes to expedite. We, the Promoter desire to utilize and consume FAR/FSI and obtain permissible TDR and apply for revision of the sanction plan to the competent authority, for which the Allottees of the project have given their consent to make necessary changes/alteration or addition in the sanctioned plans. Time is required for receiving the revised plan and to complete the revised construction work, which will then enable us to apply for a ful
Reason as filed by the promoterdue to revise sanction plan
Reason as filed by the promoter2There was procedural tussle regarding plot and that is because of change of development plan by Development Authority which leads cutting of some part of our plot for City Infrastructure Development work . However we had arrived at satisfactory solution with land owners who had offered and already settled plot dispute, hence we are now already overcome this hindrance and development activity is now started in full swing. One of our Customer ‘ Mrs. Preeti Duggad ‘ even after making her aware about facts mentioned in above point no. 2 had moved to RERA and filed case against us at ‘ Reconciliat
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000011498 | SEEMA PRITESH DUGAD | SAMARTTHA LANDMARK | 05/05/2018 |
| CC005000000033551 | Mr.Pritesh Prakash Dugad | Samarttha Landmark, a registered partnership firm through its partners Mr.Mahesh Hiraman Barne | 20/10/2019 |
| CC005000000033554 | Mrs.Seema Pritesh Dugad | Samarttha Landmark a registred partnership firm through its partners | 20/10/2019 |
| CC005000000095729 | MR PRITESH PRAKASH DUGAD | samarttha landmark a regi partnership firm though its partners | 01/07/2021 |
| CC005000000023311 | UMESH KASHINATH JOSHI | SAMARTTHA LANDMARK | 17/01/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed40
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CERSAI detailsFile: CERSAI_Search_Report_200242990548_For_Asset_Based_Search_25_07_2022_12_27_26_628.pdf | 25 Jul 2022 |
| Layout approvalFile: 1_compressed.pdf | 2 Jul 2022 |
| Building plan approvalFile: 2_compressed.pdf | 2 Jul 2022 |
| Building plan approvalFile: 3_compressed.pdf | 2 Jul 2022 |
| Building plan approvalFile: 4_compressed.pdf | 2 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: 1_compressed.pdf | 2 Jul 2022 |
| Building Plan Approval (IOD)File: 2_compressed.pdf | 2 Jul 2022 |
| Building Plan Approval (IOD)File: 3_compressed.pdf | 2 Jul 2022 |
| Building Plan Approval (IOD)File: 4_compressed.pdf | 2 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 0_compressed.pdf | 2 Jul 2022 |
| Declaration about Commencement CertificateFile: Format D (4).pdf | 2 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: shantai park architect certificate_compressed.pdf | 2 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Shantai Park.pdf | 2 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 1 Form 2A.pdf | 2 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold (2).pdf | 2 Jul 2022 |
| Certificates of CA (Form 3)File: Form 3_compressed (2).pdf | 2 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Samarttha Landmark_march 2019.pdf | 2 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Samarttha Landmark_march 2020.pdf | 2 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Samarttha Landmark_march 2021.pdf | 2 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch dec 19.pdf | 17 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg dec 19_compressed.pdf | 17 Dec 2019 |
| Certificates of CA (Form 3)File: ca 19_compressed.pdf | 17 Dec 2019 |
| Certificates of CA (Form 3)File: CA CERT.pdf | 17 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf | 16 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certiifcate_compressed.pdf | 16 Jul 2019 |
| Form 2AFile: QULITY ENGINEERS CERTIFICARE 22-01-2019 PDF.pdf | 22 Jan 2019 |
| Certificates of CA (Form 5)File: FORM 5.pdf | 22 Jan 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMICAMENT 15-compressed.pdf | 9 Mar 2018 |
| Building plan approvalFile: LAYOUT.pdf | 31 Jul 2017 |
| Layout approvalFile: LAYOUT.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: LAYOUT.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: FORM B 180.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARC LETTER.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA.pdf | 31 Jul 2017 |
| PAN CardFile: Company Pan card.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: TITLE SEARCH.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: Self Declaration.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Agreement - Shantai Park.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 40 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SHANTAI PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Thergaon13,700+ in Pune
Filed coordinates, straight-line distance. 36 registered projects within 2 km.
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: SAMARTTHA LANDMARK
SAMARTTHA LANDMARK has 1 registration on MahaRERA, including SHANTAI PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that SHANTAI PARK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHANTAI PARK is delayed beyond 31 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHANTAI PARK?
The registered promoter entity is SAMARTTHA LANDMARK, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHANTAI PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHANTAI PARK?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHANTAI PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHANTAI PARK?
The professionals named in the filing: Architect: KIMAYA ASSOCIATES; Engineer: G A BHILARE CONSULTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHANTAI PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback