Home / Browse projects / Pune, Maharashtra / DNK CAPITAL

Registration lapsed No litigation declared Commercial project

DNK CAPITAL

By D N K CORP

RG-MH-17523 · RERA P52100030549 · Last updated on MahaRERA portal: 5 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
8 of 11Construction stages donefurthest along: Internal walls, 90%
57 of 72Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

DNK CAPITAL is a Commercial project by D N K CORP in Pune, Maharashtra, registered with MahaRERA as P52100030549 on 30 Aug 2021. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 24 months from the original filing. 15 of the 72 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameDNK CAPITAL
  • TypeCommercial
  • Location
    • PUNE
    • kondhwa BK
    • Haveli
    • 411048
  • Pincode411048
  • RERA no.P52100030549
  • ReraGenie IDRG-MH-17523

Builder

  • NameD N K CORP
  • Entity typePartnership
  • PartnersRUSHABH RAVINDRA DUGAD, SUNIL CHANDMAL DUGAD, VIPUL VITTHAL GOLECHA, ALKADEVI AVINASH KOTHARI, JYOTI AKSHAY KOTHARI, ASHOKLAL ZUMBERLAL NAHAR, NEHA CHETAN NAHAR, SUSHILABAI ASHOKLAL NAHAR, JAYESH KANTILAL PHULPHAGAR, GUARAV PRAMOD DUGAD

Key dates

7 months past promisethis monthRegisteredAug 2021First promiseMar 2024Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on30 Aug 2021
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 1 Mar 2024)
  • Buildings1 building record
  • Documents filed93 files

Current status

21%15 of 72 units booked
100.0%Work done, per cost certificate

Figures as on 5 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DNK CAPITALNA8807272

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

DNK CAPITAL: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 5 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed190

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots190
Open Space190

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,600 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPune Muncipal Corporation
Permissible FSI6180.0
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSN 571, CRYSTAL ROOM, KONDHWA ROAD, KENJALE NAGAR, BIBWEWADI, PUNE 411037
Estimated costRs 20.31 cr
Cost incurredRs 20.31 cr
Work done100.0%
BuildingWingEstimatedIncurred
DNK CAPITALNARs 15.23 crRs 15.23 cr
-NARs 5.08 crRs 5.08 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIKAS DHERE
EngineerDhirajkumar Chordiya Chordiya
Chartered AccountantCA SUDEEP CHHALLANI
Chartered AccountantA N J K & Co LLP
Chartered AccountantANJK & CO LLP
PartnerRole in project
D N K CORP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018170Mar 2024 → Mar 2025

Reason as filed by the promoterWe apply for extension of the following project DNK Capital registered with the regulatory authority vide project registration certificate bearing no. P52100030549 which expired on 01/03/2024. We request you to grant extension of RERA Registration for a further period of 12 months i.e. upto 01/03/2025.

EA13062501587Mar 2024 → Mar 2026

Reason as filed by the promoterThe Project has been affected by the shortage of skilled labour force due to the recent festive seasons. Shortage of raw material has also resulted into the delay of the construction of stack parking. We would like to mention that we have received Part Occupancy Certificate dated 17/12/2024 for all floors and units except unit no. 801 to unit no. 809, and are also expecting to receive Full Occupancy Certificate before the expiry of applied extended completion date.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate Sep 25.pdf5 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Sep 25.pdf5 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Sep 25.pdf5 Jan 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate - June 2025.pdf30 Aug 2025
Withdrawal Update Form 2File: Form 2 Engineer Certifcate - June 2025 - Signed.pdf30 Aug 2025
Withdrawal Update Form 3File: Form 3 CA Certificate - June 2025 - Signed.pdf30 Aug 2025
Form 5 (FY 2023-2024)File: CA Form 5_FY 2023-24_Signed.pdf26 Jun 2025
Form 2A (FY 2023-2024)File: Form 2A - Signed.pdf24 Jun 2025
Form 1File: Form 1 Architect Certificate - March 2025.pdf23 Jun 2025
Form 2File: Form 2 Engineer Certificate - March 2025.pdf23 Jun 2025
Form 3File: Form 3 CA Certificate - March 2025 - Signed.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory March 2025.pdf23 Jun 2025
Self-declaration of Quarterly ProgressFile: RERA self declaration of QPR.pdf23 Jun 2025
Declaration in FORM BFile: Form B -Declaration by promoter.pdf19 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf16 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf4 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf4 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf4 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate September 2023 Signed_11zon.pdf4 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA Form 5.pdf21 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf20 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf6 May 2023
Layout approvalFile: Layout Approval.pdf5 May 2023
Building plan approvalFile: Building Plan 1.pdf5 May 2023
Building plan approvalFile: Building Plan 1.pdf5 May 2023
Building plan approvalFile: Building Plan 2.pdf5 May 2023
Building plan approvalFile: Building Plan 4.pdf5 May 2023
Building plan approvalFile: Building Plan 5.pdf5 May 2023
Building plan approvalFile: Building Plan 6.pdf5 May 2023
Building plan approvalFile: Building Plan 6.pdf5 May 2023
Building plan approvalFile: Building Plan 7.pdf5 May 2023
Building plan approvalFile: Building Plan 8.pdf5 May 2023
Building plan approvalFile: Building Plan 9.pdf5 May 2023
Building plan approvalFile: Building Plan 10.pdf5 May 2023
Building plan approvalFile: Building Plan 11.pdf5 May 2023
Building plan approvalFile: Building Plan 12.pdf5 May 2023
Building plan approvalFile: Building Plan 13.pdf5 May 2023
Building plan approvalFile: Building Plan 14.pdf5 May 2023
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 1.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 1.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 4.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 5.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 6.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 6.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 7.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 8.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 9.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 10.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 11.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 12.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 13.pdf5 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 14.pdf5 May 2023
Commencement Certificates / NA Order for plotted developmentFile: CC_compressed.pdf5 May 2023
Declaration about Commencement CertificateFile: CC_compressed.pdf5 May 2023
Declaration about Commencement CertificateFile: CC Declaration Signed.pdf5 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf5 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf5 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Signed.pdf5 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Signed_compressed.pdf5 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE Q3 2022.pdf30 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Q3 2022.pdf30 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Sep2021.pdf20 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate 30th Sep 2021.PDF20 Oct 2021
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf20 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Q2 - 2022 - DNK C.pdf20 Oct 2021
Copy of the legal title reportFile: legal title report 1.pdf21 Aug 2021
Copy of the legal title reportFile: legal title report 2.pdf21 Aug 2021
Proforma of Allotment letterFile: dnk corpo rera draft 18821.pdf21 Aug 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CE.PDF16 Jul 2021
Building plan approvalFile: dnk.pdf7 Jun 2021
Building plan approvalFile: dnk 2.pdf7 Jun 2021
Building plan approvalFile: dnk 3.pdf7 Jun 2021
Building plan approvalFile: dnk 4.pdf7 Jun 2021
Layout approvalFile: dnk.pdf7 Jun 2021
Copy of Layout Approval (in case of layout)File: dnk.pdf7 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: dnk.pdf7 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: dnk 2.pdf7 Jun 2021

How this compares with Pune

21%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DNK CAPITAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

Builder: D N K CORP

D N K CORP has 1 registration on MahaRERA, including DNK CAPITAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that DNK CAPITAL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DNK CAPITAL is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DNK CAPITAL?

The registered promoter entity is D N K CORP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DNK CAPITAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DNK CAPITAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DNK CAPITAL?

The professionals named in the filing: Architect: VIKAS DHERE; Engineer: Dhirajkumar Chordiya Chordiya; Chartered Accountant: CA SUDEEP CHHALLANI; Chartered Accountant: A N J K & Co LLP; Chartered Accountant: ANJK & CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DNK CAPITAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DNK CAPITAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DNK CAPITAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.