ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / Disha Swarajya Sinhagad

Registered No litigation declared Residential / Group Housing project

Disha Swarajya Sinhagad

By APA Combine LLP

RG-MH-23487 · RERA P51500078799 · Last updated on MahaRERA portal: 30 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

Disha Swarajya Sinhagad is a Residential / Group Housing project by APA Combine LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500078799 on 13 Jan 2025. Possession is promised by 31 Dec 2027.

At a glance

Project

  • NameDisha Swarajya Sinhagad
  • TypeResidential / Group Housing
  • Location
    • Garkheda
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • RERA no.P51500078799
  • ReraGenie IDRG-MH-23487

Builder

  • NameAPA Combine LLP
  • Entity typePartnership
  • PartnersAjinkya Naresh Sikchi, Rajkumar Manakchand Agrawal, Kavita Naresh Sikchi, Ajay Kotgire, Pratik Agrawal
  • Other registrations3 more →

Key dates

this monthRegisteredJan 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Jan 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed63 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Disha Swarajya SinhagadNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Disha Swarajya Sinhagad: 27% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,769 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
Aditya Arvind DeshmukhAurangabad (M Corp.)Aurangabad
Prabhakar Namdeorao GaikwadAurangabad (M Corp.)Aurangabad
Satish Uttamrao WaghchaureAurangabad (M Corp.)Aurangabad
Vishnu Nivruttirao KavhaleAurangabad (M Corp.)Aurangabad
Vasudha Chandrashekhar BhosaleAurangabad (M Corp.)Aurangabad
Sujata Satish PatilAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI5731.31
Proposed, not sanctioned5,231 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChikalthana, Chhatrapati Sambhajinagar

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerSushilkumar Arvind Kavishwar
Chartered AccountantLathi and Tapdiya
PartnerRole in project
APA Combine LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form -2A Sinhagad_0001.pdf30 Jun 2026
Form 1File: Form -1 Shihgad_0001.pdf6 May 2026
Form 2File: Form-2 APA Combine llp-Disha Swarajya Sinhagad_0001.pdf6 May 2026
Form 3File: Form-3 APA Combine llp-Disha Swarajya Sinhagad.pdf6 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sihgad_0001.pdf6 May 2026
OthersFile: Form -2 A sihgad_0001.pdf6 May 2026
Form 5 (FY 2024-2025)File: Form-5 P51500078799_0001.pdf6 Apr 2026
Form 1File: Form 1 Sinhagad_0001_0001.pdf24 Mar 2026
Form 2File: Form 2 Sinhagad_0001.pdf24 Mar 2026
Form 3File: Form-3 Sinhagad Dt-31-03-2025_0001.pdf24 Mar 2026
Disclosure of Sold and Booked InventoryFile: Discloser Shihngad_0001.pdf24 Mar 2026
OthersFile: Form 2A Sinhagad_0001_0001.pdf24 Mar 2026
Form 1File: Form-1 Dt-19-07-2025_0001.pdf24 Mar 2026
Form 2File: Form-2 Dt-30-06-2025_0001.pdf24 Mar 2026
Form 3File: Form-3 Sinhagad Dt-30-06-2025_0001.pdf24 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Sold-Book Dt-30-06-2025_0001.pdf24 Mar 2026
OthersFile: Form-2A Dt-30-06-2025_0001.pdf24 Mar 2026
Form 1File: Sinhagad architect certificate.pdf24 Mar 2026
Form 2File: Sinhagad engineer certificate.pdf24 Mar 2026
Form 3File: Form-3 Sinhagad Dt-30-09-2025_0001.pdf24 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sinhagad disclosure.pdf24 Mar 2026
OthersFile: Sinhagad quality assurance.pdf24 Mar 2026
Form 1File: sinhagad architect certificate dec 25.pdf24 Mar 2026
Form 2File: sinhagad form 2 dec 25.pdf24 Mar 2026
Form 3File: Form-3 Sinhagad Dt-31-12-2025_0001.pdf24 Mar 2026
Disclosure of Sold and Booked InventoryFile: sinhagad disclosure dec 25.pdf24 Mar 2026
OthersFile: sinhagad form no 2a dec 25.pdf24 Mar 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sinhagad_0001_0001.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sinhagad_0001.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discloser Shihngad_0001.pdf3 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Sinhagad_0001_0001.pdf3 May 2025
Copy of the legal title reportFile: UPDATED RERA Title Search Report- Sinhagad (1).pdf18 Dec 2024
Declaration about Commencement CertificateFile: sinhagad declaration.pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_0001.pdf11 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A (2 files merged).pdf11 Dec 2024
Proforma of Agreement for saleFile: ASF.pdf11 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: SBI APA Combine Format B_0001 (2 files merged).pdf11 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: SCAN03122024.pdf3 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure _rajkumar m agrawal.pdf3 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure_kavita naresh sikchi.pdf3 Dec 2024
Other - TechnicalFile: annexure a.pdf16 Nov 2024
Other - TechnicalFile: Gmail - 59 01 SANTION BP POROPSAL 06112024-1.pdf16 Nov 2024
Other - TechnicalFile: DocScanner 22-Oct-2024 2-07 pm-1.pdf16 Nov 2024
Proforma of Allotment letterFile: allotment letter.pdf15 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch certificate.pdf15 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE.pdf15 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Pratik Agrawal_0001.pdf15 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: disclosure.pdf15 Nov 2024
Layout approvalFile: 20240819_162354 - converted.pdf13 Nov 2024
Building plan approvalFile: PLANS SINHAGAD.pdf13 Nov 2024
Details of encumbrances concerned to FinanceFile: Letter of Encumberance APA Combine LLP_0001.pdf13 Nov 2024
Details of encumbrances concerned to FinanceFile: No-Encumberance Concerning Legal_0001.pdf13 Nov 2024
Copy of Layout Approval (in case of layout)File: 20240819_162354 - converted.pdf13 Nov 2024
Declaration in FORM BFile: Form B-Ajay Kotgire_0001.pdf13 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: 28092024165726.pdf13 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: PLANS SINHAGAD.pdf13 Nov 2024
CERSAI detailsFile: Declaration APA Combine LLp_0001.pdf13 Nov 2024
Deviation Report with respect to Allotment letterFile: TO Whom So Ever IT May Concern_0001.pdf13 Nov 2024
Details of encumbrances concerned to LegalFile: Letter of Encumberance APA Combine LLP_0001.pdf13 Nov 2024
Details of encumbrances concerned to LegalFile: No-Encumberance Concerning Legal_0001.pdf13 Nov 2024
Deviation Report with respect to model copy of AgreementFile: TO Whom So Ever IT May Concern APA_0001.pdf13 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Ajay Kotgire_0001.pdf13 Nov 2024
PAN CardFile: 1 PAN Card.pdf12 Nov 2024

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Disha Swarajya Sinhagad on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Garkheda1,400+ in Aurangabad

Builder: APA Combine LLP

APA Combine LLP has 4 registrations on MahaRERA, including Disha Swarajya Shivneri and Disha Swarajya Pratapgad A and B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Disha Swarajya Sinhagad is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Disha Swarajya Sinhagad?

The registered promoter entity is APA Combine LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Disha Swarajya Sinhagad?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Disha Swarajya Sinhagad?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Disha Swarajya Sinhagad?

The professionals named in the filing: Engineer: Sushilkumar Arvind Kavishwar; Chartered Accountant: Lathi and Tapdiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Disha Swarajya Sinhagad?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Disha Swarajya Sinhagad. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Disha Swarajya Sinhagad to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.