Home / Browse projects / Thane, Maharashtra / Dipti Skycity Bldg No. 7

Registered No litigation declared Residential / Group Housing project

Dipti Skycity Bldg No. 7

By Dipti Home Makers Pvt Ltd

RG-MH-37022 · RERA P51700048627 · Last updated on MahaRERA portal: 20 Oct 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • No extension sought by the promoter; the date moved only under MahaRERA's automatic 4-month extension
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 4 months by MahaRERA order
5 of 11Construction stages donefurthest along: Staircases, 85%
102 of 132Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 113 documents Report an error

Dipti Skycity Bldg No. 7 is a Residential / Group Housing project by Dipti Home Makers Pvt Ltd in Thane, Maharashtra, registered with MahaRERA as P51700048627 on 10 Jan 2023. Possession is promised by 30 Apr 2027. The completion date has moved by 4 months under MahaRERA's automatic 4-month extension for the West Asia conflict, which the promoter did not apply for. 30 of the 132 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameDipti Skycity Bldg No. 7
  • TypeResidential / Group Housing
  • Location
    • Survey No. 54/3B
    • 54/3D
    • 57/1 of village pale
    • Ambernath East District thane
    • Ambarnath (R)
    • Ambarnath
    • Thane
    • 421501
  • Pincode421501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700048627
  • ReraGenie IDRG-MH-37022

Builder

  • NameDipti Home Makers Pvt Ltd
  • Entity typeCompany
  • CINU70100MH1995PTC095189
  • GSTIN27AAACD3545L1ZK
  • Managing DirectorRamesh Shah
  • DirectorsChandulal Kalyanji Shah, Kantilal Kalyanji Shah
  • Other registrations7 more →
  • Completed3 of 8
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredJan 2023First promiseDec 2026Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Jan 2023
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2026)
  • Buildings1 building record
  • Documents filed113 files

Current status

23%30 of 132 units booked
94.5%Work done, per cost certificate

Figures as on 20 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dipti Sky City Building No 7NA13121320132

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 85%.

Dipti Sky City Building No 7: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 20 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes80%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed63

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots63
Closed/Covered1
Open Space62

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,965 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Jul 2026
LandownerVillageDistrict
Dipti Home Makers Pvt LtdMumbai CityMumbai City
Chandulal K Shah-Mumbai City

Approvals and building plan

Sanctioning authorityAmbernath Municipal Council
Permissible FSI25362.78
Proposed, not sanctioned10,363 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMittal court, B wing, ground floor, nariman point, mumbai - 400021
Estimated costRs 26.24 cr
Cost incurredRs 24.80 cr
Work done94.54%
BuildingWingEstimatedIncurred
Dipti Sky City Building No 7NARs 24.01 crRs 23.65 cr
-NARs 2.23 crRs 1.15 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJitendra Patel Samarthya Engineers K Patel
ArchitectPramod Kamble
EngineerMANZUR HUSAIN HEBBALLI
EngineerAtul Kudtarkar and Associates
EngineerAtul Kudtarkar And Associates Pvt. Ltd.
Chartered AccountantDixit Dattatray and Associates D Dixit
Chartered AccountantMohandas and Co M Shetty
Chartered AccountantAnita Choudhari
Chartered AccountantAshish C Halwai
PartnerRole in project
Dipti Home Makers Pvt Ltd-

Extensions1

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Dec 2026 → Apr 2027

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed113

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Skycity Sep 2026.pdf20 Oct 2026
Withdrawal Update Form 2File: Form 2 Sky City Sep 2026.pdf20 Oct 2026
Withdrawal Update Form 3File: Form 3 Sky city Sep 2026_0001.pdf20 Oct 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-26.pdf1 Oct 2026
Form 5 (FY 2025-2026)File: Form 5 Sky city 2025-26.pdf1 Oct 2026
Withdrawal Update Form 1File: Form 1 Dipti Sky City June 2026.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Skycity June 2025_0001.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Skycity Sep 2025.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Skycity Sep 2025.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Skycity Sep 2025.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Skycity Sep 2025.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Skycity Sep 2025.pdf30 Jul 2026
Withdrawal Update Form 1File: form 1 Skycity Dec 2025.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Sky City March 2026.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Dipti Sky City June 2026.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Dipti Sky City June 2026.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Dipti Sky City June 2026.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Dipti Skycity Sep 2025 signed_0001.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Dipti Skycity Sep 2025 signed_0001.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Dipti Skycity Sep 2025 signed_0001.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Dipti Skycity Sep 2025 signed_0001.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Dipti Skycity Sep 2025 signed_0001.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Sky City_0001.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Skycity March 2026.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Dipti Sky City June 2026.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity June 2026_0001.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity signed revised_0001.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity Signed_0001.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity Signed_0001.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity Signed_0001.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity Signed_0001.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity Signed_0001.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Dipti Sky City Dec 2025.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity March 2026.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Skycity June 2026_0001.pdf30 Jul 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Skycity signed revised_0001.pdf22 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Skycity June 2025_0001.pdf19 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Skycity form 2 June 2025_0001.pdf19 Jul 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Form B HDFC 09th july 2025.pdf15 Jul 2025
Other - LegalFile: Declaration cum Undertaking 25042025.pdf25 Apr 2025
Other - LegalFile: Declaration Rationale account change 24042025.pdf25 Apr 2025
Other - LegalFile: Format A 24042025.pdf25 Apr 2025
Other - LegalFile: Form 3 Opal Bay Revised 25042025.pdf25 Apr 2025
Other - LegalFile: Form 3 Sky City March 2025_compressed.pdf25 Apr 2025
Other - LegalFile: Declaration cum undertaking Sky City 24042025.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sky City March 2025.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sky City March 2025_compressed.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sky city March 2025.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Signed Skycity Dec 2024.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Skycity Signed Dec 2024_0001.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Skycity Signed Dec 2024 New_0001.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Skycity Sep 2024 Signed_0001.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Skycity Sep 2024 Signed_0001_0001.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Skycity Sep 2024 signed_0001.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Skycity Sep 2024 signed_compressed.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 SkyCity 30062024 signed_0001.pdf24 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Skycity 30062024 Signed_0001.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SkyCity 30062024 Signed_0001.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dipti Skycity March 2024 Signed_0001.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sky city March 2024 Signed_0001.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dipti Sky City March 2024 Signed_0001.pdf20 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 from HSMP for 2022-23.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Quarter 1 31032023_0001.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Quarter 2 30062023_0001.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Quarter 3 30092023_0001.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Quarter 4 31122023_0001.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Quarter 1 31032023_0001.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Quarter 2 30062023_0001.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Quarter 3 30092023_0001.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FOrm 2 Quarter 4 31122023.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Quarter 4 31122023_0001.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Quarter Jan 2023-March 2023_0001.pdf29 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Quarter April 2023 to June 2023_0001.pdf29 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Quarter June 2023-Sep 2023_0001.pdf29 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Quarter April 2023-June 2023_0001.pdf29 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Annexure B - 31-03-2023.pdf29 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2023.pdf29 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 ANNUAL AUDIT REPORT OF STATUTORY.pdf22 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RERA June 2023.pdf11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ANNEXURE A - 30-09-2023.pdf25 Oct 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Dipti Sky CitySurvey No 54 3B 54 3D village pale ambernath east thane254CompletedJul 2017Late, Sep 2021

How this compares with Thane

23%of this project is bookeddistrict median 24%
25%of Thane projects moved their completion datethis one moved by 4 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,700+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Dipti Skycity Bldg No. 7 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambernath East District thane7,700+ in Thane

2 kmDipti Skycity Bldg No. 7Completed 80Lapsed / revoked 25Other 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 146 registered projects within 2 km.

Builder: Dipti Home Makers Pvt Ltd

Dipti Home Makers Pvt Ltd has 8 registrations on MahaRERA, including Dipti Villa - Kolhapur and Vishvaprem Co-operative Housing Society Limited. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Dipti Skycity Bldg No. 7 is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Dipti Skycity Bldg No. 7?

The registered promoter entity is Dipti Home Makers Pvt Ltd, a company as per the filing. Its CIN U70100MH1995PTC095189 and GSTIN 27AAACD3545L1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Dipti Skycity Bldg No. 7?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Dipti Skycity Bldg No. 7?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Dipti Skycity Bldg No. 7?

The professionals named in the filing: Architect: Jitendra Patel Samarthya Engineers K Patel; Architect: Pramod Kamble; Engineer: MANZUR HUSAIN HEBBALLI; Engineer: Atul Kudtarkar and Associates; Engineer: Atul Kudtarkar And Associates Pvt. Ltd.; Chartered Accountant: Dixit Dattatray and Associates D Dixit. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dipti Skycity Bldg No. 7?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dipti Skycity Bldg No. 7. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dipti Skycity Bldg No. 7 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.