Dipti Home Makers Pvt Ltd: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Dipti Home Makers Pvt Ltd has 8 registrations in this build, including Dipti Villa - Kolhapur and Vishvaprem Co-operative Housing Society Limited. Its filings disclose 4 earlier MahaRERA projects: 3 of 4 past projects completed on time.

8Registrations in this build
4Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Dipti Villa - KolhapurKolhapur, Maharashtra--Registration lapsed
Vishvaprem Co-operative Housing Society LimitedMumbai Suburban, Maharashtra--Completed
Dipti SkyCity Building 1 and 3Thane, Maharashtra--Completed
Dipti Sky City PHASE 2Thane, Maharashtra--Completed
SURYA COOPERATIVE HOUSING SOCIETY LTDMumbai Suburban, Maharashtra--Registration lapsed
Om Shivalaya CHS LtdMumbai Suburban, Maharashtra5824%Registered
Dipti Skycity Bldg No. 7Thane, Maharashtra--Registered
Om Sahil Co-operative Housing Society LimitedMumbai Suburban, Maharashtra160%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Dipti Solitaire
15 Nov 20138 Nov 2013On time
Bamanpuri Co-operative Housing Society Limited
1 Apr 20151 Apr 2015On time
Sweta Co-operative Housing Society Limited
30 Sep 201617 Sep 2016On time
Dipti Sky City
1 Jul 201730 Sep 2021+51 months

Frequently asked questions

How do I verify Dipti Home Makers Pvt Ltd as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Dipti Home Makers Pvt Ltd?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.