Home / Browse projects / Mumbai City, Maharashtra / DILKAP GRANDEUR
DILKAP GRANDEUR
By DILIP ESTATE & TOWN PLANNERS PVT LTD
RG-MH-08505 · RERA P51900006119 · Last updated on MahaRERA portal: 31 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 3 months past the filed date
- 9 complaints at MahaRERA
- Completion date moved by 37 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DILKAP GRANDEUR is a Residential / Group Housing project by DILIP ESTATE & TOWN PLANNERS PVT LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900006119 on 14 Aug 2017. Possession was promised by 31 Jul 2026 and is now 3 months past that date. The completion date has moved by 37 months from the original filing. 28 of the 42 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 9 complaints are on record with the regulator.
At a glance
Project
- NameDILKAP GRANDEUR
- TypeResidential / Group Housing
- Location
- ADI SHANKARACHRYA MARG
- POWAI
- Mumbai City
- 400076
- Pincode400076
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900006119
- ReraGenie IDRG-MH-08505
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion31 Jul 2026
- Revised completionRevised to 31 Jul 2026 (originally 30 Jun 2023)
- Buildings1 building record
- Documents filed123 files
Current status
Figures as on 31 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DILKAP GRANDEUR | NA | 34 | 30 | 42 | 0 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 91%.
DILKAP GRANDEUR: 66% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 68% |
| Plinth | 100% |
| Stilt Floor | 62% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 91% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed146
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 42.40 cr | Rs 36.87 cr |
| DILKAP GRANDEUR | NA | Rs 32.50 cr | Rs 30.31 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PUSHKAR CONSULTANT |
| Architect | HAFEEZ CONTRACTOR |
| Engineer | HM RAJE CONSULTANT |
| Engineer | Aquib Zakir Ansari |
| Chartered Accountant | MULANI AND ASSOCIATES |
| Chartered Accountant | Shah Binal & Associates |
| Partner | Role in project |
|---|---|
| DILIP ESTATE & TOWN PLANNERS PVT LTD | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterLong pending permissions and amendments have been sought from the concerned departments which took time for due diligence. More than 90% Commencement Certificate has been recently procured and super structure is underway. Complete construction including finishing and other permissions for getting Occupation Certificate will require an extension period up to 12 months.
Reason as filed by the promoter95% of super structure is complete with internal finishings ongoing including lifts etc. Part Occupation Certificate application will be underway. Complete process and due diligence with permissions from various authorities will take its due course.
Reason as filed by the promoterA major contributing factor to the delay has been the prolonged due diligence and scrutiny process from the Brihanmumbai Municipal Corporation (BMC) and other concerned authorities. Although the CFO Final Plan has been sanctioned, our file is currently under review by the Scrutiny Department of BMC for final approval. Unfortunately, this process has been significantly delayed despite our repeated follow-ups, leading to considerable setbacks in our execution timelines
Complaints filed with MahaRERA9
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000044219 | Kinnari Rajen Chheda | Dilip Estate & Town Planners Pvt. Ltd | 23/04/2018 |
| CC006000000192175 | BARKHA VIKRAM SHARMA | Dilip Estate & Town Planners Pvt Ltd | 14/01/2020 |
| CC006000000194824 | Barkha Sharma | M/s. Dilip Estate& Town Planners Pvt Ltd | 20/11/2020 |
| CC006000000192274 | SHWETA SHARMA | Dilip Estate and Town Planners Pvt Ltd | 24/01/2020 |
| CC006000000194822 | Shweta Sharma | M/s. Dilip Estate & Town Planners Pvt Ltd | 20/11/2020 |
| CC006000000193203 | RAJU CHAWLA | Dilip Estate& Town Planners Pvt. Ltd. | 12/05/2020 |
| CC006000000396394 | Dilip Estate Town Planners | Barkha Vikram Sharma | 23/06/2023 |
| CC006000000396395 | Dilip Estate Town Planners | Shweta Vikas Sharma | 23/06/2023 |
| CC006000000397842 | Ammani Krishna Shetty | Dilip Estate & Town Planners Pvt Ltd | 14/10/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed123
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - DILKAP GRANDEUR Q1 2026.pdf | 31 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - DILKAP GRANDEUR Q1 2026.pdf | 31 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - DILKAP GRANDEUR Q1 2026.pdf | 31 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 - Dilkap Grandeur as on Sep 2025.pdf | 30 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Dilkap Grandeur As on December 2025.pdf | 30 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Dilkap Grandeur As on March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Dilkap Grandeur as on Sep 2025.pdf | 30 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Dilkap Grandeur As on December 2025.pdf | 30 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Dilkap Grandeur As on March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Dilkap Grandeur as on Sep 2025.pdf | 30 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Dilkap Grandeur As on December 2025.pdf | 30 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Dilkap Grandeur As on March 2026.pdf | 30 May 2026 |
| Withdrawal Update Form 1File: Dilkap Grandeur Architect Cert June 25.pdf | 26 Aug 2025 |
| Withdrawal Update Form 2File: Dilkap Granduer Engineer Certificate Q1 June 2025.pdf | 26 Aug 2025 |
| Withdrawal Update Form 3File: CA Certificate Form 3 June 2025_compressed.pdf | 26 Aug 2025 |
| Form 1File: Dilkap Grandeur Architect Cert June 25.pdf | 20 Aug 2025 |
| Form 2File: Dilkap Granduer Engineer Certificate Q1 June 2025.pdf | 20 Aug 2025 |
| Form 3File: CA Certificate Form 3 June 2025_compressed.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Dilkap Grandeur Sold Unsold June 2025.pdf | 20 Aug 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DETP Grandeur Architect Cert March 25 Q4.pdf | 8 Jul 2025 |
| Certificates of CA (Form 3)File: DETP Grandeur CA Cert March 25 Q4.pdf | 8 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DETP Grandeur Engineer Certificate March 2025 Q4.pdf | 8 Jul 2025 |
| Declaration in FORM BFile: Form B Affidavit Dilkap Grandeur Project Extension July 24.pdf | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Grandeur 2024.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate DG Dec 23.pdf | 10 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate DG March 24.pdf | 10 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate DG 31122023.pdf | 10 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate DG 31032024.pdf | 10 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate DG March 24.pdf | 10 Jul 2024 |
| Certificates of CA (Form 3)File: CA Cert RERA Powai 311223.pdf | 10 Jul 2024 |
| Certificates of CA (Form 3)File: CA Cert RERA DG Powai 31032024.pdf | 10 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ANNUAL Certificates of CA (Form 5) 22 23.pdf | 10 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annual CA DG Form No 05 RERA 310324.pdf | 10 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dilkap Grandeur Architect Certificate Sept 23.pdf | 11 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dilkap Grandeur Engineer Certificate Sept 23.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: CA Certificate grandeur Sept 23.pdf | 11 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD : UNSOLD DG P51900006119_FileName_18.pdf | 11 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QC OF GRANDEUR 23.pdf | 20 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert of Grandeur Mar23.pdf | 6 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert of Grandeur.pdf | 3 Jun 2023 |
| Certificates of CA (Form 3)File: CA Cert of Powai Mar23.pdf | 3 Jun 2023 |
| Certificates of CA (Form 5)File: Form no 5 of Powai Mar23.pdf | 3 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form No 5 310322.pdf | 24 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance FY 2122 Powai 020123.pdf | 1 Feb 2023 |
| Proforma of Agreement for saleFile: gRANDEUR.pdf | 29 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert 311222 of Grandeur.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert 311222 of Grandeur.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Cert of 300922 Powai.pdf | 19 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 311222.pdf | 19 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert 300922 Grandeur.pdf | 19 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert Powai 300922.pdf | 19 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate RERA Dilkap Grandeur June 22.pdf | 7 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg Cert 300622 of grandeur.pdf | 6 Sep 2022 |
| Certificates of CA (Form 3)File: Form 3 CA Cert 300622 Grandeur.pdf | 6 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC issued 231221.pdf | 11 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 070622.pdf | 11 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf | 11 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 310321.pdf | 11 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 300621.pdf | 11 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 300921.pdf | 11 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 311221.pdf | 11 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 310322.pdf | 11 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 310322.pdf | 11 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg Cert 310321.pdf | 11 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 300621.pdf | 11 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 300921.pdf | 11 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 310321.pdf | 11 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 310322.pdf | 11 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: download.pdf | 11 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf | 11 Jul 2022 |
| Certificates of CA (Form 3)File: Form no 3 CA Cert 310321.pdf | 11 Jul 2022 |
| Certificates of CA (Form 3)File: Form no 3 CA Cert 300621.pdf | 11 Jul 2022 |
| Certificates of CA (Form 3)File: Form no 3 CA Cart 300921.pdf | 11 Jul 2022 |
| Certificates of CA (Form 3)File: Form no 3 CA Cert 311221.pdf | 11 Jul 2022 |
| Certificates of CA (Form 3)File: Form no 3 CA Cart 310322.pdf | 11 Jul 2022 |
| Certificates of CA (Form 5)File: Form No 5 310322.pdf | 11 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form No 5 310321.pdf | 11 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 9 Jul 2022 |
| CERSAI detailsFile: cersai.pdf | 9 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Architect 310321.pdf | 9 Jul 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Dilkap Chambers | Dilkap Chambers, Veera Desai Road, Off. Andheri Link Road, Andher West | 100 | Completed | Jan 2008 | Jan 2008 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 123 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DILKAP GRANDEUR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near POWAI780+ in Mumbai City
Filed coordinates, straight-line distance. 30 registered projects within 2 km.
EMPRESS HILL A B C and D Wings
HGP Community Pvt. Ltd.
MARS - WING - B
SUNCITY HOUSING
MARS- SUNCITY HOUSING PHASE II
SUNCITY HOUSING
MARS WING-C
Sun City Housing
SHREE KRISHNA Wing C,D and E
Shreem Properties
ISLE OF CALM TOWER 1
SUNRISE HOUSING
See every Mumbai City project, with the district possession charts
Builder: DILIP ESTATE & TOWN PLANNERS PVT LTD
DILIP ESTATE & TOWN PLANNERS PVT LTD has 2 registrations on MahaRERA, including DILKAP GRANDEUR and MAKSKAP CENTRE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What does it mean that DILKAP GRANDEUR shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DILKAP GRANDEUR is delayed beyond 31 Jul 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DILKAP GRANDEUR?
The registered promoter entity is DILIP ESTATE & TOWN PLANNERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DILKAP GRANDEUR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DILKAP GRANDEUR?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DILKAP GRANDEUR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DILKAP GRANDEUR?
The professionals named in the filing: Architect: PUSHKAR CONSULTANT; Architect: HAFEEZ CONTRACTOR; Engineer: HM RAJE CONSULTANT; Engineer: Aquib Zakir Ansari; Chartered Accountant: MULANI AND ASSOCIATES; Chartered Accountant: Shah Binal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DILKAP GRANDEUR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback