Home / Browse projects / Raigarh, Maharashtra / DHRUV RESIDENCY PLATINUM

Registered No litigation declared Residential / Group Housing project

DHRUV RESIDENCY PLATINUM

By KAMLESH DEVIDAS DHRUV

RG-MH-86455 · RERA P52000047179 · Last updated on MahaRERA portal: 26 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
7 of 18Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
77 of 124Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 115 documents Report an error

DHRUV RESIDENCY PLATINUM is a Residential / Group Housing project by KAMLESH DEVIDAS DHRUV in Raigarh, Maharashtra, registered with MahaRERA as P52000047179 on 11 Oct 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 47 of the 124 units on this registration are recorded sold or booked, and 7 of 18 construction stages are filed complete.

At a glance

Project

  • NameDHRUV RESIDENCY PLATINUM
  • TypeResidential / Group Housing
  • Location
    • KALAMB PASHANE ROAD
    • VANGANI WEST
    • Pashane
    • Karjat
    • Raigarh
    • 410101
  • Pincode410101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000047179
  • ReraGenie IDRG-MH-86455

Builder

  • NameKAMLESH DEVIDAS DHRUV
  • Entity typeIndividual
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2022First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Oct 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed115 files

Current status

38%47 of 124 units booked
96.0%Work done, per cost certificate

Figures as on 26 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1 WING ANA5512921
BUILDING NO 2 WING B,C,D,ENA559211103

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

BUILDING NO 1 WING A69%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
BUILDING NO 2 WING B,C,D,E54%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes5%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed145

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots145
Open Space145
BuildingOpen SpaceTotal
BUILDING NO 1 WING A2020
BUILDING NO 2 WING B,C,D,E125125

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area21,200 sq m
Land owned byNot the promoter
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Dec 2025
LandownerVillageDistrict
KETAN DHRUVKurlaMumbai Suburban
PRATIMA DHRUVKurlaMumbai Suburban
ZARNA DHRUVKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityDISTRICT COLLECTOR RAIGADH
Permissible FSI3811.05
Proposed, not sanctioned3,811 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch31, M G ROAD, BEDESHWAR BUILDING, NXT TO TRIBHUWANDAS BHIMJI ZAVERI SHOWROOM, GHATKOPAR (EAST), MUMBAI - 400077, MAHARASHTRA ,INDIA
Estimated costRs 8.21 cr
Cost incurredRs 7.88 cr
Work done96.01%
BuildingWingEstimatedIncurred
BUILDING NO 2 WING B,C,D,ENARs 6.43 crRs 6.36 cr
BUILDING NO 1 WING ANARs 1.17 crRs 1.14 cr
-NARs 61.50 lakhRs 37.51 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKETAN VAIDYA ASSOCIATES
EngineerS V PATEL & ASSOCIATES
Chartered AccountantKARISHMA SHAH & ASSOCIATES
Chartered AccountantMANISHA RAJBHAR
PartnerRole in project
KAMLESH DEVIDAS DHRUV-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA17122518721Dec 2025 → Dec 2026

Reason as filed by the promoterThe project is currently ongoing, and we have obtained consent from all allottees. The RCC for the project has been completed, and we assure the authorities that the project will be finished according to the promised timeline, along with obtaining the full occupancy certificate, before December 31, 2026. Therefore, we kindly request the authorities to grant us an extension until December 31, 2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed115

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: Highlighted Plan.pdf26 May 2026
Withdrawal Update Form 1File: KETAN VAIDYA 19-01-2026.pdf20 Jan 2026
Withdrawal Update Form 2File: SV 16-01-2026.pdf20 Jan 2026
Withdrawal Update Form 3File: CA MANISHA 19-01-2026.pdf20 Jan 2026
Form 1File: ketan vaidya oct 2025.pdf16 Oct 2025
Form 2File: s v patel 2025.pdf16 Oct 2025
Form 3File: CA manisha & co.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: platinum sold and booked.pdf16 Oct 2025
Form 1File: arch.pdf20 Jul 2025
Form 2File: engg.pdf20 Jul 2025
Form 3File: ca.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 10.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 9.pdf20 Jul 2025
Form 1File: ketan vaidya (1).pdf20 Jul 2025
Form 2File: sv patel.pdf20 Jul 2025
Form 3File: CA (3).pdf20 Jul 2025
Form 1File: architects certificate (1).pdf20 Jul 2025
Form 2File: sv patel certificate.pdf20 Jul 2025
Form 3File: ca.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 8.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 7.pdf20 Jul 2025
Form 1File: arc.pdf20 Jul 2025
Form 2File: eng.pdf20 Jul 2025
Form 3File: ca.pdf20 Jul 2025
Form 1File: ARCHITECT CERTIFICATE.pdf20 Jul 2025
Form 2File: engg.pdf20 Jul 2025
Form 3File: ca.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 6.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 5.pdf20 Jul 2025
Form 1File: KETAN VAIDYA CERTIFICATE.pdf20 Jul 2025
Form 2File: S V PATELCERTIFICATE.pdf20 Jul 2025
Form 3File: CA CERTIFICATE.pdf20 Jul 2025
Form 1File: arch.pdf20 Jul 2025
Form 2File: engg.pdf20 Jul 2025
Form 3File: CA KARISHMA SHAH.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 3.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 2.pdf20 Jul 2025
Form 1File: Ketan vaidya (2).pdf20 Jul 2025
Form 2File: S V PATEL 2.pdf20 Jul 2025
Form 3File: krishma shah.pdf20 Jul 2025
Form 1File: architect.pdf20 Jul 2025
Form 2File: engg.pdf20 Jul 2025
Form 3File: ca.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 1.pdf20 Jul 2025
Form 1File: arch.pdf20 Jul 2025
Form 2File: engg.pdf20 Jul 2025
Form 3File: KARISHMA SHAH CA.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: FILE 4.pdf20 Jul 2025
Form 1File: arch.pdf16 Jul 2025
Form 2File: engg.pdf16 Jul 2025
Form 3File: ca.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD.pdf16 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANNEXURE A FORM.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1352 RERA CERTIFICATE.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ketan vaidya.pdf10 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf10 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sv patel.pdf10 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 FY 2324.pdf4 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: architects certificate.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ketan vaidya.pdf10 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sv patel.pdf10 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: karishma shah asso.pdf10 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer.pdf10 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KETAN VAIDYA CERTIFICATE.pdf10 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: S V PATELCERTIFICATE.pdf10 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Form 5 certificate_FY 22-23.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KETAN VAIDYA.pdf10 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: S V PATEL.pdf10 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KARISHMA SHAH CA.pdf10 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architact.pdf7 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC.pdf7 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA KARISHMA SHAH.pdf7 Jul 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
DHRUV RESIDENCY-NXRAIGAD125CompletedMar 2022Mar 2022

How this compares with Raigarh

38%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 12 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DHRUV RESIDENCY PLATINUM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VANGANI WEST5,900+ in Raigarh

2 kmDHRUV RESIDENCY PLATINUMCompleted 8Lapsed / revoked 10Other 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 31 registered projects within 2 km.

Builder: KAMLESH DEVIDAS DHRUV

KAMLESH DEVIDAS DHRUV has 1 registration on MahaRERA, including DHRUV RESIDENCY PLATINUM. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if DHRUV RESIDENCY PLATINUM is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DHRUV RESIDENCY PLATINUM?

The registered promoter entity is KAMLESH DEVIDAS DHRUV, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DHRUV RESIDENCY PLATINUM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DHRUV RESIDENCY PLATINUM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DHRUV RESIDENCY PLATINUM?

The professionals named in the filing: Architect: KETAN VAIDYA ASSOCIATES; Engineer: S V PATEL & ASSOCIATES; Chartered Accountant: KARISHMA SHAH & ASSOCIATES; Chartered Accountant: MANISHA RAJBHAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DHRUV RESIDENCY PLATINUM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DHRUV RESIDENCY PLATINUM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DHRUV RESIDENCY PLATINUM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.