ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Dhanorina

Registration lapsed No litigation declared Residential / Group Housing project

Dhanorina

By Paritosh Pungaliya

RG-MH-20426 · RERA P52100006082 · Last updated on MahaRERA portal: 9 Aug 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 41 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 53 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2023Possession promised41 months past this date
3 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 97%
5Complaints at MahaRERAon this registration
Jump to the 25 documents Report an error

Dhanorina is a Residential / Group Housing project by Paritosh Pungaliya in Pune, Maharashtra, registered with MahaRERA as P52100006082 on 14 Aug 2017. Possession was promised by 31 May 2023 and is now 41 months past that date. The completion date has moved by 53 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameDhanorina
  • TypeResidential / Group Housing
  • Location
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411015
  • Pincode411015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100006082
  • ReraGenie IDRG-MH-20426

Builder

  • NameParitosh Pungaliya
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

41 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toMay 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Aug 2017
  • Promised completion31 May 2023
  • Revised completionRevised to 31 May 2023 (originally 31 Dec 2018)
  • Buildings2 building records
  • Documents filed25 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing BNA50000
Wing ANA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 9 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 97%.

Wing B57%
ActivityProgress
Excavation97%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor75%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Wing A27%
ActivityProgress
Excavation97%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
Wing B11
Wing A11

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area923 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Harishkumar AroraPune (M Corp.)Pune

Approvals and building plan

Permissible FSI1659.89
Proposed, not sanctioned911 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPune

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVeena Mehta
PartnerRole in project
Paritosh Sudhir Pungaliya-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001767Dec 2018 → Dec 2019

Reason as filed by the promoter(1) Airforce NOC application was made way back (May 2018 and April 2019) but was rejected as original copy of survey report was misplaced when querries were raised. Copy attached.May 2018 and April 2019.They needed site cooordinates and site elevations from survey of India required to be submitted with NOC application. (2) Subsequently due to overload of work the Survey of India did not accept the application for duplicate copy for prolonged period of time. No official circular is available for the same except for the photo of notice on the main gate of Survey of India. Copy attached. (3) Subs

EXT52100012269Dec 2018 → May 2023

Reason as filed by the promoterAs Airforce NOC delayed and after that Covid pandemic we could not complete the project within time

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC005000000000211Ankit MalviyaParitosh30/11/2018
CC005000000022719BHARAMA KALLAPPA DUNDAGEKARPARITOSH PUNGALIYA28/02/2019
CC005000000033505DEVRAJ BHIMRAJ AREKARPARITOSH PUNGALIYA10/10/2019
CC005000000043744Rahul ChandanParitosh Pungaliya27/12/2019
CC005000000043788Shikha BhardwajParitosh Pungaliya29/12/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed25

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: sold unsold.pdf9 Aug 2022
Declaration about Commencement CertificateFile: commencement declaration_compressed.pdf8 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 19-20.pdf8 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 20-21.pdf8 Aug 2022
Disclosure of sold/ booked inventoryFile: Sold unsold summary.pdf8 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA-18-19.pdf15 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA-19-20.pdf15 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA-20-21.pdf15 Jul 2022
Certificates of CA (Form 5)File: Form 5Dhanorina.PDF9 Jul 2019
Layout approvalFile: building plan 24 25.pdf31 Jul 2017
Building plan approvalFile: building plan 24 25.pdf31 Jul 2017
Building plan approvalFile: building plan 24 25.pdf31 Jul 2017
PAN CardFile: PAN card.PDF31 Jul 2017
Copy of the legal title reportFile: Copy of the legal title report DH-ilovepdf-compressed (1)-ilovepdf-compressed.pdf31 Jul 2017
Copy of the legal title reportFile: Copy of the legal title report DH-ilovepdf-compressed (1)-ilovepdf-compressed.pdf31 Jul 2017
Copy of the legal title reportFile: Copy of the legal title report DH-ilovepdf-compressed (1)-ilovepdf-compressed.pdf31 Jul 2017
Details of encumbrancesFile: Form B.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: building plan 24 25.pdf31 Jul 2017
Building Plan Approval (IOD)File: building plan 24 25.pdf31 Jul 2017
Building Plan Approval (IOD)File: building plan 24 25.pdf31 Jul 2017
Declaration in FORM BFile: Form B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 DH-ilovepdf-compressed.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 DH.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3.pdf31 Jul 2017
Proforma of Allotment letterFile: Proforma.pdf31 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 53 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Dhanorina on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune (M Corp.)13,700+ in Pune

2 kmDhanorinaCompleted 78Lapsed / revoked 28Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 152 registered projects within 2 km.

Builder: Paritosh Pungaliya

Paritosh Pungaliya has 2 registrations on MahaRERA, including Chandrai and Dhanorina. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Dhanorina shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Dhanorina is delayed beyond 31 May 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Dhanorina?

The registered promoter entity is Paritosh Pungaliya, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Dhanorina?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Dhanorina?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Dhanorina?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Dhanorina?

The professionals named in the filing: Architect: Veena Mehta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dhanorina?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dhanorina. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dhanorina to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.