Registered No litigation declared Residential / Group Housing project

Defence Colony Pune Phase4

By Defence Colony Pune

RG-MH-11945 · RERA P52100009756 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • 16 complaints at MahaRERA
  • Completion date moved by 95 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 95 months from the original
45 of 55Construction stages doneacross 5 buildings; furthest along: Basement (if any), 0%
32 of 312Units unsoldnot recorded sold or booked
16Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Defence Colony Pune Phase4 is a Residential / Group Housing project by Defence Colony Pune in Pune, Maharashtra, registered with MahaRERA as P52100009756 on 22 Aug 2017. Possession is promised by 30 Nov 2026. The completion date has moved by 95 months from the original filing. 280 of the 312 units on this registration are recorded sold or booked, and 45 of 55 construction stages are filed complete. 16 complaints are on record with the regulator.

At a glance

Project

  • NameDefence Colony Pune Phase4
  • TypeResidential / Group Housing
  • Location
    • -
    • WAGHOLI
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100009756
  • ReraGenie IDRG-MH-11945

Builder

  • NameDefence Colony Pune
  • Entity typeSociety
  • ChairpersonPandurang Prabhakar Ankushe
  • SecretoryAkshayKumar Dnyanoba Navgire
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion30 Nov 2026
  • Revised completionRevised to 30 Nov 2026 (originally 31 Dec 2018)
  • Buildings5 building records
  • Documents filed73 files

Current status

90%280 of 312 units booked
100.0%Work done, per cost certificate

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A wingNA131272072
B WingNA131272072
E WingNA121188088
C wingNA121144044
D WingNA9936036

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Basement (if any), at 0%.

A wing82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Wing82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E Wing82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C wing82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D Wing82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed226

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots226
Closed/Covered226
BuildingClosed/CoveredTotal
A wing4848
B Wing5454
E Wing5656
C wing3232
D Wing3636

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area13,600 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Oct 2025

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority Pune
Permissible FSI15565.2
Proposed, not sanctioned13,524 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSurvey no 151/14/6, Opposite Nobel Hospital, Mundwa road, Hadapsar -411028
Estimated costRs 122.73 cr
Cost incurredRs 122.73 cr
Work done100.0%
BuildingWingEstimatedIncurred
A wingNARs 22.08 crRs 22.08 cr
B WingNARs 22.08 crRs 22.08 cr
E WingNARs 22.08 crRs 22.08 cr
C wingNARs 22.08 crRs 22.08 cr
D WingNARs 22.08 crRs 22.08 cr
-NARs 12.33 crRs 12.33 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtit Srikant Admulwar SHRIKANT ADMULWAR
ArchitectMUKTA ARCHITECTS
EngineerDINESH RAKH
Chartered AccountantSPARK AND CO.
Chartered AccountantMUKESH M CHOKSI AND CO
Chartered AccountantNilesh Thakor& Associates
PartnerRole in project
Defence Colony Pune-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001228Dec 2018 → Sep 2020

Reason as filed by the promoterMore than 90% work for the current sanctioned stage have been completed. However, the additional FSI is now getting approved which will take time to complete the additional floors and amenities. As of date, considering the additional floors from new FSI, approx 80% has been completed. Requesting one time extension to complete all the work including amenities and handover the project.

EXT52100005218Dec 2018 → Sep 2020

Reason as filed by the promoterAmenity space handed over to PMRDA in July 2019, FSI against the amenity space expected by first week of January 2020.

EXT52100011684Dec 2018 → Sep 2022

Reason as filed by the promoterNON AVAILABILITY OF LABOUR AND CONSTRUCTION MATERAL DUE TO COVID 19 PANDEMIIC

EXT52100009423Dec 2018 → Sep 2021

Reason as filed by the promoterThe project has been delayed due to COVID 19 lockdown and limited availability of skilled work force once the lockdown was relaxed. Even now the work is getting done adhering lot of precautions and physical distancing with limited workers. Last 5% work is pending and those will be completed in next 4-5 months. Request extension for 6 months.

EA03112518228Dec 2018 → Nov 2026

Reason as filed by the promoterCONSTRUCTION OF THE SAID PROJECT IS 100% COMPLETED. WE ARE IN PROCESS TO APPLY FOR FULL OCCUPANCY CERTIFICATE. WE NEED EXTENSION TO OBTAIN FULL OCCUPANCY CERTIFICATE. WE WANT TO APPLY FOR EXTENSION OF THE SAID PROJECT TILL 30/11/2026. REQUESTING YOU TO KINDLY PROVIDE US EXTENSION TILL 30/11/2026.

Complaints filed with MahaRERA16

Case no.ComplainantRespondentFiled
CC005000000064460Jitendra Champalal JainDefence Colony Pune Phase401/09/2020
CC005000000117069Jitendra Champalal JainMr.Narayan Prabhakar Ankushe03/05/2022
CC005000000075093Sanjeev Nandkishore SharmaNarayan Prabhakar Ankushe16/01/2021
CC005000000095936GIRISH RAGHUNATH SONARNarayan Prabhakar Ankushe27/08/2021
CC005000000095962Harshal MehtaNarayan Prabhakar Ankushe07/09/2021
CC005000000095957Bhushan Makrand PhadkeNarayan Prabhakar Ankushe06/09/2021
CC005000000095974Ankit MishraNarayan Prabhkar Ankushe07/09/2021
CC005000000095982Ankit UpadhyayNarayan Prabhakar Ankushe01/04/2022
CC005000000096318Aditya Devidas GampawarMr. Narayan Prabhakar Ankushe29/11/2021
CC005000000096074VIKRAM GAIKWADNARAYAN ANKUSHE28/09/2021
CC005000000096083Ketan Kailas DhodareNarayan Prabhakar Ankushe30/09/2021
CC005000000106413Shailaja Mahendra JainDefence Colony Co-Operative Housing Society Phase 426/12/2021
CC005000000117018DEFENCE COLONY CO-OPERATIVE SOCIETY THROUGH ITS PROMOTER NARAYAN PRABHAKAR ANKUSHEMR. DEVIDAS BHAUSAHEB KARDILE07/05/2022
CC005000000167460Rajesh Kumar JhaDEFENCE COLONY PUNE05/09/2022
CC005000000177905Ganesh Vitthal PawarDefence Colony Co-operative Housing Society Ltd. Through its Chairman Mr Pandurang Prabhakar Ankushe08/12/2022
CC12502729Defence Colony PuneDEEPMALA AJITSINGH CHAUHAN04/08/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Oct 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Oct 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Oct 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Jan 2023

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: from 1.pdf22 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf22 Jun 2026
Withdrawal Update Form 3File: Form 3 New.PDF22 Jun 2026
Withdrawal Update Form 1File: from 1.pdf20 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf20 Jun 2026
Withdrawal Update Form 3File: Form 3 New.PDF20 Jun 2026
Withdrawal Update Form 1File: from 1.pdf9 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf9 Jun 2026
Withdrawal Update Form 3File: FORM 3 FINAL.pdf9 Jun 2026
Withdrawal Update Form 1File: FORM 1.pdf8 Jun 2026
Withdrawal Update Form 1File: FORM 1 final.pdf8 Jun 2026
Withdrawal Update Form 1File: FORM 1 FINAL.pdf8 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf8 Jun 2026
Withdrawal Update Form 2File: FORM 2 FINAL.pdf8 Jun 2026
Withdrawal Update Form 2File: FORM 2 FINAL.pdf8 Jun 2026
Withdrawal Update Form 3File: FORM 3 June final.PDF8 Jun 2026
Withdrawal Update Form 3File: FORM 3 fINAL.pdf8 Jun 2026
Withdrawal Update Form 3File: FORM 3.pdf8 Jun 2026
Form 2A (FY 2025-2026)File: FORM 2A ( 2025-2026).pdf16 May 2026
Form 2A (FY 2024-2025)File: FORM 2A ENGINEER CERTIFICATE FOR FY 2024-2025.pdf18 Mar 2026
Form 5 (FY 2022-2023)File: FORM 5 FY 2022 - 2023.pdf16 Mar 2026
Form 5 (FY 2023-2024)File: FORM 5 FY 2023-2024.pdf16 Mar 2026
Form 5 (FY 2024-2025)File: FORM 5 FY 2024-2025.pdf16 Mar 2026
Layout approvalFile: Layout 01.pdf3 Oct 2025
Building plan approvalFile: Plan 02.pdf3 Oct 2025
Building plan approvalFile: Plan 03.pdf3 Oct 2025
Building plan approvalFile: Plan 04.pdf3 Oct 2025
Building plan approvalFile: Plan 05.pdf3 Oct 2025
Building plan approvalFile: Plan 06.pdf3 Oct 2025
Building plan approvalFile: Plan 07.pdf3 Oct 2025
Building plan approvalFile: Plan 08.pdf3 Oct 2025
Building plan approvalFile: Plan 09.pdf3 Oct 2025
Building plan approvalFile: Plan 10.pdf3 Oct 2025
Copy of Layout Approval (in case of layout)File: Layout 01.pdf3 Oct 2025
Commencement Certificates / NA Order for plotted developmentFile: FINAL CC _11zon.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 02.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 10.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 09.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 08.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 07.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 06.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 05.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 04.pdf3 Oct 2025
Building Plan Approval (IOD)File: Plan 03.pdf3 Oct 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC.pdf16 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Defence Colony Architect Certificate_compressed.pdf31 Mar 2022
Certificates of CA (Form 3)File: Form 3 With Annex New (1).pdf31 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RE Engineer Certificate Form 2.pdf31 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_20.pdf31 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_19.pdf31 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_18-19.pdf31 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_19-20.pdf31 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_20-21.pdf31 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_21.pdf31 Mar 2022
Disclosure of sold/ booked inventoryFile: Defence Colony - Sold Unsold.pdf31 Mar 2022
Declaration about Commencement CertificateFile: Commencement Certificate RERA.pdf31 Mar 2022
CERSAI detailsFile: CERSAI_For_Asset_Based_Search_Defence Colony.pdf31 Mar 2022
Certificates of Architect (Form 4)File: Def_Col_RERA_Extn_Arch_Certificate.pdf28 Jan 2019
Certificates of CA (Form 5)File: RERA_Ext_CA_Certificate.PDF28 Jan 2019
Copy of the legal title reportFile: DCP_Phase4_Search_Title.pdf31 Jul 2017
Declaration in FORM BFile: Phase4_FormB.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_Phase4.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA_certificate_Phase4.PDF31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E Form Phase 4.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: DCP_Phase4_Comencement_Letter.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: DCP_Phase4_Comencement_Letter2.pdf31 Jul 2017
Layout approvalFile: Phase4_layout.pdf30 Jul 2017
Building plan approvalFile: Phase4_Plan.pdf30 Jul 2017
PAN CardFile: DCP_PAN.pdf30 Jul 2017
Details of encumbrancesFile: NIL_Incumbrances.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Phase4_layout.pdf30 Jul 2017
Proforma of Allotment letterFile: B_304_Agreement.pdf30 Jul 2017
Building Plan Approval (IOD)File: Phase4_Plan.pdf30 Jul 2017

How this compares with Pune

90%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 95 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Defence Colony Pune Phase4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -13,700+ in Pune

2 kmDefence Colony Pune PhasCompleted 44Lapsed / revoked 20Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 125 registered projects within 2 km.

Builder: Defence Colony Pune

Defence Colony Pune has 3 registrations on MahaRERA, including Defence Colony Pune Phase1 and Defence Colony Pune Phase2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Defence Colony Pune Phase4 is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Defence Colony Pune Phase4?

The registered promoter entity is Defence Colony Pune, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Defence Colony Pune Phase4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Defence Colony Pune Phase4?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Defence Colony Pune Phase4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Defence Colony Pune Phase4?

The professionals named in the filing: Architect: Atit Srikant Admulwar SHRIKANT ADMULWAR; Architect: MUKTA ARCHITECTS; Engineer: DINESH RAKH; Chartered Accountant: SPARK AND CO.; Chartered Accountant: MUKESH M CHOKSI AND CO; Chartered Accountant: Nilesh Thakor& Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Defence Colony Pune Phase4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Defence Colony Pune Phase4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Defence Colony Pune Phase4 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.