ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / DAVID’S COURT

Registration approved No litigation declared Residential/Group Housing project

DAVID’S COURT

By MARIAN PROMINENCE LLP

RG-KA-87769 · RERA PRM/KA/RERA/1257/334/PR/090125/007367 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
15 of 15Construction stages doneevery applicable stage filed complete
5 of 18Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 93 documents Report an error

DAVID’S COURT is a Residential/Group Housing project by MARIAN PROMINENCE LLP in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/090125/007367 on 9 Jan 2025. Possession is promised by 31 Dec 2029. 13 of the 18 units on this registration are recorded sold or booked, and 15 of 15 construction stages are filed complete.

At a glance

Project

  • NameDAVID’S COURT
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575002
  • Pincode575002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/090125/007367
  • ReraGenie IDRG-KA-87769

Builder

  • NameMARIAN PROMINENCE LLP
  • Entity typePartnership Firm
  • LLPINACG-8473
  • GSTIN29ACAFM4043M1Z0
  • Authorized SignatoryNAVEEN CARDOZA

Key dates

this monthRegisteredJan 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Jan 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed93 files

Current status

72%13 of 18 units booked
174.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DAVID’S COURT---18018

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 15 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes100%
ParksYes100%
Power BackupYes100%
Piped GasYes100%
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area984 sq m
Named landowners1
LandownerVillageDistrict
ANNETTE MARY DAVID & AUREL DAVID--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.59 cr
Cost incurredRs 8.00 cr
Spent of the estimate174.21%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 4.59 crRs 7.27 cr
On-site expenditure-Salaries of workers-Rs 73.01 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARSHA HARINATHBABU KASSA
EngineerNAVEEN CARDOZA-Marian Infrastructures
Chartered AccountantGANESH RAO P

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed93

As listed on the registration, under the names the promoter filed them with; the newest 80 of 93 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/090125/007367 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form 4.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: 261008-Form- 5- Architect.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Signed.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: 260707-Form- 5- Architect.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: 270715-Engineers form with annexure A R1.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: SIGNED RERA Q4 MARIAN.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: 260408-Form- 5- Architect.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: 260408-Form 6- Engineer.PDF15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: SIGNED RERA Q3 MARIAN.pdf16 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form- 5- Architect.pdf16 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineers form.PDF16 Jan 2026
Certificate of AuthorizationFile: Authorisation Letter.PDF2 Jan 2025
FS NAVEENFile: FS Naveen.pdf2 Jan 2025
FS HAZELFile: FS Hazel.pdf2 Jan 2025
FS PRAKASHFile: FS Prakash.pdf2 Jan 2025
FS JOSHALFile: FS Joshal.pdf2 Jan 2025
SOURCE OF FUNDFile: Source of Fund.pdf2 Jan 2025
CA KYCFile: CA KYC.pdf2 Jan 2025
RTCFile: RTC.pdf2 Jan 2025
EC 2/7/2024 to till dateFile: EC 02072024-01012025.pdf2 Jan 2025
ADLR SKETCHFile: ADLR sketch.pdf2 Jan 2025
SINGLE LAYOUTFile: single layout.pdf2 Jan 2025
BUILDING LICENCEFile: building licence.pdf2 Jan 2025
Approved building planFile: approved plan.pdf2 Jan 2025
floor section elevation planFile: floor section elevation plan.pdf2 Jan 2025
commencement certificateFile: commencement certificate.pdf2 Jan 2025
master planFile: CDP plan.jpeg2 Jan 2025
village mapFile: village map-site highligthed.pdf2 Jan 2025
amenities certified by engineerFile: Ameneties certified by engineer.PDF2 Jan 2025
self-attested copy of the Engineer LicenseFile: Self atteseted license of Engineer.PDF2 Jan 2025
form 1 ca reportFile: form 1 ca report revised.pdf2 Jan 2025
stabilty certificateFile: Structural Stability Certificate.pdf2 Jan 2025
proforma AOSFile: proforma AOS.pdf2 Jan 2025
land cost calculation sheet with guidance valueFile: Land Cost sheet with guidance value.pdf2 Jan 2025
stp notification order copyFile: Goverment STP Order.pdf2 Jan 2025
clarificationFile: Clarification.PDF2 Jan 2025
RTC, survey 125/9-
Mutation, survey 125/9-
Encumbrance Certificate, survey 125/9-
Conversion/Alienation Order, survey 125/9-
Sale/Title/Gift Deed, survey 125/9-
JDA, survey 125/9-
Khatha, survey 125/9-
Registration CertificateFile: firm regisatrtion certiifcate.pdf-
GST CertificateFile: GST.pdf-
Partnership DeedFile: partnership deed.PDF-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: form 1 ca report revised.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Certificate (revised cost).pdf-
Certificate issued by Engineer Form 3File: Form -3 Engineer Certificate (revised cost ).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: form 1 ca report revised.pdf-
building licence-
single layout-
approved plan-
Structural Stability Certificate-
specifiction-
RELINQUISHMENT DEED-
proforma AOS-
proforma allotment letter-
Form B Affidavit-
affidavit 3(1)-
Jda affidavt-
search report-
MESCOM NOC-
Water NOC-MCC-
Pollution-NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Dakshina Kannada

72%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep DAVID’S COURT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmDAVID’S COURTOther 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: MARIAN PROMINENCE LLP

MARIAN PROMINENCE LLP has 1 registration on RERA Karnataka, including DAVID’S COURT. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if DAVID’S COURT is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DAVID’S COURT?

The registered promoter entity is MARIAN PROMINENCE LLP, a partnership firm as per the filing. Its LLPIN ACG-8473 and GSTIN 29ACAFM4043M1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DAVID’S COURT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DAVID’S COURT?

The professionals named in the filing: Architect: HARSHA HARINATHBABU KASSA; Engineer: NAVEEN CARDOZA-Marian Infrastructures; Chartered Accountant: GANESH RAO P. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DAVID’S COURT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DAVID’S COURT. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DAVID’S COURT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.