Home / Browse projects / Thane, Maharashtra / DAVAKHAR SERENO PHASE III B

Registered No litigation declared Residential / Group Housing project

DAVAKHAR SERENO PHASE III B

By DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED

RG-MH-31710 · RERA P51700080045 · Last updated on MahaRERA portal: 10 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2030Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

DAVAKHAR SERENO PHASE III B is a Residential / Group Housing project by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700080045 on 21 Apr 2025. Possession is promised by 31 Mar 2030.

At a glance

Project

  • NameDAVAKHAR SERENO PHASE III B
  • TypeResidential / Group Housing
  • Location
    • ADIVALI DHOKALI
    • KALYAN EAST
    • Ambarnath
    • Thane
    • 421306
  • Pincode421306
  • RERA no.P51700080045
  • ReraGenie IDRG-MH-31710

Builder

  • NameDAVAKHAR INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • CINU45400MH2010PTC199726
  • GSTIN27AADCD3567H1ZK
  • DirectorsSantosh Sopan Davakhar, Diksha Santosh Davakhar
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2025PromisedMar 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Apr 2025
  • Promised completion31 Mar 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 2NA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

BUILDING NO 2: 9% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed193

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots193
Closed/Covered64
Open Space129

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,855 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
SURESH RAJARAM PAWSHEAdivali DhokaliThane
DEVIDAS BHIVA BHANEAdivali DhokaliThane
DILIP BHIVA BHANEAdivali DhokaliThane
Jitendra Bhiva BhaneAdivali DhokaliThane

Approvals and building plan

Sanctioning authorityKALYAN DOMBIVALI MUNICIPAL CORPORATION
Permissible FSI24264.84
Proposed, not sanctioned18,265 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch101 1ST FLOOR BHOOMI VELOCITY B39 ROAD NO 23 WAGLE ESTATE THANE 400604

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDECON CONSULTANTS
ArchitectDe-Con Consultants
EngineerASSOCIATES STRUCTURAL ENGINEER LLP
EngineerASC Associated Structural Engineering LLP
Chartered AccountantMAYUR K JAIN AND CO
Chartered AccountantManohar Sheth
Chartered AccountantMayur Jain
Chartered AccountantM.N SHETH & CO
PartnerRole in project
DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2030

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 31-03-2026 III 3B.pdf10 Jun 2026
Form 2File: Form-2_DS 3B March 2026-FINAL.pdf10 Jun 2026
Form 3File: Form 3 31-03-2026 III 3B_compressed.pdf10 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 31-03-2026 III 3B.pdf10 Jun 2026
Form 1File: Form-1 31-12-2025.pdf25 May 2026
Form 2File: Form - 2 31-12-2025.pdf25 May 2026
Form 3File: Form-3 31-12-2025_compressed.pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 31-12-2025.pdf25 May 2026
Form 1File: Form-1 30-09-2025.pdf18 May 2026
Form 2File: Form 2 30-09-2025.pdf18 May 2026
Form 3File: Form 3 30-09-2025 Final.pdf18 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold 30-09-2025.pdf18 May 2026
Form 1File: Form-1 30-06-2025.pdf14 May 2026
Form 2File: Form-2 30-06-2025.pdf14 May 2026
Form 3File: Form-3 30-06-2025_compressed.pdf14 May 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 30-6-2025.pdf14 May 2026
Details of encumbrances concerned to FinanceFile: DOC-20250321-WA0030_250411_201329.pdf11 Apr 2025
Details of encumbrances concerned to LegalFile: DOC-20250321-WA0030_250411_201329.pdf11 Apr 2025
Proforma of Agreement for saleFile: Revised_Davakhar Sereno Phase III B.pdf11 Apr 2025
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (1).pdf1 Apr 2025
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (1).pdf1 Apr 2025
Other - LegalFile: Declaration about Legal heir.pdf1 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: CC Verification.pdf31 Mar 2025
CERSAI detailsFile: Adobe Scan 31-Mar-2025.pdf31 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: SBI FORMAT B (1).pdf31 Mar 2025
Copy of the legal title reportFile: Title Report DS III B Part 1.pdf25 Mar 2025
Copy of the legal title reportFile: Title Report DS III B Part 2.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 25-03-2025_0001_compressed.pdf25 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Deviation for AFS.pdf25 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Diksha Davakhar.pdf25 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Dis Secured Unsecured.pdf25 Mar 2025
Details of encumbrances concerned to FinanceFile: Financial Encumbrance.pdf21 Mar 2025
Details of encumbrances concerned to LegalFile: Financial Encumbrance.pdf21 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf21 Mar 2025
Building plan approvalFile: MYSCAN_20250228_0004.pdf13 Mar 2025
Building plan approvalFile: MYSCAN_20250228_0005.pdf13 Mar 2025
Building plan approvalFile: MYSCAN_20250228_0006 (1).pdf13 Mar 2025
PAN CardFile: 1 PAN Card (2).pdf13 Mar 2025
Proforma of Allotment letterFile: Davkhar Allotment Letter_0001_compressed.pdf13 Mar 2025
Declaration in FORM BFile: Form B Promotor.pdf13 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 .pdf13 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3020_Davkhar Sereno_Form 2__Phase III__revised 07_250311_160005 (1).pdf13 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf13 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20250228_0004.pdf13 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20250228_0005.pdf13 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20250228_0006 (1).pdf13 Mar 2025
Other - LegalFile: Davkhar Declaration About Land Area of project_0001.pdf13 Mar 2025
Declaration about Commencement CertificateFile: Format D Davkhar_0001.pdf13 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Davkhar_0001_0001.pdf13 Mar 2025
Deviation Report with respect to Allotment letterFile: Report on deviation with respect to allotment letter.pdf13 Mar 2025
Other - FinanceFile: declaration of land owner (1).pdf13 Mar 2025
Other - FinanceFile: Suresh Pawshe Declaration Davakhar _0001.pdf13 Mar 2025
Other - TechnicalFile: Undertaking Davkhar_0001.pdf13 Mar 2025
Other - TechnicalFile: Davkhar Declaration About Land Area of project_0001.pdf13 Mar 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
DAVAKHAR ELEGANCEP51700016124KALYAN EAST, ThaneApr 2018OngoingDec 2022Not delivered

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DAVAKHAR SERENO PHASE III B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN EAST7,600+ in Thane

Builder: DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED

DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED has 6 registrations on MahaRERA, including DAVAKHAR ELEGANCE and Davakhar Elegance Phase II. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if DAVAKHAR SERENO PHASE III B is delayed beyond 31 Mar 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DAVAKHAR SERENO PHASE III B?

The registered promoter entity is DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Its CIN U45400MH2010PTC199726 and GSTIN 27AADCD3567H1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DAVAKHAR SERENO PHASE III B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DAVAKHAR SERENO PHASE III B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DAVAKHAR SERENO PHASE III B?

The professionals named in the filing: Architect: DECON CONSULTANTS; Architect: De-Con Consultants; Engineer: ASSOCIATES STRUCTURAL ENGINEER LLP; Engineer: ASC Associated Structural Engineering LLP; Chartered Accountant: MAYUR K JAIN AND CO; Chartered Accountant: Manohar Sheth. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DAVAKHAR SERENO PHASE III B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DAVAKHAR SERENO PHASE III B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DAVAKHAR SERENO PHASE III B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.