Home / Browse projects / Thane, Maharashtra / DAVAKHAR ELEGANCE

Completed No litigation declared Residential / Group Housing project

DAVAKHAR ELEGANCE

By DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED

RG-MH-82225 · RERA P51700016124 · Last updated on MahaRERA portal: 9 Nov 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 51 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Installation of Lifts, 99%
1Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

DAVAKHAR ELEGANCE is a Residential / Group Housing project by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700016124 on 17 Apr 2018. The registration is recorded completed; possession was promised by 31 Mar 2027. The completion date has moved by 51 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameDAVAKHAR ELEGANCE
  • TypeResidential / Group Housing
  • Location
    • PISAVALI
    • KALYAN EAST
    • Kalyan
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700016124
  • ReraGenie IDRG-MH-82225

Builder

  • NameDAVAKHAR INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • CINU45400MH2010PTC199726
  • GSTIN27AADCD3567H1ZK
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorSOPAN GOPAL DAVAKHAR
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2018First promiseDec 2022Revised toMar 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Apr 2018
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed123 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DAVAKHAR ELEGANCENA290000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 99%.

DAVAKHAR ELEGANCE: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Progress on shared amenities15

As on 9 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed138

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots138
Closed/Covered135
Open Space3

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,800 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10500.0
Proposed, not sanctioned7,978 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWAGLE ESTATE THANE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDECON CONSUTALANTS
EngineerMANOHAR PATIL AND ASSOCIATES
PartnerRole in project
DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018200Dec 2022 → Jun 2024

Reason as filed by the promoterAs per attachment

EXT51700012955Dec 2022 → Dec 2023

Reason as filed by the promoterWe, Davakhar Infrastructure Private Limited, have registered for our real estate project "Davakhar Elegance" bearing registration no. P51700016124. The date of completion of the project was given as 30.12.2023 at the time of registration. However, we couldn’t complete said project within the stipulated period due to shortage of sand, inadequate labour supply and changes in policies. The finishing work, fire-fighting NOC, electricity main line connection and solar work are yet to be completed. We request to kindly accept our application and grant us the extension till 30.12.2023.

EXT51700024230Dec 2022 → Mar 2027

Reason as filed by the promoterWe, Davakhar Infrastructure Private Limited, have registered for our real estate project &quote Davakhar Elegance &quote bearing registration no. P51700016124.We had obtained extension for the project as per order 40A till 30.06.2024. We have received part completion certificate till 25 th Floor on 20.12.2023. We have already handed over possession of the flats till 25 th Floor. We had already applied for full completion certificate on 28.12.2023. However, due to assembly elections, the officers were not in the corporation and the application is still pending. We have obtained consent of allot

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000334056vijay karbhari barkaleDAVKHAR INFRASTRUCTURE PVT LTD20/01/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Jan 2024

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 FY 2023-24 Sign.pdf9 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf4 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (2).pdf18 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (2).pdf18 Jun 2024
Disclosure of sold/ booked inventoryFile: Sold and Unsold.pdf15 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Structural Engineer Certificate.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SE Certificate 31 Mar 19.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cost Estimate Structural Engineer 15Oct19-compressed.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: March 20.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sep 20(2).pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SE Certificate 31 Dec 21.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Structural Engineer 31 Mar 21.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Apr to June 2021.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 March 22.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30 Dec 22.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sep 18.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dec - 19.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: June 19.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: June 20.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30 June 22_compressed.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form II 30 Sept 22.pdf12 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31-03-20.pdf11 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 31-03-21.pdf11 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 31-03-22.pdf11 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 31-03-23.pdf11 Jan 2024
Disclosure of sold/ booked inventoryFile: Unsold Inventory1.pdf11 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (1).pdf11 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: scan0018_compressed.pdf4 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR LATTER WORK DONE (1).pdf28 Dec 2023
Other - TechnicalFile: Scan_20231228_123846.pdf28 Dec 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf27 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: DIPL RERA Form 5 Phase I.pdf30 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form I Pahse 1 30-9-23.pdf21 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cost Estimate Structural Engineer 30 Sept 23.pdf21 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase I 31st Mar 23.pdf8 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase I 30 June 23 (1).pdf8 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cost Estimate Structural Engineer 31-03-23.pdf8 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cost Estimate Structural Engineer 30-06-23.pdf8 Aug 2023
Certificates of CA (Form 3)File: Form 3.pdf11 Jan 2023
Certificates of CA (Form 3)File: form 3 fINAL.pdf11 Jan 2023
Certificates of CA (Form 3)File: FORM 3.pdf11 Jan 2023
Certificates of CA (Form 3)File: FORM 3_compressed (3).pdf11 Jan 2023
Certificates of CA (Form 3)File: Form 3 Sep 2019_compressed.pdf11 Jan 2023
Certificates of CA (Form 3)File: IMG_compressed.pdf11 Jan 2023
Certificates of CA (Form 3)File: FORM-3-DAVAKHAR ELEGANCE-SIGNED.pdf11 Jan 2023
Certificates of CA (Form 3)File: FORM-3-Signed.pdf11 Jan 2023
Certificates of CA (Form 3)File: Form 3 fINAL.pdf11 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.pdf11 Jan 2023
Certificates of CA (Form 3)File: Form 3 Scanned.pdf24 Nov 2022
Certificates of CA (Form 3)File: Form 3 Scanned.pdf22 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 DIPL FY 2021 22.pdf15 Nov 2022
Layout approvalFile: HPSCANNER1188-converted_11zon.pdf1 Apr 2022
Layout approvalFile: HPSCANNER1189.pdf1 Apr 2022
Building plan approvalFile: HPSCANNER1188-converted_11zon.pdf1 Apr 2022
Building plan approvalFile: HPSCANNER1189.pdf1 Apr 2022
Copy of Layout Approval (in case of layout)File: HPSCANNER1188-converted_11zon.pdf1 Apr 2022
Copy of Layout Approval (in case of layout)File: HPSCANNER1189.pdf1 Apr 2022
Building Plan Approval (IOD)File: HPSCANNER1188-converted_11zon.pdf1 Apr 2022
Building Plan Approval (IOD)File: HPSCANNER1189.pdf1 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised CC 26 Floors.pdf1 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised CC 26 Floors.pdf1 Apr 2022
Certificates of CA (Form 3)File: Form 3 Davakhar Elegance scan_compressed.pdf9 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf20 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-c.pdf20 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200228105939_For_Asset_Based_Search_14_01_2022_18_17_32_629.pdf14 Jan 2022
Layout approvalFile: Copy1.pdf10 Dec 2021
Layout approvalFile: COPY2.pdf10 Dec 2021
Layout approvalFile: COPY3.pdf10 Dec 2021
Copy of Layout Approval (in case of layout)File: Copy1.pdf10 Dec 2021
Copy of Layout Approval (in case of layout)File: COPY2.pdf10 Dec 2021
Copy of Layout Approval (in case of layout)File: COPY3.pdf10 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf10 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: fORM-2.pdf9 Dec 2021
CERSAI detailsFile: FORM-2.pdf9 Dec 2021
OtherFile: Allottees Consent_merged_compressed.pdf9 Dec 2021
Declaration about Commencement CertificateFile: format d.pdf8 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Certificate Phase II.pdf8 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf26 Oct 2021
Certificates of CA (Form 3)File: FORM 3.pdf26 Oct 2021

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 51 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DAVAKHAR ELEGANCE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN EAST7,600+ in Thane

2 kmDAVAKHAR ELEGANCECompleted 22Lapsed / revoked 19Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 125 registered projects within 2 km.

Builder: DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED

DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED has 6 registrations on MahaRERA, including DAVAKHAR ELEGANCE and Davakhar Elegance Phase II. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if DAVAKHAR ELEGANCE is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DAVAKHAR ELEGANCE?

The registered promoter entity is DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Its CIN U45400MH2010PTC199726 and GSTIN 27AADCD3567H1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DAVAKHAR ELEGANCE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DAVAKHAR ELEGANCE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DAVAKHAR ELEGANCE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DAVAKHAR ELEGANCE?

The professionals named in the filing: Architect: DECON CONSUTALANTS; Engineer: MANOHAR PATIL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DAVAKHAR ELEGANCE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DAVAKHAR ELEGANCE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DAVAKHAR ELEGANCE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.