Home / Browse projects / Thane, Maharashtra / Davakhar Elegance Phase II

Registration lapsed No litigation declared Others project

Davakhar Elegance Phase II

By DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED

RG-MH-81893 · RERA P51700046008 · Last updated on MahaRERA portal: 19 Aug 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 6 months past the filed date
  • Completion date moved by 25 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2026Possession promised6 months past this date
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 99%
20 of 38Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

Davakhar Elegance Phase II is a Others project by DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700046008 on 15 Jun 2022. Possession was promised by 29 Apr 2026 and is now 6 months past that date. The completion date has moved by 25 months from the original filing. 18 of the 38 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameDavakhar Elegance Phase II
  • TypeOthers
  • Location
    • Opp Essar Petrol Pump
    • Kalyan East
    • Pisawali
    • Kalyan
    • Thane
    • 421306
  • Pincode421306
  • RERA no.P51700046008
  • ReraGenie IDRG-MH-81893

Builder

  • NameDAVAKHAR INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • CINU45400MH2010PTC199726
  • GSTIN27AADCD3567H1ZK
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorSOPAN GOPAL DAVAKHAR
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

6 months past promisethis monthRegisteredJun 2022First promiseMar 2024Revised toApr 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Jun 2022
  • Promised completion29 Apr 2026
  • Revised completionRevised to 29 Apr 2026 (originally 31 Mar 2024)
  • Buildings1 building record
  • Documents filed88 files

Current status

47%18 of 38 units booked
98.0%Work done, per cost certificate

Figures as on 19 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building no 2NA88122638

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 99%.

Building no 2: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 19 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed102

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots102
Closed/Covered102

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area750 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 May 2025

Approvals and building plan

Sanctioning authorityKALYAN DOMBIVALI MUNICIPAL CORPORATION
Permissible FSI3091.06
Proposed, not sanctioned3,091 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRoad No 23, Wagle Industrial Estate Thane 400604
Estimated costRs 8.50 cr
Cost incurredRs 8.33 cr
Work done98.0%
BuildingWingEstimatedIncurred
Building no 2NARs 8.50 crRs 8.33 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDecon Consultants
EngineerManohar Patil & Associates
Chartered AccountantAnkit Paras Jain & Co
Chartered AccountantMayur Jain
PartnerRole in project
DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019481Mar 2024 → Mar 2025

Reason as filed by the promoterwe could not complete the said project within stipulated period due to shortage of sand, inadequate labour supply and changes in policies. The finishing work, fire fighting NOC, electricity main line connection and solar work are yet to be completed. we request you to kindly grant extension till 31.03.2025

EA19052501176Mar 2024 → Mar 2026

Reason as filed by the promoterWe say that our project 80% completed in March-2025. However, we have sold 18 units till dated. Hence, there is an issue for cash flow for the project. There are some inquiries from customer for flats/shops and we are expecting the said inquiries shall be converted into bookings. Considering this situation, we assure you that we shall complete the project by 31.03.2026 in all aspect. Hence, we want to apply for extension for 1 year till 31.03.2026.

EA19082622232Mar 2024 → Apr 2026

Reason as filed by the promoterThe project received its Occupancy Certificate (OC) on 29.04.2026. However, the approved project completion date was 31.03.2026. Since the completion date had already expired before the OC was received, the project has been marked as lapsed, and the completion status is currently not getting updated. Therefore, we are applying for an extension of the project completion date in RERA to regularize the project status and update the completion details accordingly.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form-2A 31-03-2025.pdf19 Aug 2026
Form 2A (FY 2024-2025)File: Form-2A 31-03-2025.pdf19 Aug 2026
Form 2A (FY 2025-2026)File: Form-2A 31-03-2026.pdf19 Aug 2026
Form 5 (FY 2024-2025)File: Form-5.pdf19 Aug 2026
Form 5 (FY 2024-2025)File: Form-5.pdf19 Aug 2026
Layout approvalFile: ELEGANCE PLAN_1.pdf31 Jul 2026
Building plan approvalFile: ELEGANCE PLAN_2.pdf31 Jul 2026
Building plan approvalFile: ELEGANCE PLAN_3.pdf31 Jul 2026
Declaration and undertaking (Annexure A)File: Undertaking.pdf31 Jul 2026
Withdrawal Update Form 1File: Final Form-1 31-03-2026 Signed.pdf21 May 2026
Withdrawal Update Form 2File: Form 2 Mar 26 DE 2 (1).pdf21 May 2026
Withdrawal Update Form 3File: Form-3 Davakhar Elegance Phase-II 31-03-2026 Signed.pdf21 May 2026
Withdrawal Update Form 1File: Form 1 30-06-2025.pdf23 Feb 2026
Withdrawal Update Form 1File: Form 1 Sept 25 De 1.pdf23 Feb 2026
Withdrawal Update Form 1File: Form 1 DEc 25 De 1.pdf23 Feb 2026
Withdrawal Update Form 2File: Form-2 30-06-2025.pdf23 Feb 2026
Withdrawal Update Form 2File: Form 2 Sept 25 DE 2.pdf23 Feb 2026
Withdrawal Update Form 2File: Form 2 Dec 25 DE 2.pdf23 Feb 2026
Withdrawal Update Form 3File: Form-3 30-06-2025 Signed.pdf23 Feb 2026
Withdrawal Update Form 3File: Form 3 Sept.pdf23 Feb 2026
Withdrawal Update Form 3File: Fomr 3 Dec.pdf23 Feb 2026
Form 1File: Form-1 30-06-2024.pdf25 Aug 2025
Form 2File: Form-2 30-06-2024.pdf25 Aug 2025
Form 3File: Form-3 30-06-2024.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold List 30-06-2024.pdf25 Aug 2025
Form 1File: Form-1 30-09-2024.pdf25 Aug 2025
Form 2File: Form-2 30-09-2024.pdf25 Aug 2025
Form 3File: Form-3 30-09-2024.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold UNsold List 30-09-2024.pdf25 Aug 2025
Form 1File: Form-1 31-12-2024.pdf25 Aug 2025
Form 2File: Form-2 31-12-2024.pdf25 Aug 2025
Form 3File: Form-3 31-12-2024.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold List 30-06-2025.pdf25 Aug 2025
Form 1File: Form-1 31-03-25.pdf25 Aug 2025
Form 2File: Form-2 31-March-2025.pdf25 Aug 2025
Form 3File: Form-3 All Page Signed.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold List 31-03-2025.pdf25 Aug 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A- 31-03-2024 Sing.pdf25 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (2).pdf18 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 31-03-23.pdf12 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf12 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 31-12-2023 (1)_compressed.pdf3 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 31-03-2024_compressed.pdf3 May 2024
Declaration in FORM BFile: Form B Davkhar Elegance Ph II_compressed.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC 31-12-23.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC 31-03-24.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SE 31-12-23.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SE 31-12-23.pdf26 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold and Unsold 31-12-2023.pdf26 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold And Unsold 31-03-2024.pdf26 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Davakhar cc.pdf30 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: DIPL RERA Form 5 Phase II.pdf30 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase 2 30-9-23.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase 2 30-9-23.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cost Estimate Structural Engineer 30-09-23.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Phase II 31st Mar 23.pdf8 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Phase II 30 June 23.pdf8 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cost Estimate Structural Engineer 31-03-23 (1).pdf8 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cost Estimate Structural Engineer 30-06-23.pdf8 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Davkhar Infrastructure Phase 2.pdf8 Aug 2023
Disclosure of sold/ booked inventoryFile: Adobe Scan 15 Jul 2022 (1).pdf15 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: revised commencement certificate_compressed.pdf1 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Davakhar Elegance Revised CC Compressed.pdf1 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Davkhar Form 3_Signed.pdf1 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-both party signed.pdf2 Jun 2022
Copy of the legal title reportFile: Title Report1_compressed.pdf28 May 2022
Copy of the legal title reportFile: Title Report2_compressed.pdf28 May 2022
Copy of the legal title reportFile: Title Report3_compressed.pdf28 May 2022
Layout approvalFile: Plan copy-1 (1).pdf24 May 2022
Layout approvalFile: Plan copy-2.pdf24 May 2022
Building plan approvalFile: Plan copy-1 (1).pdf24 May 2022
Building plan approvalFile: Plan copy-2.pdf24 May 2022
PAN CardFile: Davakhar Pan.pdf24 May 2022
Details of encumbrancesFile: No encrumbrances Letter on Letter Head_compressed.pdf24 May 2022
Copy of Layout Approval (in case of layout)File: Plan copy-1 (1).pdf24 May 2022
Copy of Layout Approval (in case of layout)File: Plan copy-2.pdf24 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan copy-1 (1).pdf24 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan copy-2.pdf24 May 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf24 May 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
DAVAKHAR ELEGANCEP51700016124KALYAN EAST, ThaneApr 2018OngoingDec 2022Not delivered

How this compares with Thane

47%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 25 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Davakhar Elegance Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kalyan East7,600+ in Thane

Builder: DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED

DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED has 6 registrations on MahaRERA, including DAVAKHAR ELEGANCE and Davakhar Elegance Phase II. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Davakhar Elegance Phase II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Davakhar Elegance Phase II is delayed beyond 29 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Davakhar Elegance Phase II?

The registered promoter entity is DAVAKHAR INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Its CIN U45400MH2010PTC199726 and GSTIN 27AADCD3567H1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Davakhar Elegance Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Davakhar Elegance Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Davakhar Elegance Phase II?

The professionals named in the filing: Architect: Decon Consultants; Engineer: Manohar Patil & Associates; Chartered Accountant: Ankit Paras Jain & Co; Chartered Accountant: Mayur Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Davakhar Elegance Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Davakhar Elegance Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Davakhar Elegance Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.