Home / Browse projects / Sindhudurg, Maharashtra / DATTAKRUPA APARTMENT

Registration lapsed No litigation declared Others project

DATTAKRUPA APARTMENT

By MAHALAXMI ENTERPRISES

RG-MH-62842 · RERA P52900016742 · Last updated on MahaRERA portal: 29 May 2018

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 55%
1Complaints at MahaRERAon this registration
Jump to the 15 documents Report an error

DATTAKRUPA APARTMENT is a Others project by MAHALAXMI ENTERPRISES in Sindhudurg, Maharashtra, registered with MahaRERA as P52900016742 on 12 Jun 2018. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 18 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameDATTAKRUPA APARTMENT
  • TypeOthers
  • Location
    • SAWANTWADI
    • Sawantwadi (M Cl)
    • Sindhudurg
    • 416510
  • Pincode416510
  • RERA no.P52900016742
  • ReraGenie IDRG-MH-62842

Builder

  • NameMAHALAXMI ENTERPRISES
  • Entity typePartnership
  • PartnersBHERULAL CHAGANLAL JAIN, RAVIKIRAN DHARMAJI TODANKAR, KISHAN KALURAM KUMAR
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live4 lapsed, de-registered or revoked

Key dates

52 months past promisethis monthRegisteredJun 2018First promiseDec 2020Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Jun 2018
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Dec 2020)
  • Buildings2 building records
  • Documents filed15 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WING OF THE I PHASENA60000
B WING OF THE I PHASENA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 May 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 55%.

A WING OF THE I PHASE56%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING OF THE I PHASE58%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 May 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered8
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
A WING OF THE I PHASE426
B WING OF THE I PHASE426

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,620 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2589.0
Proposed, not sanctioned2,589 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKARJAT

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJ ASSOCIATES
EngineerATUL KUDTARKAR
PartnerRole in project
MAHALAXMI ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52900008927Dec 2020 → Dec 2021

Reason as filed by the promoterDUE TO COVID-19 SITE WAS NOT OPERATIONAL TILL NOVEMBER -2020 HENSE WE SEEK AN EXTENTION UPTO 31-12-2021

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000397346VIKRANT VIJAY PARABSUNILKUMAR RAMSWAROOP SONI - Partner & Power of Attorney Holder Mahalaxmi Enterprises08/09/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed15

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: Letter for Delay in Rera Reg.pdf29 May 2018
Certificates of CA (Form 3)File: Mahalaxmi Enterprises CA Certificate.pdf22 May 2018
Proforma of Allotment letterFile: DRAF AGREEMENT MAHALAXMI ENTERPRISES.pdf22 May 2018
Details of encumbrancesFile: Non Encumbrances Certificate.pdf14 May 2018
Declaration in FORM BFile: FORM B.pdf14 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mahalaxmi Enterprises Architect Certificate.pdf14 May 2018
Proforma of Allotment letterFile: Allotment Letter.pdf14 May 2018
Building plan approvalFile: MYSCAN_20180314_0002 (2).pdf9 May 2018
Layout approvalFile: MYSCAN_20180314_0002 (2).pdf9 May 2018
PAN CardFile: PAN CARD20180509_16274332.pdf9 May 2018
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf9 May 2018
Copy of Layout Approval (in case of layout)File: MYSCAN_20180314_0002 (2).pdf9 May 2018
Building Plan Approval (IOD)File: MYSCAN_20180314_0002 (2).pdf9 May 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf9 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERING CERTIFICATE.pdf9 May 2018

How this compares with Sindhudurg

21%of Sindhudurg projects moved their completion datethis one moved by 18 months
30%of Sindhudurg registrations have lapsed or been cancelledthis one is among them

Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.

Keep DATTAKRUPA APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SAWANTWADI530+ in Sindhudurg

Builder: MAHALAXMI ENTERPRISES

MAHALAXMI ENTERPRISES has 6 registrations on MahaRERA, including KINGSTON COURT and MAHALAXMI KRUPA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sindhudurg district page.

Frequently asked questions

What does it mean that DATTAKRUPA APARTMENT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DATTAKRUPA APARTMENT is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DATTAKRUPA APARTMENT?

The registered promoter entity is MAHALAXMI ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DATTAKRUPA APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DATTAKRUPA APARTMENT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DATTAKRUPA APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DATTAKRUPA APARTMENT?

The professionals named in the filing: Architect: RAJ ASSOCIATES; Engineer: ATUL KUDTARKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DATTAKRUPA APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DATTAKRUPA APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DATTAKRUPA APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.