Home / Browse projects / Amravati, Maharashtra / DATTA NAGARI 2

Registration lapsed No litigation declared Plotted project

DATTA NAGARI 2

By Vijay Nanakram Talda

RG-MH-05022 · RERA P50300053198 · Last updated on MahaRERA portal: 19 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Amravati registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
50 of 50Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 35 documents Report an error

DATTA NAGARI 2 is a Plotted project by Vijay Nanakram Talda in Amravati, Maharashtra, registered with MahaRERA as P50300053198 on 23 Oct 2023. Possession was promised by 31 Mar 2025 and is now 19 months past that date. 0 of the 50 units on this registration are recorded sold or booked.

At a glance

Project

  • NameDATTA NAGARI 2
  • TypePlotted
  • Location
    • BEHIND RAJ TOWNSHIP
    • BADNERA
    • Amravati
    • 444701
  • Pincode444701
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50300053198
  • ReraGenie IDRG-MH-05022

Builder

  • NameVijay Nanakram Talda
  • Entity typeIndividual
  • Other registrations6 more →
  • Completed5 of 7
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

19 months past promisethis monthRegisteredOct 2023PromisedMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Oct 2023
  • Promised completion31 Mar 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed35 files

Current status

0%0 of 50 units booked

Figures as on 19 Feb 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 19 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,666 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7665.62
Proposed, not sanctioned7,666 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVIMACO TOWER BUS STAND ROAD AMRAVATI 444601

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTANUJ TARACHAND JANGADA
EngineerTANUJ TARACHAND JANGADA
Chartered AccountantCA DEEPAK ZAMBANI GAD AND ASSOCIATES
PartnerRole in project
Vijay Nanakram Talda-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Feb 2025

Documents filed35

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DATTA NAGARI 2 FORM 3.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DATTA NAGARI 2 FORM 2.pdf19 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Tanuj Datta nagari 2.pdf18 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_Datta Nagari 2 310324.pdf14 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Datta Nagari 2 NA Order.pdf19 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Datta Nagari 2_Antim Manjuri.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 2 DN .pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: DATTA NAGARI 2 SOLD 300624.pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DATTA NAGARI 2 FORM 3 12-7.pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DATTANAGRI -RERA.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: DATTANAGARI 2.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Datta Nagari 2.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Datta Nagari 2_Form 2 311223.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Datta Nagari 2_Sold 311223.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Datta nagari 2 Form 3_311223.pdf17 Jan 2024
CERSAI detailsFile: Datta Nagari 2_Cersai.pdf13 Oct 2023
Other - TechnicalFile: Datta Nagari 2_Mail.pdf13 Oct 2023
Copy of the legal title reportFile: Datta Nagari 2_Search Report.pdf10 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Datta Nagari 2_Form 3.pdf10 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Datta Nagari 2_Annexure A Other Interest.pdf10 Oct 2023
Proforma of Agreement for saleFile: Datta Nagari 2_Agreement for Sale.pdf10 Oct 2023
Layout approvalFile: Datta Nagari 2_Techincal Map.pdf9 Oct 2023
Building plan approval or NA orderFile: Datta Nagari 2_Techincal Map.pdf9 Oct 2023
PAN CardFile: Datta Nagari 1_pan cARD.pdf9 Oct 2023
Details of encumbrances concerned to FinanceFile: Datta Nagari 2_Encumberance.pdf9 Oct 2023
Details of encumbrances concerned to LegalFile: Datta Nagari 2_Encumberance.pdf9 Oct 2023
Copy of Layout Approval (in case of layout)File: Datta Nagari 2_Techincal Map.pdf9 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Datta Nagari 2_Techincal Map.pdf9 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Datta Nagari 2_Techincal Sanction Letter.pdf9 Oct 2023
Declaration about Commencement CertificateFile: Datta Nagari 2_C C Declaration.pdf9 Oct 2023
Declaration in FORM BFile: Datta Nagari 2_Form B.pdf9 Oct 2023
Proforma of Allotment letterFile: Datta Nagari 2_Allotment Letter.pdf9 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Datta Nagari 2_Format A Bank.pdf9 Oct 2023
Deviation Report with respect to Allotment letterFile: Datta Nagari 2_Deviation Allotment Letter.pdf9 Oct 2023
Deviation Report with respect to model copy of AgreementFile: Datta Nagari 2_Deviation ATS.pdf9 Oct 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Govinda Residencymaloo and talda layout26CompletedJun 2016Late, Jul 2016

How this compares with Amravati

0%of this project is bookeddistrict median 0%
8%of Amravati projects moved their completion datethis one has not
33%of Amravati registrations have lapsed or been cancelledthis one is among them

Computed across the 450+ Amravati projects on ReraGenie, from their own filings.

Keep DATTA NAGARI 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BADNERA450+ in Amravati

2 kmDATTA NAGARI 2Completed 3Lapsed / revoked 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: Vijay Nanakram Talda

Vijay Nanakram Talda has 7 registrations on MahaRERA, including GOVINDA SKY and Vrundawan by Govinda Group. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Amravati district page.

Frequently asked questions

What does it mean that DATTA NAGARI 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DATTA NAGARI 2 is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DATTA NAGARI 2?

The registered promoter entity is Vijay Nanakram Talda, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DATTA NAGARI 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DATTA NAGARI 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DATTA NAGARI 2?

The professionals named in the filing: Architect: TANUJ TARACHAND JANGADA; Engineer: TANUJ TARACHAND JANGADA; Chartered Accountant: CA DEEPAK ZAMBANI GAD AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DATTA NAGARI 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DATTA NAGARI 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DATTA NAGARI 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.