Home / Areas / Amravati

New projects and RERA data in Amravati district, Maharashtra

449 of the projects in this build are in Amravati district: 5,168 units across them, 21 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

449Projects in this build
21Registered, last 12 months
5,168Units declared
4,446Units not yet booked
35Completion dates revised
0With declared litigation

Of the 449 covered registrations, 35 have revised their promised completion date and 0 declare litigation. The median project here is 0% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.

When Amravati projects promise possession

Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 449 projects with a promised date, 202 are recorded delivered, 91 are still on the register and 156 have a registration that has lapsed or been cancelled.

DeliveredOn the registerRegistration lapsed or cancelled

0255075100today2017: 3 projects, delivered2017: 2 projects, registration lapsed or cancelled’172018: 14 projects, delivered2018: 3 projects, registration lapsed or cancelled’182019: 38 projects, delivered2019: 2 projects, registration lapsed or cancelled’192020: 16 projects, delivered2020: 15 projects, registration lapsed or cancelled’202021: 16 projects, delivered2021: 12 projects, registration lapsed or cancelled’212022: 32 projects, delivered2022: 20 projects, registration lapsed or cancelled’222023: 27 projects, delivered2023: 21 projects, registration lapsed or cancelled’232024: 23 projects, delivered2024: 23 projects, registration lapsed or cancelled’242025: 14 projects, delivered2025: 43 projects, registration lapsed or cancelled’252026: 9 projects, delivered2026: 15 projects, on the register2026: 14 projects, registration lapsed or cancelled’262027: 4 projects, delivered2027: 26 projects, on the register’272028: 3 projects, delivered2028: 26 projects, on the register2028: 1 projects, registration lapsed or cancelled’282029: 2 projects, delivered2029: 16 projects, on the register’292030: 1 projects, delivered2030: 5 projects, on the register’302031: 2 projects, on the register’312032: 1 projects, on the register’32

125 projects promise possession in 2026 or later. Facts as per filings on RERA website.

02505007501,000today’172018: 35 flats, registration lapsed or cancelled (only 1 of 17 projects filed a flat count)’182019: 219 flats, delivered (only 7 of 40 projects filed a flat count)’192020: 30 flats, delivered (only 2 of 31 projects filed a flat count)2020: 126 flats, registration lapsed or cancelled (only 2 of 31 projects filed a flat count)’202021: 49 flats, registration lapsed or cancelled (only 2 of 28 projects filed a flat count)’212022: 432 flats, delivered (only 5 of 52 projects filed a flat count)2022: 32 flats, registration lapsed or cancelled (only 5 of 52 projects filed a flat count)’222023: 225 flats, registration lapsed or cancelled (only 3 of 48 projects filed a flat count)’232024: 43 flats, delivered (only 3 of 46 projects filed a flat count)2024: 59 flats, registration lapsed or cancelled (only 3 of 46 projects filed a flat count)’242025: 558 flats, registration lapsed or cancelled (only 11 of 57 projects filed a flat count)’252026: 32 flats, delivered (only 11 of 38 projects filed a flat count)2026: 574 flats, on the register (only 11 of 38 projects filed a flat count)2026: 175 flats, registration lapsed or cancelled (only 11 of 38 projects filed a flat count)’262027: 41 flats, delivered (only 10 of 30 projects filed a flat count)2027: 306 flats, on the register (only 10 of 30 projects filed a flat count)’272028: 28 flats, delivered2028: 874 flats, on the register’282029: 591 flats, on the register’292030: 382 flats, on the register’302031: 269 flats, on the register’312032: 88 flats, on the register’32

3,360 flats are promised in 2026 or later, across the 49% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.

How far Amravati possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 35 of 449 projects (8%) have moved at least once; the median move is 18 months and the longest is 73 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

0255075100Originally due 2017: 5 projects kept the original date, 100% of the year’17Originally due 2018: 17 projects kept the original date, 71% of the yearOriginally due 2018: 4 projects moved by under 2 years, 17% of the yearOriginally due 2018: 3 projects moved by 2 years or more, 12% of the year’18Originally due 2019: 38 projects kept the original date, 86% of the yearOriginally due 2019: 4 projects moved by under 2 years, 9% of the yearOriginally due 2019: 2 projects moved by 2 years or more, 5% of the year’19Originally due 2020: 26 projects kept the original date, 84% of the yearOriginally due 2020: 2 projects moved by under 2 years, 6% of the yearOriginally due 2020: 3 projects moved by 2 years or more, 10% of the year’20Originally due 2021: 22 projects kept the original date, 85% of the yearOriginally due 2021: 4 projects moved by under 2 years, 15% of the year’21Originally due 2022: 48 projects kept the original date, 96% of the yearOriginally due 2022: 1 projects moved by under 2 years, 2% of the yearOriginally due 2022: 1 projects moved by 2 years or more, 2% of the year’22Originally due 2023: 43 projects kept the original date, 98% of the yearOriginally due 2023: 1 projects moved by under 2 years, 2% of the year’23Originally due 2024: 45 projects kept the original date, 92% of the yearOriginally due 2024: 2 projects moved by under 2 years, 4% of the yearOriginally due 2024: 2 projects moved by 2 years or more, 4% of the year’24Originally due 2025: 54 projects kept the original date, 92% of the yearOriginally due 2025: 4 projects moved by under 2 years, 7% of the yearOriginally due 2025: 1 projects moved by 2 years or more, 2% of the year’25Originally due 2026: 33 projects kept the original date, 97% of the yearOriginally due 2026: 1 projects moved by under 2 years, 3% of the year’26Originally due 2027: 29 projects kept the original date, 100% of the year’27Originally due 2028: 29 projects kept the original date, 100% of the year’28Originally due 2029: 16 projects kept the original date, 100% of the year’29Originally due 2030: 6 projects kept the original date, 100% of the year’30Originally due 2031: 2 projects kept the original date, 100% of the year’31Originally due 2032: 1 projects kept the original date, 100% of the year’32

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

05001,0001,5002,000’17Originally due 2018: 35 flats kept the original date, 71% of the year (only 1 of 24 projects filed a flat count)’18Originally due 2019: 219 flats kept the original date, 86% of the year (only 8 of 44 projects filed a flat count)Originally due 2019: 126 flats moved by under 2 years, 9% of the year (only 8 of 44 projects filed a flat count)’19Originally due 2020: 30 flats kept the original date, 84% of the year (only 1 of 31 projects filed a flat count)’20Originally due 2021: 49 flats kept the original date, 85% of the year (only 2 of 26 projects filed a flat count)’21Originally due 2022: 464 flats kept the original date, 96% of the year (only 5 of 50 projects filed a flat count)’22Originally due 2023: 225 flats kept the original date, 98% of the year (only 3 of 44 projects filed a flat count)’23Originally due 2024: 102 flats kept the original date, 92% of the year (only 4 of 49 projects filed a flat count)Originally due 2024: 49 flats moved by 2 years or more, 4% of the year (only 4 of 49 projects filed a flat count)’24Originally due 2025: 558 flats kept the original date, 92% of the year (only 15 of 59 projects filed a flat count)Originally due 2025: 530 flats moved by under 2 years, 7% of the year (only 15 of 59 projects filed a flat count)Originally due 2025: 162 flats moved by 2 years or more, 2% of the year (only 15 of 59 projects filed a flat count)’25Originally due 2026: 202 flats kept the original date, 97% of the year (only 8 of 34 projects filed a flat count)Originally due 2026: 29 flats moved by under 2 years, 3% of the year (only 8 of 34 projects filed a flat count)’26Originally due 2027: 318 flats kept the original date, 100% of the year (only 9 of 29 projects filed a flat count)’27Originally due 2028: 902 flats kept the original date, 100% of the year’28Originally due 2029: 429 flats kept the original date, 100% of the year’29Originally due 2030: 382 flats kept the original date, 100% of the year’30Originally due 2031: 269 flats kept the original date, 100% of the year’31Originally due 2032: 88 flats kept the original date, 100% of the year’32

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Projects in Amravati

ProjectDeveloperUnits BookedRegistered
GOVINDA NAGARISHRI GOVINDA PROPERTIES2110%31 Dec 2020
Jai Amba Palm City- Areca Palm Wing A,B,CGrand Palm City LLP2040%5 Mar 2026
AURA LIFESTYLELIFESTYLE HOME SPACES2000%18 Mar 2026
DATTA NAGARI 1Vijay Nanakram Talda1990%31 Oct 2023
Vivanta Infinity Private LimitedVIVANTA INFINITY PRIVATE LIMITED19765%15 Oct 2021
DCC Dreamz City ChambersDREAMZ-CITY REAL ESTATE PVT LTD17920%7 Dec 2022
PARIKRAMA GREENSNITIN JUGALKISHOR CHENDULKAR16239%31 Aug 2017
SAHYADRI HEIGHTSANSHUMAN BUILDERS15436%22 Jun 2022
SHRI GURU ANAND DHAMSudhir Rameshrao Wakode12623%30 Nov 2017
SANKALP ICONSANKALP DREAM SPACES LLP1260%29 Apr 2026
RACHANA SRUSHTI PHASE IISRUSHTI INFRA12410%15 Feb 2023
KESHAV EMPIRE PHASE IISACHIN KESHAORAO INGOLE1128%28 Nov 2023
CHANDANVADISHRI AMARNATH BUILDERS AND DEVELOPERS979%14 Mar 2022
VEDAH PHASE 1TRENDBUILT LIFESPACES LLP880%6 Apr 2026
Jai Amba Palm City- Queen Palm Wing A BM/s Grand Palm City LLP880%4 Jun 2026
Radha CityKrishnagiri Developers860%12 Mar 2020
Radha CityRavi sahu, Rupesh sahu And Deepak sahu850%18 Mar 2020
SHREEKRUPA TOWNSHIPCHHUGARAM LAHORIMAL KHATRI (HUF)840%23 Jan 2019
VIJAYSHREE PARKPANKAJKUMAR RAMESHRAO DESHMUKH8415%21 Nov 2022
Madhavam HeightsSky Line Infra Vision770%6 Aug 2024
SHIVA SHRI APARTMENTJog Mahajan Infra Privet Limited7262%19 Jan 2023
Lucky Orange CityIqbal Haroon Kasmani690%24 Dec 2019
CASA GrandParas Buildcom6816%27 Jun 2023
Radha CityRahul sharma And Yogesh Gawande660%12 Mar 2020
Harmony PrathameshRadha Shrihari Builders And Developers LLP6611%9 Aug 2024
SAMRA ONESAMRA LUXURY PRIVATE LIMITED650%30 Dec 2025
SHIVRAY COMMERCIALSHIVRAY BUILDER5821%15 Feb 2024
Green HeightsAksha Builder and Developers564%1 Jul 2020
MY ORCHID HEIGHTS PHASE INitin Bhatkar5620%31 May 2024
LIFESTYLE HOMESLIFESTYLE HOME SPACES5520%25 Jan 2024
AMBER PRIDEABHIMANYU SANJAY RATHI520%8 Oct 2024
Aakar RegencyROHIT ASHOKRAO JIWARKAR5116%21 Jan 2025
UDAY NAGAR LAYOUT DDEVENDRA RAMACHANDRA CHANDAK500%2 Nov 2017
DATTA NAGARI 2Vijay Nanakram Talda500%23 Oct 2023
SUMERU VEDANTA 2MARIGOLD REALITY4982%13 Sep 2021
UDAY NAGAR LAYOUT AUMESH RAMCHANDRA CHANDAK480%2 Nov 2017
MOUJE BADNERA SURVEY NO. 13/2 A AND BSUBHASH NANAKRAM TALDA482%23 May 2018
DATTA DHAMMITRANGAN BUILDER & DEVELOPERS480%6 Jan 2020
VARMA HEIGHTSDILIP NANDKISHOR VARMA460%28 Feb 2025
ROYAL TOWERANIL LAXMICHAND BOTHRA440%22 Sep 2023
MIDAS HEIGHTSVASAVI VENTURE430%15 Oct 2021
Dwarka CityPraful Shingote and 1 Other4340%4 Aug 2022
Vedanta HeightsVedanta Buildcon4248%22 Sep 2023
AMRAVATI COMPLEXRANJANA SUNIL ZOMBADE4156%17 Oct 2023
Raghuvir IconDilip Mangalbhai Popat400%10 Jun 2026
VIJAY FORTUNEVIJAY PARANJAPE ESTATE LLP370%11 Feb 2026
Shree Shiv Gajanan ResidencyD.S Ganorkar and Company3631%29 Sep 2025
OMKAR GALAXYDinesh Ramraoji Dolare360%2 Mar 2026
ISHWARY COLONYSAI SRUJAN BUILDERS & DEVELOPERS350%23 Jan 2018
NAVODAYAChirag Vinod Jajoo350%13 Aug 2025
SOLARIS CUBESOLARIS INFRA350%11 Sep 2025
Crystal PlazaLAXMIKANT PRABHAKAR JOSHI333%24 Sep 2025
AFFORDABLE HOUSING PROJECT MOUJA RAHATGAON S NO 116/2 PLOT NUMBER 24 TO 28PMAY AMRAVATI MUNICIPAL CORPORATION320%23 Oct 2021
RUKHMINI HEIGHTSSADANI AND PATURDE BUILDERS LLP323%3 Jan 2024
SANJONI HEIGHTSADITYA ENGINEERS AND CONTRACTORS3244%1 Jul 2025
Vidhi HeightsVidhi Developers3222%1 Aug 2025
Decent Shraddha ResidencyJayant Parmanand Chhutlani320%10 Dec 2025
GOVINDA GARDEN CITYSUBHASH NANAKRAM TALDA300%16 May 2019
DCH CASTLEBLUSERA INFRASTRUCTURE3047%19 Jul 2023
Shree Gajanan ResidencySaurabh Construction and Developers303%19 Sep 2025
Amarsukh TowerRajeshkumar Amarlal Talreja290%17 Jan 2023
Midas EnclaveVasavi Lifespaces Private Limited2938%28 Jun 2024
UDAY PARK - LAYOUT CSAROJ UMESH CHANDAK280%7 Nov 2017
SHREE GAJANAN ENCLAVEAJAY NAMDEORAO DAMBALE280%29 May 2024
Shree Dwarka ResidencyMangesh Shyamrao Gulhane280%5 Mar 2026
Krushnayan VillasSanchit Pradip Patil2741%20 May 2025
GOVINDA SMART CITYSANJAY SHANKARLAL BATRA260%24 Apr 2018
Nimisha - 2Aditya Anagha Multi State Credit Co-Operative Society Limited2623%28 Jan 2025
Aarambh PrideAarambh Infracon LLp2524%3 Feb 2025
SHRI RHIDESHANANT KESHAORAO SAURKAR240%2 Jun 2025
NITYA:SHRI APARTMENTJog Mahajan Infra Private Limited240%3 Dec 2025
VIJAY PRIVILEGEVIJAY PARANJAPE ESTATE LLP240%22 Apr 2026
VEERA PRIMEVEERA BUILDERS240%29 Jun 2026
Galaxy TowerSky Line Builders And Developers2326%6 Jan 2023
SANKALP PEARLSANKALP PROPERTIES21100%20 Jan 2025
INDRAKSHI RESIDENCYPRAVIN SAHEBRAO MAHALLE2040%7 Jul 2023
AAI RESIDENCY IISAMIR HARIBHAU PANDE200%2 Apr 2024
Krushnayan PrimeRayaji Realty2075%14 Mar 2024
Shri Krushna ResidencyRAVINDRA PUNDLIKRAO MAHALLE2035%16 Jul 2024
Advik NestTathey Realty2010%10 Jun 2025
MAHALAKSHMI APARTMENTMegha Sachin Wankhade200%9 Mar 2026
Chanakya HeightsAshok Satyanrayan Joshi1811%6 Mar 2023
SAI AARYANHAJARE BUILDERS1712%12 Jan 2023
GALAXY TOWERFIROZKHAN MUSAKHAN160%8 Dec 2022
UDAY NAGAR -LAYOUT BPOONAM DEVENDRA CHANDAK150%20 Nov 2017
RATNA MAULIRATNA MAULI CONSTRUCTIONS140%4 Mar 2024
Gajanan TowerKAMAL DIGRILAL MALVIYA140%3 Jul 2024
Dwarkadhish ResidencyAshish Mohanrao Jirapure1217%26 Aug 2022
G B DESIREG B CONSTRUCTION120%12 Dec 2022
SHALINI RESIDENCYVIJAYSHALI ENTERPRISES PRIVATYE LIMITED12100%24 Feb 2023
Ganraya HeightsA B Associates119%27 Jun 2023
Chandak TowerChandak Construction90%1 Jun 2023
GOVINDA CITY - 1SHANKARLAL WADHUMAL BATRA40%30 Nov 2017
GOVIND PRIYAKIRIT JAYANTILAL KOTAK10%28 Dec 2018
VISTA IMPERIADEEPRAJAM INFRASPACE LLP10%15 May 2023
GOVINDA SKYVijay Nanakram Talda--18 Jul 2017
Naman ViharNAMAN VENTURES PRIVATE LIMITED--4 Aug 2017
SILVER OAK PLAZASAFFRON DEVELOPERS--31 Jul 2017
SHREE SHARDUL NESTSHARDUL ASSOCIATES--18 Aug 2017
GREEN PARKRAASHI BUILDERS AND DEVELOPERS LLP--31 Aug 2017
RASHI TRINITYRAASHI ASSOCIATES--17 Aug 2017
SHREE GURU PUSHP AMRUT PARIWARSudhir Rameshrao Wakode--23 Aug 2017
JANKI RESIDENCYAMIT VINOD SAHU--19 Aug 2017
JOG CHARITABLE MEDICAL RELIF FUND HOSPITAL AND RACHANASHRI COMMERCIALSM/S RACHANA BUILDERS AND DEVELOPERS--9 Aug 2017
PURVA RESIDENCY CONDOMINIUMNAKSHATRA BUILDERS & DEVELOPERS--19 Aug 2017
UTTARA RESIDENCY CONDOMINIUMNAKSHATRA BUILDERS & DEVELOPERS--14 Aug 2017
VIMACO RESIDENCY IIABBASALI AHTESHAM HUSAIN HAJI--9 Aug 2017
SHIVAJI ENCLAVE - 2SUBHASH DEVIDAS BHARSAKALE--18 Aug 2017
THE EMPIRE MALLSOL POWER PRIVATE LIMITED--24 Aug 2017
SAI HEIGHTSSAI HEIGHTS--31 Jul 2017
CHIRAG CITYCHIRAG CONSTRUCTIONS--23 Aug 2017
The Best ResidencyPawan Kisanrao Shende--18 Aug 2017
SHREE APPARTMENTSHARDUL ASSOCIATES--28 Mar 2018
RAJ TOWNSHIPRAJ ASSOCIATES--31 Aug 2017
Sai HeritageSai Datta Developers--31 Jul 2017
PRATIK TOWERKAMAL DIGRILAL MALVIYA--6 Aug 2017
MANAV MANDIRTARUN CONSTRUCTION COMPANY--17 Aug 2017
VARDVINAYAK RESIDENCYRAVI PANJABRAO GHURDE--6 Aug 2017
SAI SHRADDHA RESIDENCYSANCHIT BUILDERS AND INFRASTRUCTURE DEVELOPERS--31 Aug 2017
DEVI HEAVENDEVI INFRASPACE PRIVATE LIMITED--1 Aug 2017
EKDANT RESIDENCYR.S. CONSTRUCTION--23 Aug 2017
SAI CITYSSB ASSOCIATES--6 Aug 2017
SAI VIDHISSB ASSOCIATES--4 Aug 2017
ICON DREAMSICON BUILDERS--14 Sep 2017
NeetaShree ResidencyRohan Shrikrishna Chimote--4 Aug 2017
RANTHAMBORE CITY PHASE IRANTHAMBORE CITY--4 Aug 2017
VITTHALARPAN RESIDENCY-BDHANRAJ HARICHAND KHANDELWAL--7 Aug 2017
ADARSH RESIDENCYJITENDRA KESHWANI--9 Aug 2017
DREAMZ PARK WING ADREAMZ INFRASPACE--17 Aug 2017
DREAMZ PARK WING BDREAMZ INFRASPACE--11 Aug 2017
VIMACO GULMOHAR CONDOMINIUMABBASALI AHTESHAM HUSAIN HAJI--14 Aug 2017
Shri Govinda ImperialSHREE GOVINDA CONSTRUCTIONS--4 Aug 2017
Daga Sapphire InfinityDaga Infratech Pvt Ltd--17 Aug 2017
Dreamzland Business Park Phase IM/S DREAMZ INFRASTRUCTURE--9 Aug 2017
Dreamzland Business Park Phase IIM/S DREAMZ INFRASTRUCTURE--9 Aug 2017
THE VIDARBHA PREMIER AMBANAGRI KIRAN NAGAR AMRAVTIPRAKASH NARAYANRAO RAOLE--4 Oct 2017
VYANKATESH DEV RESIDENCYSHRI VYAANKATES ASSOCIATES--31 Aug 2017
SHRI KRISHNA VIHARSHAILESH INFRASTRUCTURE PRIVATE LIMITED--7 Aug 2017
Dreamzland Business Park PHASE IIIM/S DREAMZ INFRASTRUCTURE--9 Aug 2017
VENUS HEIGHTM/S S.NAVIN BUILDERS--19 Aug 2017
Dreamaland Business Park Phase No IVM/S DREAMZ INFRASTRUCTURE--8 Aug 2017
Dreamz LandmarkM/S DREAMZ INFRASTRUCTURE--10 Aug 2017
PLOT NO 802CITY LAND ASSOCIATES--14 Aug 2017
PLOT NO 804CITY LAND ASSOCIATES--7 Aug 2017
Aryavan HillsSomeshwar Vitthalrao Pusatkar--18 Aug 2017
SANKALP HEIGHTSANKALP INFRATECH--6 Aug 2017
SHRINIWASA 63 COMPLEXSHRINIWASA CONSTRUCTION--4 Sep 2017
WARDHEKAR COMPLEXSINDH ASSSOCIATE--14 Aug 2017
PLOT NO 805CITY LAND ASSOCIATES--9 Aug 2017
Shri Radha Krishna ResidencyPadm Builders--22 Aug 2017
SHIVANAND HEIGHTSSHIVANAND INFRASTRUCTURE--14 Aug 2017
SHREE SAI MEHER ENCLAVEOM SAI BUILDERS AND DEVELOPERS--11 Aug 2017
SHRI SAIKRUPA RESIDENCYSAVITA PRALHAD AGARKAR--11 Aug 2017
Shri Pinglai HeightsUnnati Infraspace Private Limited--6 Sep 2017
JAI BHOLE APARTMENTMOHIT ASSOCIATES--17 Aug 2017
SHRI GAJANAN TOWERTEJAS ASSOCIATES--5 Aug 2017
SUMERU MANGALAMNARENDRA PRATAPRAI KINGRANI--24 Aug 2017
KAUSHIK HEIGHTSARUN CONSTRUCTION COMPANY--22 Aug 2017
MANSAVALI RESIDENCYMANSAVALI BUILDERS & DEVELOPERS--10 Nov 2017
ORANGE COUNTYDNYANESHWAR NAMDEVRAO WANKHADE--31 Aug 2017
MAHALAXMI APARTMENT-VIIP S ASSOCIATES--22 Aug 2017
BHUMI LANDBHUMI LANDS--14 Aug 2017
SHREE GANESH RESIDENCYRAVINDRA PUNDLIKRAO MAHALLE--19 Aug 2017
SANKALP HEIGHTSSANKALP BUILDERS & DEVELOPERS--31 Aug 2017
HARIGANGA HEIGHTSKALASH LANDMARKS--31 Aug 2017
ASHWAMEDH RESIDENCYASHWAMEDH BUILDERS AND DEVELOPERS--22 Aug 2017
SALASAR ICON ADeoganga Builders And Developers--31 Aug 2017
AMBER HEIGHTSAMBER BUILDERS AND DEVELOPERS--31 Aug 2017
SHIVAJI SANKUL4SUBHASH DEVIDAS BHARSAKALE--31 Aug 2017
RAGHAV FLORENCERAGHAV BUILDERS AND DEVELOPERS--7 Nov 2017
SHIVAJI SANKUL 5SUBHASH DEVIDAS BHARSAKALE--31 Aug 2017
GOVIND NIILYAMSHRI GOVIND BUILDCON--4 Oct 2017
CITY CENTRE MALLTIRUPATI ASSOCIATES--7 Sep 2017
Shree Sai Shraddha ApartmentRajubhau Shankarrao Ingole--4 Sep 2017
SHREE JAI RESIDENCYSHREE KRUPA BUILDERS--21 Sep 2017
Rachayati EnclaveRachayati Realtors and Developers pvt ltd--13 Oct 2017
HARISHCHANDRA RESIDENCYPRATAP NARAYAN DESHMUKH--14 Sep 2017
SAI SAGAR ENCLAVE VSAGAR PANDHARINATH BANKAR--14 Sep 2017
YASHASVI-3MAHARUDRA INFRACOMBINES PRIVATE LIMITED--25 Oct 2017
RADHE RESIDENCYRADHE BUILDERS--9 Oct 2017
SHREE GURUDEV RESIDENCYNITIN SAHEBRAO UMAP--9 Oct 2017
Block D -Ramlaxman SankulBajaj Construction--25 Apr 2018
DREAMZ SIGNATUREDREAMZ INFRASPACE--25 Oct 2017
SATPUDA CAVESSUMIT SUBHASHRAO TANGADE--9 Nov 2017
SHREE NIRMAL DHAMSAURKAR CONSTRUCTION--7 Nov 2017
ATHARVA RESIDENCYMAHENDRA BALIRAM BHOJANE--9 Nov 2017
MANOHAR TOWER - ISACHIN MANOHAR SANAP--20 Nov 2017
GREEN SQUAREUJJWALA SATISH HAWARE--29 Nov 2017
GANPATI HEIGHTRUPESH TANBAJI TADAS--12 Dec 2017
MAI RESIDENCYRUPESH GAJANAN BURGHATE--11 Apr 2018
RAGHUKUNJSHRI GAJANAN CONSTRUCTION--9 Jan 2018
PLOT NO 803CITY LAND ASSOCIATES--20 Nov 2017
Sonaji EnterpriseSONAJI ENTERPRISES--22 Jan 2018
DATERAO RESIDENCYASHA BUILDERS AND DEVELOPERS--20 Dec 2017
GARDEN CITYGARDEN CITY--29 Nov 2017
MAHALAXMI EMPIRESHREE GAJANAN ASSOCIATES--2 Jan 2018
MAZA GHARJEEVAN KRUSHNARAO ZANZAT--15 Dec 2017
Durga ResidencyAshok Satyanarayan Joshi--15 Dec 2017
JAI AMBA APARTMENT 15NILESH PRAKASHRAO THAKARE--26 Dec 2017
green vallyLAXMIKANT PRABHAKAR JOSHI--20 Dec 2017
DEVIS PLATINUMDEVI INFRASPACE PRIVATE LIMITED--15 Feb 2018
LAXMI RESIDENCY SATURNAANIL LAXMICHAND BOTHRA--9 Jan 2018
Rich County ApartmentNirmiti Construction--22 Mar 2018
BUSYLAND HEIGHTSBUSYLAND HEIGHTS--22 Jun 2018
VIDYA RESIDENCYM/S SUNSHINE INFRATECH, AMRAVATI--22 Jan 2018
Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIGAmravati Housing And Area Development Board Amravati--31 Jan 2018
SWAPN SAKAR APPARTMENTMAA AMBE CONSTRUCTION--8 Feb 2018
ORBIT CONSTRUCTIONAKSHAY ANIL JAIN--2 Feb 2018
GOVIND KRUPAM/S C & D ENGINEER'S & DEVELOPERS--15 Feb 2018
SARVADNYA RESIDENCYM/S C & D ENGINEER'S & DEVELOPERS--20 Feb 2018
MAULI APARTMENTPUSHPA DHANRAJ KHANDELWAL--15 Feb 2018
YASHODHAN APARTMENTSAMEER RAMRAOJI BODKHE--8 Mar 2018
SHREE AMBA BUSINESS PARK WING ASHREE AMBA BUSINESS PARK--22 Mar 2018
HORIZON HEIGHTSHORIZON CREATORS--15 Mar 2018
Rajsuya EnclaveShri Dharmaraj Builders Private Limited--3 May 2018
Madhurajani ResidencyNitin Bhatkar--9 Apr 2018
AYUR MALLK. K. INFRASTRUCTURE--12 Apr 2018
Saidatta Developers Project SaidhamSai Datta Developers--16 Apr 2018
PUSHP SHRI APARTMENTYASH SHRI ENGINEERS AND CONTRACTORS--3 May 2018
SHRI VARADVINAYAK RESIDENCYSAGAR PRAKASHRAO BUTE--24 Apr 2018
Decent SargamJAYANT PARMANAND CHHUTLANI--20 Apr 2018
AVANI HERITAGERAVI PANJABRAO GHURDE--23 Apr 2018
KALASH RESIDENCYCHINTAMANI HOMES--8 May 2018
USHA RESIDENCYMAHAKALI BUILDERS AND LAND DEVELOPERS--5 Jun 2018
HARIGANGA ELITEKISHOR GHISULALJI GOENKA--5 Jun 2018
SUMERU VEDANTAMARIGOLD REALITY--12 Jun 2018
SHREE AMBA BUSINESS PARK WING B PHASE ISHREE AMBA BUSINESS PARK--20 Jun 2018
SAI SAGAR ENCLAVE VISAGAR PANDHARINATH BANKAR--20 Jun 2018
Vrundawan by Govinda GroupVijay Nanakram Talda--22 Jun 2018
VARAD ENCLAVESUMANGAL ASSOCIATES--23 Jul 2018
SALASAR RESIDENCYDEOGANGA BUILDERS--23 Aug 2018
SILVER WOOD RESIDENCYSukhaadi Infrastructure--11 Sep 2018
BHUMI ENCLAVEBHUMI BUILDERS AND DEVELOPERS--23 Aug 2018
VIJAY PLAZA - ASIDDHIVINAYAK DEVELOPERS--27 Sep 2018
VIJAY PLAZA - BSIDDHIVINAYAK DEVELOPERS--24 Sep 2018
VIJAY PLAZA - CAMIT ARVIND DESHMUKH--17 Sep 2018
Samruddhi HeightsSamrudhi Housing and Infrastructures--10 Oct 2018
Devisha PearlDarshan Shrikisan Kalantri--10 Oct 2018
SILVER CRESTSAFFRON DEVELOPERS--26 Oct 2018
ADIL - 1ADIL CONSTRUCTION--12 Nov 2018
Nanda HiLifeNanda Properties--5 Nov 2018
ARJUN EMPIRE MEERASHANKAR ARJUNDAS BHATEJA--28 Dec 2018
BHAGIRATHI TOWERADITYA RATHI--5 Dec 2018
USHA RESIDENCYSHRUSHTI BUILDERS & DEVELOPERS--10 Dec 2018
mauli plazaMAULI ASSOCIATES--17 Dec 2018
Tapadiya City CenterLandmark Tapadia LLP--9 Jan 2019
SHREE AMBA BUSINESS PARK WING B PHASE IISHREE AMBA BUSINESS PARK--28 Dec 2018
Gajanan HeightsKAMAL DIGRILAL MALVIYA--28 Dec 2018
SANKALP HERITAGESANKALP BUILDERS AND DEVELOPERS--4 Jan 2019
Swpnashri ApartmentShriram Mahadevrao Nagpurkar--28 Dec 2018
Decent SanskrutiJAYANT PARMANAND CHHUTLANI--15 Jan 2019
Kasturi HeightsGAJANAN VASUDEO PATIL--14 Jan 2019
PANCHRATNAGANGA BUILDERS AND DEVELOPERS--22 Feb 2019
YASHWANT RESIDENCYAGARKAR BUILDER AND DEVELOPERS--23 Jan 2019
SHREEKRUPA TOWNSHIPMEERADEVI CHHUGARAM KHATRI--29 Jan 2019
ANANDI DREAMSANANDI INFRASTRUCTURE (INDIA) PRIVATE LIMITED--15 Mar 2019
RAI AASHIYANA.RAI UDYOG LIMITED--5 Mar 2019
RAGHAV RESIDENCYPRAMOD BALKISANJI DAMMANI--26 Mar 2019
SAHYADRI RESIDENCYSAHYADRI ASSOCIATES--29 Mar 2019
Govind TowerSuresh Govindramji Malviya--29 Mar 2019
RIDDHI SIDDHI APARTMENTRIDDHI SIDDHI BUILDERS--5 Apr 2019
Dreamz PrideDreamz Infravision--26 Apr 2019
Maharshi ApartmentDHANRAJ HARICHAND KHANDELWAL--23 May 2019
TULSI PEARLNITESH SHYAM BUNDELE--31 May 2019
AMBER PARKAMBER BUILDERS AND DEVELOPERS--2 Mar 2020
AMBER HERITAGEAMBER BUILDERS AND DEVELOPERS--21 Jun 2019
CRYSTAL PLAZAAMIT CONSTRUCTION--14 Jun 2019
VINAYAK APARTMENTDINESH RAMRAO DOLARE--9 Sep 2019
SILVER PARKTEJAS ASSOCIATES--5 Aug 2019
RAJ TOWNSHIPRAJ ASSOCIATES--5 Sep 2019
SHIV RESIDENCYRAVINDRA PUNDLIKRAO MAHALLE--8 Jul 2019
TIMES SQUARESHYAM SADHURAM CHHUTLANI--25 Aug 2019
GARDEN CITY - GULMOHARGARDEN CITY--29 Jul 2019
104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, AmravatiAmravati Housing And Area Development Board Amravati--7 Jan 2020
MADHUSUMAN RESIDENCYADITYA SHREE BUILDERS & DEVELOPERS--9 Sep 2019
SUMERU SHANKARANARENDRA PRATAPRAI KINGRANI--28 Aug 2019
DAGA PLAZZOKAMLESH LAXMINARAYAN DAGA--29 Nov 2019
MANIK ENCLAVESACHIN KISANLAL GUPTA--30 Oct 2019
Gautam Nagar Phase 1 Building Nos. 6 and 7J K Investors (Bombay) Limited--12 Oct 2019
AJIT HEIGHTSRUPESH TANBAJI TADAS--18 Dec 2019
SAI PEARLHAJARE BUILDERS--9 Jul 2020
VRUNDAWAN PRIMEVijay Nanakram Talda--30 Oct 2019
SHREE YOGIRAJ APARTMENTRAJESH SUKHADEORAO RAUT--30 Oct 2019
SKY GardensV & M BUILDERS & DEVELOPERS--2 Dec 2019
AFFORDABLE HOUSING PROJECT 860 EWS IN MHASLA 21/FVIJAYKUMAR EKANATH KHORATE--29 Nov 2019
SHRINIWASSAURKAR CONSTRUCTION--5 Dec 2019
SATYA SANKULSATYA BUILDER & DEVLOPERS--14 Jan 2020
SHREE AMBA BUSINESS PARK WING CSHREE AMBA BUSINESS PARK--18 Dec 2019
MAHALAXMI PLAZAP. S. ASSOCIATES--19 Dec 2019
SAHYADRI ENCLAVEPAVAN KISANRAO SHENDE--2 Jan 2020
PARAG COMPLEX PHASE 1MALOO CONSTRUCTION--2 Jan 2020
SHREE GURU ANAND DHAM PHASE 2YOGIRAJ BUILDERS--30 Jan 2020
KESHAV EMPIRE PHASE ISACHIN KESHAORAO INGOLE--24 Feb 2020
ORCHID HOMESLAXMIKANT PRABHAKAR JOSHI--18 Feb 2020
JAIEE JUIEE JASWANDGARDEN CITY--26 Feb 2020
GARDEN CITY-CHAFA KAMALGARDEN CITY--26 Feb 2020
SHRI SAI RAGHAV ENCLAVESHRI RAM BUILDER--27 Mar 2020
CROWNVijay Nanakram Talda--31 Mar 2020
SHRI SAI RAGHUNANDAN ENCLAVESHRI YOGIRAJ BUILDERS--19 Mar 2020
YASHASVI-5MAHARUDRA INFRACOMBINES PRIVATE LIMITED--2 Aug 2020
Bluebells ArcadeMayank Ramesh Dundale--8 Jun 2020
IMPERIAL COMPLEXVipul Uttam Jadhao--24 Sep 2020
SADANAND HEIGHTSSANGEETA ANILKUMAR KHATRI--9 Jul 2020
SKY TOWERHEDA CONSTRUCTIONS AOP--7 Aug 2020
MAHAKAL RESIDENCYSATISH JAWAHARLAL KANOJIA--2 Sep 2020
Atharva ComplexAtul Uttamrao Yadgire--15 Aug 2020
mahalaxmi apartment 8P. S. ASSOCIATES--29 Aug 2020
Sai Raj HeightsBhavesh Khushal Patel--22 Oct 2020
Shree HeritageShyam Prabhakarrao Kedare--3 Nov 2020
GOVIND VILLAANSHUMAN BUILDERS--28 Oct 2020
Govind ComplexSUNITA SURESH MALVIYA--13 Nov 2020
GOVINDAMVijay Nanakram Talda--25 Dec 2020
Rahul ApartmentSHREE RUKMINI ASSOCIATES--20 Dec 2020
AFFORDABLE HOUSING PROJECT 860 EWS IN NIMBHORA 55/2ASuresh Bansiji Patil--10 Jan 2021
AFFORDABLE HOUSING PROJECT 860 EWS IN MHASALA - 22PARTSuresh Bansiji Patil--10 Jan 2021
CITY CENTER ZANWAR SHOPPING MALLSSB CONSTRUCTION--4 Feb 2021
MATO SHRI APARTMENTYASH SHRI ENGINEERS AND CONTRACTORS--10 Feb 2021
Rachayati CrownRachayati Realtors and Developers pvt ltd--5 Apr 2021
JAEE RESIDENCYMANISHA ANANTKUMAR LINGOT--8 Mar 2021
VANDAN PARKVANDAN INFRA PROJECTS PRIVATE LIMITED--10 Mar 2021
Avinashe AvenueAvinashe Builders And Developers--30 Mar 2021
The PrimusMahesh Chandrabhan Kingrani--5 Oct 2021
MAULI COMPLEXMAULI ASSOCIATES--25 Mar 2021
GAJANAN PLAZAP. S. ASSOCIATES--5 Apr 2021
OMKARSHRIYASHSHRI ENGINEERS AND CONTRACTORS--10 May 2021
GEET PARADISEGEET KAMALKUMAR MALVIYA--23 Apr 2021
Advik OneTathey Realty--29 Apr 2021
KRUSHNAKUNJ RESIDENCYPOOJA BUILDERS AND DEVELOPERS--18 May 2021
DECENT SUKHKARTAJAYANT PARMANAND CHHUTLANI--10 May 2021
Srushti HeightsSrushti Builders And Land Developers--18 May 2021
SANKALP HEAVENSANKALP BUILDERS DEVELOPERS--10 May 2021
Aditya EnclavePiyush Nibjiya--18 May 2021
SHRI BALLALESHWAR RESIDENCYSAGAR PRAKASHRAO BUTE--4 Jun 2021
PUSHPANJALI ENCLAVEShri Ashtavinayaka Developers & Builders--4 Jun 2021
GKP TOWERPRATIBHA KAMALKUMAR MALVIYA--14 Jun 2021
Mandar EnclaveMANDAR INFRASTRUCTURE--26 Jun 2021
POPULAR TRADE CENTERPOPULAR BUILDERS AND DEVELOPERS--26 Jun 2021
SMAHI HEIGHTADITYA ENGINEERS AND DEVELOPERS--29 Jun 2021
NANDISH OBERONM/S NANDISH DEVELOPERS--26 Jul 2021
PURVIKA RESIDENCYKEDIA BUILDERS AND DEVELOPERS--14 Mar 2022
ORCHID HEIGHTSNitin Bhatkar--31 Jul 2021
MAULI KRUPA APARTMENTMAULI INDUSTRIES--31 Jul 2021
CREATIVE HEIGHTSCREATIVE ASSOCIATES--25 Oct 2021
SILVER STARPRAVEEN VASANTRAO CHARJAN--23 Oct 2021
AFFORDABLE HOUSING PROJECT MOUJA NAVSARI S NO 129/2A PLOT NO 91 TO 97PMAY AMRAVATI MUNICIPAL CORPORATION--23 Oct 2021
AFFORDABLE HOUSING PROJECT MOUJA NAVSARI S NO 129/2A PLOT NO 107 TO 113PMAY AMRAVATI MUNICIPAL CORPORATION--8 Sep 2021
AFFORDABLE HOUSING PROJECT MOUJA RAHATGAON S NO 199/3A PLOT NO 59 TO 65PMAY AMRAVATI MUNICIPAL CORPORATION--23 Oct 2021
AFFORDABLE HOUSING PROJECT MOUJA BADNERA S NO 10/3 PLOT NUMBER 8 TO 13PMAY AMRAVATI MUNICIPAL CORPORATION--23 Oct 2021
AFFORDABLE HOUSING PROJECT MOUJA BADNERA S NO 194 PLOT NUMBER 36 TO 41PMAY AMRAVATI MUNICIPAL CORPORATION--13 Sep 2021
AFFORDABLE HOUSING PROJECT MOUJA BENODA PLOT NUMBER 42 TO 54PMAY AMRAVATI MUNICIPAL CORPORATION--23 Oct 2021
AFFORDABLE HOUSING PROJECT MOUJA BENODA S NO 26 PLOT NUMBER 132 TO 138PMAY AMRAVATI MUNICIPAL CORPORATION--23 Oct 2021
NANDADEEP APARTMENTSAHIL ASSOCIATES--20 Sep 2021
RACHANA SRUSHTISRUSHTI INFRA--11 Oct 2021
Vivanta Business ParkSanjay Premchand Harwani--1 Oct 2021
RIDDHI SIDDHI APARTMENTDINESH RAMRAO DOLARE--23 Oct 2021
Sagar EnclaveSagar Enclave--15 Dec 2021
Indrayani PrideGovind Shridhar Tatte--3 Dec 2021
SAIKRUPASaidutta Developers--14 Dec 2021
SHRI SAI GAJANAN ENCLAVESHREE SIYARAM BUILDERS--29 Dec 2021
JAI AMBA APPARTMENT 16NILESH PRAKASHRAO THAKARE--29 Jan 2022
NUTAN RESIDENCYADITYA DEEPAKKUMAR HEDA--22 Feb 2022
Sushila ResidencyChhatrapati Shivaray Associates--8 Mar 2022
MAHIND WISDOMPRADHNYAKAR HARIDAS BHALEKAR--3 Feb 2022
Shree Datta Prabhu ResidencyRAVINDRA PUNDLIKRAO MAHALLE--2 Feb 2022
V K COMMERCIAL COMPLEXVK CONSTRUCTION & DEVELOPERS--2 Mar 2022
Tulsi PrideNitesh Shyam Bundele--15 Feb 2022
Deep ResidencyDeep Builders And Developers--20 Jun 2022
Vasudeo ApartmentSaurabh Raju Ingole--8 Mar 2022
SAI ENCLAVEMAHESH CHETANDAS BAJAJ (HUF)--8 Mar 2022
JAEE RESIDENCY 2MANISHA ANANTKUMAR LINGOT--25 Mar 2022
Sai Isha ApartmentAjayshree Apartment--15 Jun 2022
Shri Krishna ResidencyS R Builders And Developers--15 Jun 2022
Silver PlazaARUN L.GUPTA AND OMPRAKASH L.GUPTA--24 May 2022
SAI-SHALWAKNITIN VINAYAK DANGORE--18 May 2022
GOVINDA TRADE CENTERSHRI GOVINDA PROPERTIES PRIVATE LIMITED--28 Apr 2022
Sai InfinityAgarkar Builders And Developer--12 May 2022
Kailash TowerShyam Prabhakarrao Kedare--18 May 2022
GURUMAULI RESIDENCYMANOJ SANTOSHRAO DESHMUKH--20 Jun 2022
SHRI SAI GAJANAN ENCLAVE IIJEET SHUTAKSHI BUILDERS--15 Jun 2022
Gokuldham ResidencyM/S C & D ENGINEER'S & DEVELOPERS--20 Jun 2022
KRUSHNAI HEIGHTSURJA INFRASTRUCTURE--16 Sep 2022
Gayatri HeightsRajesh Rameshpant Kherde--15 Dec 2022
TARA RESIDENCYRamdas Vyankatrao Nistane--12 Oct 2022
GokuldhamGokuldham Construction--19 Oct 2022
MAULI APARTMENTPrakash Namdeorao Saurkar--14 Sep 2022
RUKHMINI RESIDENCYRAVINDRA WANKHADE--15 Dec 2022
DHRUVATARAADA ASSOCIATES--3 Jan 2023
VAISHNAVI HERITAGEVAISHNAVI INFRA--22 Feb 2023
Ali TowerUniversal Builders--2 Dec 2022
SHRI NANDANANANT KESHAORAO SAURKAR--17 Jan 2023
SAI SAGAR ENCLAVE XIVSAGAR PANDHARINATH BANKAR--12 Dec 2022
AAKAR PRIMEROHIT ASHOKRAO JIWARKAR--24 Jan 2023
Krushnayan ResidencyRayaji Realty--26 Dec 2022
ADVIK NUTAN RESIDENCYADVIK NUTAN ASSOCIATES--3 Feb 2023
SAI DARSHAN APPARTMENTA.M.D. DEVELOPERS--21 Apr 2023
Shri Guru PlazaShree Gajanan Infra--30 Jan 2023
VASANTPUSHPAABHISHEK VASANTRAO VINCHURKAR--17 Jan 2023
PARIJAT RESIDENCYS & M ASSOCIATES--6 Mar 2023
BHERDE CITY MARKDATERAO BUILDER AND ASSOCIATES--19 Jan 2023
VANDANAI EMPIRESHIV BUILDERS--30 Jan 2023
Gandharv SkylineGandharv Meghe Associates--15 Feb 2023
Horizon H SquareHorizon Creators--24 Jan 2023
Advik TwoTathey Realty--21 Apr 2023
CRYSTAL TOWERLAXMIKANT PRABHAKAR JOSHI--22 May 2023
JIJAH PROSPERADIGVIJAY SURENDRA DESHMUKH--27 Mar 2023
SHRAVIKA RESIDENCYSAGAR PRAKASHRAO BUTE--12 Apr 2023
Sai Darshan HeightsPOOJA BUILDERS & DEVELOPERS--28 Apr 2023
SANKALP PRIDESANKALP BUILDERS DEVELOPERS--8 Jun 2023
MK MALLDEEPRAJAM INFRASPACE LLP--19 Jul 2023
CENTRAL VISTASHRI GOVINDA DEVELOPERS--13 Jul 2023
H. V. Y. EMPIRESHRI GANESHAY NAMAHA BUILDERS & DEVELOPERS--27 Jun 2023
MAHENDRA ABODESANKESH NAVINKUMAR CHORDIYA--13 Jul 2023
Shiva HeightsM Krishna Buchanna--7 Jul 2023
TITAN RESIDENCYD-REALTY--9 Aug 2023
Galaxy HeightsSky Point Builders--23 Jun 2023
MORPANKH AVENUENIRAJ REALTY--5 Oct 2023
NILKANTH HEIGHTSBHASKAR GOMAJI DAHAT--10 Oct 2023
GANESH PLAZApravin sahebrao mahalle--22 Sep 2023
Sai ParkTejas Associates--5 Oct 2023
Indrayani wadaGovind Shridhar Tatte--27 Dec 2023
Shri Vishwa HeightsMADHUBAN ASSOCIATES--12 Oct 2023
SAI CITYANSHUMAN BUILDERS--10 Nov 2023
JIJAU RESIDENCY PARKMATOSHRI DEVELOPERS--22 Sep 2023
NATIONAL MALLIRFAN KHAN USMAN KHAN--25 Jan 2024
GRISHA HEIGHT SKYLINESKYLINE REALITIES--5 Oct 2023
SHRI GIRIJATMAJ HEIGHTSSAGAR PRAKASHRAO BUTE--23 Oct 2023
KESHAVAM HEIGHTSSHRI GOVINDA BUILDCON--27 Oct 2023
GAGAN ENCLAVEIMPERIAL BUILDERS AND DEVELOPERS--22 Nov 2023
RUDRAKSHA APARTMENTSHIVNANDAN BUILDERS AND DEVELOPERS--15 Feb 2024
MILLENIUM PARKCITY EMPIRE INFRA LLP--27 Dec 2023
GOKULAMGOVINDA GANESHA INFRASPACES--15 Jan 2024
AVANTIKA RESIDENCYPRATIKSHA PRAVIN MAHALLE--3 Jan 2024
Sky Garden HillsV & M BUILDERS & DEVELOPERS--22 Mar 2024
DIAMOND HEIGHTSQUALITY STONE CONSTRUCTION AND DEVELOPERS LLP--12 Feb 2024
GOKULAM 2GOVINDA GANESHA INFRASPACES--5 Apr 2024
CITYLAND EMPIRECITYLAND EMPIRE--16 Jul 2024
The Busyland Block-MBusyland Construction Co--22 May 2024
SRUSHTI COMMERCIALSSRUSHTI COMMERCIALS--23 Apr 2024
THE PRESIDENTSRUSHTI BANDSONS--10 May 2024
GOVINDA ARCADESTEELARROW COMMERCIAL LLP--28 Jun 2024
BHAIRAVI HERITAGEAshish Mohanrao Jirapure--11 Jun 2024
Veera EnclaveChetan Associates--16 Jul 2024
Shree Govindjyot ResidencyMangesh Shyamrao Gulhane--7 Nov 2024
Tulsi UtkarshNitesh Shyam Bundele--7 Nov 2024
Guru Gajanan ResidencyVTLD AND BUILDERS GROUP--4 Dec 2024
GOVIND IMPRESSASuresh Govindramji Malviya--10 Dec 2024
JAYU HEIGHTSNITIN MOHOD--13 Jan 2025
SKY VUEM/S ARK INFRASPACE--7 Mar 2025
VYOM PHASE 1TALDA INFINITY LLP--19 May 2025
Planning a launch in Amravati? The area consolidated report packs launches, inventory movement, unit sizes and absorption across the projects you pick into one document. Rs 2,999 for the first project and Rs 1,999 for each additional one. Area report · Rs 2,999 · coming soon  See what is coming

Developers active in Amravati

PMAY AMRAVATI MUNICIPAL CORPORATION (8), Vijay Nanakram Talda (7), M/S DREAMZ INFRASTRUCTURE (5), LAXMIKANT PRABHAKAR JOSHI (4), Jayant Parmanand Chhutlani (4), RAVINDRA PUNDLIKRAO MAHALLE (4). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Amravati projects listed above?

Compare each project against its neighbours, not against the brochure. The median project on this page is 0% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Amravati project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What stamp duty will I pay on a flat in Amravati district?

The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.

What does it mean that some Amravati registrations have lapsed?

A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.

What if a Amravati project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Data from official MahaRERA filings.