Home / Browse projects / Mumbai Suburban, Maharashtra / CRYSTAL PRIDE

Registration lapsed No litigation declared Residential / Group Housing project

CRYSTAL PRIDE

By CRYSTAL CONSTRUCTION COMPANY

RG-MH-26981 · RERA P51800009735 · Last updated on MahaRERA portal: 23 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 78 months
  • 6 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
4 of 11Construction stages donefurthest along: Staircases, 95%
7 of 33Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 287 documents Report an error

CRYSTAL PRIDE is a Residential / Group Housing project by CRYSTAL CONSTRUCTION COMPANY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009735 on 22 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 78 months from the original filing. 26 of the 33 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameCRYSTAL PRIDE
  • TypeResidential / Group Housing
  • Location
    • Kedarmal Road
    • Bachani Nagar
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009735
  • ReraGenie IDRG-MH-26981

Builder

  • NameCRYSTAL CONSTRUCTION COMPANY
  • Entity typePartnership
  • GSTIN27AAGFC3764M2Z1
  • PartnersSHAUKAT ALI MOHD VALI KHAN, MOHD ARSHAD MOHD KALEEM SIDDIQUI
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed287 files

Current status

79%26 of 33 units booked
90.7%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CRYSTAL PRIDENA191631233

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

CRYSTAL PRIDE: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor65%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered18

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area708 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Aug 2025

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI2125.5
Proposed, not sanctioned1,889 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVILEPARLE WEST, MUMBAI MH MUMBAI 400049
Estimated costRs 12.22 cr
Cost incurredRs 11.08 cr
Work done90.7%
BuildingWingEstimatedIncurred
-NARs 7.97 crRs 7.17 cr
CRYSTAL PRIDENARs 4.25 crRs 3.91 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSWARAJ ARCH CONSULTANTS
EngineerHARSHAD JAMSANDEKAR
Chartered AccountantJain Pal & Associates
PartnerRole in project
CRYSTAL CONSTRUCTION COMPANY-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012226Dec 2019 → Jun 2023

Reason as filed by the promoterAs per DCPR 2034 our FSI increased and we have started procedure of amended plan approval and obtaining of increased FSI commencement certificate. But due to delay in obtaining of permissions our site labours moved and this resulted slow in construction work. Now we have arranged all and our construction is in full swing but it will take another one year to complete the project.

EXT51800009851Dec 2019 → Jun 2022

Reason as filed by the promoterStop of work due to Pandemic period of COVID-19 and change in rules of DCPR 2034 of SRA. Delay in receiving of permissions of extended F.S.I.like Amendments of plan, L.O.I, I.O.D. & C.C. All required permission now received and construction is in full swing. But it will take another One Year to give Possession.

EXT51800003866Dec 2019 → Dec 2020

Reason as filed by the promoterCarpet Area of Tenant and FSI increased due to change in DCR 2034 rules of SRA.

EXT51800017086Dec 2019 → Jun 2024

Reason as filed by the promoterAs per DCPR 2034 time taken for approvals & amendement of plan and amendedment in existing structure of Tenents constructed flats. Further we have also completed full RCC work alongwith part finishing work as per details submitted in projects details. Further It will take another 1 year to complete the project in all respect as only few finishing work remained to be completed.

EXT51800024559Dec 2019 → Jun 2025

Reason as filed by the promoterRCC work completed. Finishing work partly finished and partly pending. Due to no sale of flat financial instability raised. Now everything is lineup and hopefully it shall be completed before extension period.

EA01092502486Dec 2019 → Jun 2026

Reason as filed by the promoterDue to medical emergency of authorised partner of promoter, the work has been stopped and also due to no sale of flat financial instability raised. Now everything is lineup and hopefully it shall be completed before extension period coz only few finishing works like lift, firefighting etc. remains pending.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Sep 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed287

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 287 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 31122025.pdf23 Jul 2026
Withdrawal Update Form 1File: FORM 1 31122025.pdf23 Jul 2026
Withdrawal Update Form 1File: FORM 1 31032026.pdf23 Jul 2026
Withdrawal Update Form 1File: FORM 1 30062026.pdf23 Jul 2026
Withdrawal Update Form 2File: 30122025.pdf23 Jul 2026
Withdrawal Update Form 2File: 30122025.pdf23 Jul 2026
Withdrawal Update Form 2File: 31032026.pdf23 Jul 2026
Withdrawal Update Form 2File: FORM 2 30062026.pdf23 Jul 2026
Withdrawal Update Form 3File: Form 3 30092025.pdf23 Jul 2026
Withdrawal Update Form 3File: FORM 3 31122025.pdf23 Jul 2026
Withdrawal Update Form 3File: FORM 3 31032026.pdf23 Jul 2026
Withdrawal Update Form 3File: FORM 3 30062026.pdf23 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A 310326.pdf23 Jul 2026
Withdrawal Update Form 1File: FORM 1 30092025.pdf22 Jul 2026
Withdrawal Update Form 2File: 30092025.pdf22 Jul 2026
Withdrawal Update Form 3File: Form 3 30092025.pdf22 Jul 2026
Form 1File: Architect Certificate 21072017.pdf22 Nov 2025
Form 2File: Form 2 - 220717.pdf22 Nov 2025
Form 3File: CA Certificate - Form 3.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01072017.pdf22 Nov 2025
Form 1File: Architect Certificate - 01102017.pdf22 Nov 2025
Form 2File: Form 2 - 01102017.pdf22 Nov 2025
Form 3File: CA Certificate - Form 3.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01102017.pdf22 Nov 2025
Form 1File: Architect Certificate Form 1 - 01042018.pdf22 Nov 2025
Form 2File: Form 2 - 01042018.pdf22 Nov 2025
Form 3File: CA Form 3 31032018.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01042018.pdf22 Nov 2025
Form 1File: Architect Certificate Form 1 - 26072018.pdf22 Nov 2025
Form 2File: Form 2 - 140718.pdf22 Nov 2025
Form 3File: CA Form 3 31032018.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01072018.pdf22 Nov 2025
Form 1File: Architect Certificate Form 1 - 01102018.pdf22 Nov 2025
Form 2File: Form 2 - 01102018.pdf22 Nov 2025
Form 3File: CA Form 3 31032018.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01102018.pdf22 Nov 2025
Form 1File: Architect Certificate Form 1 - 01012019.pdf22 Nov 2025
Form 2File: Form 2 - 010119.pdf22 Nov 2025
Form 3File: Form 3 31122018.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01012019.pdf22 Nov 2025
Form 1File: Architect Certificate Form 1 - 01042019.pdf22 Nov 2025
Form 2File: Form 2 - 010419.pdf22 Nov 2025
Form 3File: Form-3 31032019.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01042019.pdf22 Nov 2025
Form 1File: Form 1 - 01072019.pdf22 Nov 2025
Form 2File: Form 2 - 010719.pdf22 Nov 2025
Form 3File: Form-3 31032019.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01072019.pdf22 Nov 2025
Form 1File: Form 1 - 20112019.pdf22 Nov 2025
Form 2File: Form 2 - 191119.pdf22 Nov 2025
Form 3File: Form-3 30092019.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01102019.pdf22 Nov 2025
Form 1File: Form 1 - 01012020.pdf22 Nov 2025
Form 2File: Form 2 - 311219.pdf22 Nov 2025
Form 3File: Form-3 30092019.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01012020.pdf22 Nov 2025
Form 1File: Form 1 - 01042020.pdf22 Nov 2025
Form 2File: Form 2 - 01042020.pdf22 Nov 2025
Form 3File: Form-3 31032020.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 31032020.pdf22 Nov 2025
Form 1File: Form 1 - 01072020.pdf22 Nov 2025
Form 2File: Form 2 - 01072020.pdf22 Nov 2025
Form 3File: Form-3 31032020.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01072020.pdf22 Nov 2025
Form 1File: Form 1 - 30092020.pdf22 Nov 2025
Form 2File: Form 2 - 30092020.pdf22 Nov 2025
Form 3File: Form-3 31032020.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01102020.pdf22 Nov 2025
Form 1File: Form 1 - 01012021.pdf22 Nov 2025
Form 2File: Form 2 - 01012021.pdf22 Nov 2025
Form 3File: Form-3 31122020.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 31122020.pdf22 Nov 2025
Form 1File: Form 1 - 01042021.pdf22 Nov 2025
Form 2File: Form 2 - 01042021.pdf22 Nov 2025
Form 3File: Form -3 31032021.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - 01042021.pdf22 Nov 2025
Form 1File: Form - 1 30062021.pdf22 Nov 2025
Form 2File: Form 2 30062021.pdf22 Nov 2025
Form 3File: Form -3 31032021.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: 01072021.pdf22 Nov 2025

How this compares with Mumbai Suburban

79%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 78 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CRYSTAL PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bachani Nagar6,700+ in Mumbai Suburban

2 kmCRYSTAL PRIDECompleted 143Lapsed / revoked 86Other 156Dot size: filed unitsN

Filed coordinates, straight-line distance. 385 registered projects within 2 km.

Builder: CRYSTAL CONSTRUCTION COMPANY

CRYSTAL CONSTRUCTION COMPANY has 2 registrations on MahaRERA, including CRYSTAL PRIDE and Hitendra Dhamm Shabha Co-operative Housing Society Limited. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that CRYSTAL PRIDE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CRYSTAL PRIDE is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CRYSTAL PRIDE?

The registered promoter entity is CRYSTAL CONSTRUCTION COMPANY, a partnership as per the filing. Its GSTIN 27AAGFC3764M2Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CRYSTAL PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CRYSTAL PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CRYSTAL PRIDE?

The professionals named in the filing: Architect: SWARAJ ARCH CONSULTANTS; Engineer: HARSHAD JAMSANDEKAR; Chartered Accountant: Jain Pal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CRYSTAL PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CRYSTAL PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CRYSTAL PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.