Completed No litigation declared Residential / Group Housing project

Crescent Bay - T1 - 40, 41 floors

By L&T Parel Project LLP (JV with ORDPL)

RG-MH-11840 · RERA P51900008032 · Last updated on MahaRERA portal: 16 Dec 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: .
Mar 2018Possession promisedregistration recorded completed
0 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
0Complaints at MahaRERAon this registration
Jump to the 40 documents Report an error

Crescent Bay - T1 - 40, 41 floors is a Residential / Group Housing project by L&T Parel Project LLP (JV with ORDPL) in 400012, registered with MahaRERA as P51900008032 on 18 Aug 2017. The registration is recorded completed; possession was promised by 31 Mar 2018.

At a glance

Project

  • NameCrescent Bay - T1 - 40, 41 floors
  • TypeResidential / Group Housing
  • Location
    • 400012
  • Pincode400012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900008032
  • ReraGenie IDRG-MH-11840

Builder

  • NameL&T Parel Project LLP (JV with ORDPL)
  • Entity typeOthers
  • GSTIN27AAEFL4474F1Z9
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersL and T Realty Ltd L and T Realty Ltd, Chennai Vision Developers Pvt Ltd Chennai Vision Developers Pvt Ltd
  • Named personsL&T Realty Limited, Chennai Vision Developers Private Limited
  • Other registrations5 more →
  • Completed6 of 6
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017PromisedMar 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Aug 2017
  • Promised completion31 Mar 2018
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Crescent Bay - T1 - 40, 41 floorsNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

Crescent Bay - T1 - 40, 41 floors: 50% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 16 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes6%
Street LightingYes12%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes75%
Energy managemcntYes70%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered26

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area910 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Omkar Realtors & Developers Pvt LtdKurlaMumbai Suburban
Darshan Realtors Private LtdKurlaMumbai Suburban
Omkar Realtors & DevelopersKurlaMumbai Suburban

Approvals and building plan

Permissible FSI1365.46
Proposed, not sanctioned1,365 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch5C/II, Mittal Court, 224 BRP Road, Church Gate, Nariman Point, Mumbai 400021

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Shikre Associates
ArchitectANAND V. DHOKAY
EngineerDr. KELKAR DESIGNS Pvt. Ltd
PartnerRole in project
L&T Parel Project LLP (JV with ORDPL)-

Litigation declared24

CaseCourtStatus
310 of 2014/2013High Court of BombayPreadmission
L 65 of 2017/2017High Court of BombayPreadmission
647 of 2017/2016High Court of BombayPreadmission
1545 of 2015/2015High Court of BombayPreadmission
7/2016HPCHearing
1300161/2016Metropolitan magistrate Court DadarPreadmission
9/2015HPCHearing
1625 of 2010/2010Bombay City Civil Court at BombayHearing
L 12245 of 2015/2015HIGH COURT OF JUDICATURE AT BOMBAYPreadmission
1936 of 2016/2016Bombay City Civil Court at BombayHearing
1969 of 2016/2016Bombay City Civil Court at BombayHearing
1323 of 2013/2013Bombay City Civil Court at BombayHearing
1322 of 2013/2013Bombay City Civil Court at BombayHearing
2108 of 2013/2013Bombay City Civil Court at BombayHearing
2622 of 2015/2015Bombay City Civil Court at BombayHearing
179 of 2016/2016Bombay City Civil Court at BombayHearing
806 of 2017/2017Bombay City Civil Court at BombayHearing
924 of 2018/2018High Court of BombayHearing
1618 of 2018/2018High Court of BombayHearing
101255 of 2017/2017Court of Session For Greater BombayHearing
2249 of 2017/2017Bombay City Civil CourtHearing
193 of 2018/2018The Honble Grievance Redressal committeeHearing
83 of 2018/2018The Honble Grievance Redressal committeeHearing
125 of 2013/2013Bombay City Civil CourtHearing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Dec 2021

Documents filed40

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: T1.pdf16 Dec 2021
Status of ConveyanceFile: Tower 1.pdf30 Oct 2021
OtherFile: Amended IOA220518.pdf30 Sep 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Regn_CB-T1.pdf26 Nov 2019
Certificates of CA (Form 5)File: Form 5 T1.pdf30 Sep 2018
Details of encumbrancesFile: Encumbrance Certificate - Revised.pdf12 Apr 2018
OtherFile: T1 CB.pdf5 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: CC Copy.pdf29 Mar 2018
Certificates of Architect (Form 4)File: Form 4 T1 with OC.pdf24 Mar 2018
OtherFile: OC Copy.pdf24 Mar 2018
Certificates of CA (Form 3)File: Form 3 - T1.pdf29 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - T1.pdf25 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - T1-SE.pdf25 Jan 2018
OtherFile: CB AFS final - Copy.pdf9 Jan 2018
Certificates of CA (Form 3)File: Form3 - T1.pdf2 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 T1.pdf31 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - T1.pdf31 Oct 2017
Certificates of CA (Form 3)File: Form 3 - T1.pdf31 Oct 2017
Details of encumbrancesFile: Encumbrance certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: AFS.pdf31 Jul 2017
OtherFile: Disclosures Tower 1.pdf31 Jul 2017
Layout approvalFile: T1.pdf30 Jul 2017
Copy of the legal title reportFile: Legal Title.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: T1.pdf30 Jul 2017
OtherFile: Darshan Declaration.pdf30 Jul 2017
Declaration in FORM BFile: Form B - T1.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - T1.pdf29 Jul 2017
Certificates of CA (Form 3)File: Form 3 - T1.pdf29 Jul 2017
Layout approvalFile: Layout PLan.pdf28 Jul 2017
Building plan approvalFile: IOA.PDF28 Jul 2017
PAN CardFile: LTPPLLP Signed PAN.pdf28 Jul 2017
Copy of the legal title reportFile: 1 Title Certificate.pdf28 Jul 2017
Copy of the legal title reportFile: 2 Title Certificate.pdf28 Jul 2017
Copy of the legal title reportFile: 3 Title certificate.pdf28 Jul 2017
Copy of the legal title reportFile: 4 Title Certificate.pdf28 Jul 2017
Copy of the legal title reportFile: 5 Title Certificate.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout PLan.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOA.PDF28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 T1.pdf28 Jul 2017
OtherFile: Omshanti declaration.pdf28 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsStatusPromisedDelivered
Test111OngoingSep 2026Not delivered
Crescent Bay - Wing M - T1 - 39 floors of Sale Building No 1Parel sewri Dadar Naigaon Parel Mumbai 400012208CompletedOct 2017May 2017

Keep Crescent Bay - T1 - 40, 41 floors on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

2 kmCrescent Bay - T1 - 40, Completed 26Lapsed / revoked 12Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 52 registered projects within 2 km.

Builder: L&T Parel Project LLP (JV with ORDPL)

L&T Parel Project LLP (JV with ORDPL) has 6 registrations on MahaRERA, including Crescent Bay - T4 and Crescent Bay - T5. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record.

Frequently asked questions

What are my rights if Crescent Bay - T1 - 40, 41 floors is delayed beyond 31 Mar 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Crescent Bay - T1 - 40, 41 floors?

The registered promoter entity is L&T Parel Project LLP (JV with ORDPL), an others as per the filing. Its GSTIN 27AAEFL4474F1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Crescent Bay - T1 - 40, 41 floors?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Crescent Bay - T1 - 40, 41 floors?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Crescent Bay - T1 - 40, 41 floors?

The professionals named in the filing: Architect: Sandeep Shikre Associates; Architect: ANAND V. DHOKAY; Engineer: Dr. KELKAR DESIGNS Pvt. Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Crescent Bay - T1 - 40, 41 floors?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Crescent Bay - T1 - 40, 41 floors. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Crescent Bay - T1 - 40, 41 floors to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.