Home / Browse projects / Mumbai Suburban, Maharashtra / CONTENDRE HEIGHTS
CONTENDRE HEIGHTS
By Contendre Infratech Pvt. Ltd.
RG-MH-40020 · RERA P51800032162 · Last updated on MahaRERA portal: 28 Nov 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CONTENDRE HEIGHTS is a Others project by Contendre Infratech Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032162 on 14 Dec 2021. The registration is recorded completed; possession was promised by 30 Nov 2023.
At a glance
Project
- NameCONTENDRE HEIGHTS
- TypeOthers
- Location
- NA
- VILLAGE NAHUR
- MULUND WEST
- Kurla
- Mumbai Suburban
- 400078
- Pincode400078
- RERA no.P51800032162
- ReraGenie IDRG-MH-40020
Builder
- NameContendre Infratech Pvt. Ltd.
- Entity typeCompany
- DirectorsNITA PARESH SHETH, PARESH MANILAL SHETH
- Other registrations2 more →
- Completed2 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on14 Dec 2021
- Promised completion30 Nov 2023
- Revised completionNone
- Buildings1 building record
- Documents filed40 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CONTENDRE HEIGHTS | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
CONTENDRE HEIGHTS: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MULUND HARE RAM CO-OPERATIVE SOCIETY | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NASA |
| Engineer | SWAPNEEL CONSULTANTS |
| Chartered Accountant | MTC & CO |
| Partner | Role in project |
|---|---|
| Contendre Infratech Pvt. Ltd. | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Nov 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Dec 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 May 2023
Documents filed40
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CH 21-22.pdf | 28 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CH 22-23.pdf | 28 Nov 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate 6994 (1).pdf | 3 May 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: RERA FORM NO-4 HARE RAM (1).pdf | 3 May 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: hareram society registration certificate (1).pdf | 3 May 2023 |
| Status of ConveyanceFile: Deed of conveyance Index II.pdf | 3 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CONTENDRE HEIGHTS FORM 1.pdf | 27 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CONTENDRE HEIGHTS FORM 2.pdf | 27 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: CONTENDRE HEIGHTS SOLD-UNSOLD.pdf | 27 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CONTENDRE HEIGHTS FORM 3_compressed.pdf | 27 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 28 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 28 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_compressed.pdf | 28 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 28 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 28 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Nasa Certificate.pdf | 24 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 24 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf | 24 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 18 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 18 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf | 18 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf | 18 May 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_compressed.pdf | 18 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Sign Copy_compressed.pdf | 18 May 2022 |
| Layout approvalFile: 22.pdf | 6 Dec 2021 |
| Building plan approvalFile: 11.pdf | 6 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: 22.pdf | 6 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 11.pdf | 6 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Plinth.pdf | 6 Dec 2021 |
| Declaration about Commencement CertificateFile: COMMENCEMENT CERTIFICATE.pdf | 6 Dec 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 1 Dec 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 1 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 1 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200224729404_For_Asset_Based_Search_25_11_2021_20_02_11_861.pdf | 26 Nov 2021 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE DRAFT.pdf | 24 Nov 2021 |
| PAN CardFile: PAN CARD-converted.pdf | 18 Nov 2021 |
| Copy of the legal title reportFile: legal title report.pdf | 18 Nov 2021 |
| Details of encumbrancesFile: NON ENCUM.pdf | 18 Nov 2021 |
| Declaration in FORM BFile: FORM B PROMOTER.pdf | 18 Nov 2021 |
| Proforma of Allotment letterFile: Allotment_Letter_apartment.pdf | 18 Nov 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 40 filed documents as one ZIP, foldered, with a manifest
Keep CONTENDRE HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VILLAGE NAHUR, MULUND WEST6,700+ in Mumbai Suburban
Runwal Forests Tower 9 - 11
Wheelabrator Alloy Castings Limited
SHRADDHA VARDAAN
SHRADDHA LANDMARK PRIVATE LIMITED
SHRADDHA EVOQUE
SHRADDHA LANDMARK PRIVATE LIMITED
Sugee Vaayu
Sugee Developers Private Limited
SHRADDHA CLASSIC
SHRADDHA LANDMARK PRIVATE LIMITED
Om Siddhivinayak CHS Ltd
Shree Shiv Samarth Reality
See every Mumbai Suburban project, with the district possession charts
Builder: Contendre Infratech Pvt. Ltd.
Contendre Infratech Pvt. Ltd. has 3 registrations on MahaRERA, including JIN YASH and CONTENDRE HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if CONTENDRE HEIGHTS is delayed beyond 30 Nov 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CONTENDRE HEIGHTS?
The registered promoter entity is Contendre Infratech Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CONTENDRE HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CONTENDRE HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CONTENDRE HEIGHTS?
The professionals named in the filing: Architect: NASA; Engineer: SWAPNEEL CONSULTANTS; Chartered Accountant: MTC & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CONTENDRE HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback