Codename One and Only
RG-MH-28551 · RERA P51700026503 · Last updated on MahaRERA portal: 23 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Codename One and Only is a Plotted project by LODHA DEVELOPERS LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700026503 on 26 Sep 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 75 of the 157 units on this registration are recorded sold or booked. 2 complaints are on record with the regulator.
At a glance
Project
- NameCodename One and Only
- TypePlotted
- Location
- .
- Surai
- Bhiwandi
- Thane
- 421302
- Pincode421302
- RERA no.P51700026503
- ReraGenie IDRG-MH-28551
Builder
- NameLODHA DEVELOPERS LIMITED
- Entity typeCompany
- CINL45200MH1995PLC093041
- GSTIN27AAACL1490J1ZG
- ChairpersonsRAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA and 1 more
- Other registrations178 more →
- Completed16 of 179
- No longer live3 lapsed, de-registered or revoked
- Past their filed date3
- Declared earlier projects22 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on26 Sep 2020
- Promised completion30 Jun 2026
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed82 files
Current status
Figures as on 23 Jun 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pradeep Kamble |
| Engineer | Hiroji Rane |
| Engineer | MEHUL SHAH |
| Chartered Accountant | M S K A & Associates |
| Chartered Accountant | Chirag Sarvaiya & Co |
| Partner | Role in project |
|---|---|
| LODHA DEVELOPERS LIMITED | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12600353 | LODHA DEVELOPERS LIMITED | KAMLESH KUMAR HARIHARNATH SHUKLA | 19/01/2026 |
| CC12603932 | RAVINDRA SINGH | LODHA DEVELOPERS LIMITED | 25/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Sep 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Sep 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed82
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form1 March 26.pdf | 23 Jun 2026 |
| Withdrawal Update Form 1File: Form1 March 26.pdf | 23 Jun 2026 |
| Withdrawal Update Form 2File: Layout Sector H- Parcel 9 dated 23062026.pdf | 23 Jun 2026 |
| Withdrawal Update Form 2File: Latest CC 19062029_compressed.pdf | 23 Jun 2026 |
| Withdrawal Update Form 3File: Codename One and Only.pdf | 23 Jun 2026 |
| Withdrawal Update Form 3File: Codename One and Only.pdf | 23 Jun 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A - Codename One and Only - P51700026503.pdf | 23 Jun 2026 |
| Form 1File: Form1 March 26.pdf | 21 Apr 2026 |
| Form 2File: Codename Mar 2026 - Form 02 Signed.pdf | 21 Apr 2026 |
| Form 3File: Codename Mar 2026 - Form 03 Signed.pdf | 21 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Codename Mar 2026 - SoldUnsold Signed.pdf | 21 Apr 2026 |
| Form 1File: Form-1 Dec-25.pdf | 28 Jan 2026 |
| Form 2File: Codename Form 02 Signed Dec 25.pdf | 28 Jan 2026 |
| Form 3File: Codename Form 03 Signed Dec 25.pdf | 28 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Codename Sold Unsold Signed Dec 25.pdf | 28 Jan 2026 |
| Self-declaration of Quarterly ProgressFile: Amended Layout (1).pdf | 28 Jan 2026 |
| Form 1File: Form-1 Dec-25.pdf | 27 Jan 2026 |
| Form 2File: Codename Form 02 Signed Dec 25.pdf | 27 Jan 2026 |
| Form 3File: Codename Form 03 Signed Dec 25.pdf | 27 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Codename Sold Unsold Signed Dec 25.pdf | 27 Jan 2026 |
| Form 1File: Form 1- Codename One And Only -Sep 25.pdf | 31 Oct 2025 |
| Form 2File: Form 02 - Codename One And Only - Sep 25 signed.pdf | 31 Oct 2025 |
| Form 3File: Form 03 - Codename One And Only - Sep 25 signed.pdf | 31 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold - Codename One And Only - Sep 25 signed.pdf | 31 Oct 2025 |
| Form 5 (FY 2024-2025)File: Codename One And Only.pdf | 14 Oct 2025 |
| Form 2A (FY 2024-2025)File: Codename One And Only.pdf | 29 Jul 2025 |
| Form 1File: Codename One And Only - Form1 - June 25 - P51700026503 -okk.pdf | 18 Jul 2025 |
| Form 2File: Codename One and only Form 2 June-25.pdf | 18 Jul 2025 |
| Form 3File: Codename One and only Form 3 June-25.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Codename One and only Sold Unsold June 2025.pdf | 18 Jul 2025 |
| Form 1File: Form 1 -lodha Codename One Only -March 25.pdf | 23 Jun 2025 |
| Form 2File: Form 2 - Codename One And Only.pdf | 23 Jun 2025 |
| Form 3File: Form 3 -Codename One And Only.pdf | 23 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Signed Sold-Unsold_Codename One and Only March 2025.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (lodha Codename One Only).pdf | 2 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: codename.pdf | 17 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: codename.pdf | 17 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold_Codename One and Only Dec 2024.pdf | 17 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: P51700026503 - Codename One And Only.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Codename One And Only - P51700026503.pdf | 17 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Codename one only.pdf | 13 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Codename One And Only.pdf | 16 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 104 Codename One And Only.pdf | 12 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 104 Codename One And Only.pdf | 29 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Codename One and Only.pdf | 29 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Codename One And Only.pdf | 22 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: Codename One And Only.pdf | 27 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Codename One And Only.pdf | 24 Dec 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 113 Codename One And Only.pdf | 17 Dec 2021 |
| Layout approvalFile: Layout Compressed.pdf | 16 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: Layout Compressed.pdf | 16 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: first Page.pdf | 16 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 104 Codename One And Only.pdf | 15 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: New Approval_compressed-1.pdf | 14 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: New Approval_compressed-2.pdf | 14 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: New Approval_compressed-3.pdf | 14 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: New Approval_compressed-4.pdf | 14 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: New Approval_compressed-5.pdf | 14 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: New Approval_compressed-6.pdf | 14 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: ITP Approval.pdf | 2 Dec 2021 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 2 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 194 Codename One And Only.pdf | 18 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 114 Codename One And Only.pdf | 15 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 113 Codename One And Only.pdf | 14 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: P51700026503.pdf | 14 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 104 Codename One And Only.pdf | 9 Oct 2021 |
| Building plan approval or NA orderFile: layout plan sector 'F' - Final_.pdf | 25 Sep 2020 |
| Copy of the legal title reportFile: Anjur TR 06 05 2017-1-25.pdf | 25 Sep 2020 |
| Copy of the legal title reportFile: Anjur TR 06 05 2017-26-50.pdf | 25 Sep 2020 |
| Copy of the legal title reportFile: Anjur TR 06 05 2017-51-83.pdf | 25 Sep 2020 |
| Copy of the legal title reportFile: Further Supplemental Report On Title - Upper Thane 19 09 2020-1-3.pdf | 25 Sep 2020 |
| Copy of the legal title reportFile: Further Supplemental Report On Title - Upper Thane 19 09 2020-4-7.pdf | 25 Sep 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: layout plan sector 'F' - Final_.pdf | 25 Sep 2020 |
| Proforma of Allotment letterFile: Draft ATS-Plotted Development-1-20.pdf | 25 Sep 2020 |
| Proforma of Allotment letterFile: Draft ATS-Plotted Development-21-40.pdf | 25 Sep 2020 |
| Layout approvalFile: UT LAYOUT_pinnacle.pdf | 23 Sep 2020 |
| Copy of Layout Approval (in case of layout)File: UT LAYOUT_pinnacle.pdf | 23 Sep 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: 4th Layout Clearance Bhiwandi ITP.pdf | 8 Sep 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RERA Certificate - PINNACLE_compressed.pdf | 8 Sep 2020 |
| Proforma of Allotment letterFile: Allotment letter v1.pdf | 8 Sep 2020 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| LODHA PARKP51900001339 | . | 2,210 | Jul 2017 | Completed | Dec 2023Registered original: Dec 2021 | Feb 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 178 other registrations, which the RERA portal never shows together
- All 82 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Codename One and Only on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near .7,600+ in Thane
GODREJ UPAVAN
PRAKHHYAT DWELLINGS LLP
DGT - Sector 3A - Cluster 2 - Phase 1
ADRIKA DEVELOPERS PRIVATE LIMITED
DOSTI GREATER THANE - PHASE 1
ADRIKA DEVELOPERS PRIVATE LIMITED
Dosti Greater Thane - Sector 3A - Cluster 1B -
ADRIKA DEVELOPERS PRIVATE LIMITED
USHA RESIDENCY
SHREE BUDHDEV INFRA
NARAYANI DHAM BUILDING NO 2A AND 2B
MAYA DEVELOPER
See every Thane project, with the district possession charts
Builder: LODHA DEVELOPERS LIMITED
LODHA DEVELOPERS LIMITED has 179 registrations on MahaRERA, including Lodha Adrina and Mhatre Compound. Its filings disclose 22 earlier MahaRERA projects: declares 9 of 10 past projects completed on time. Litigation is declared on 39 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Codename One and Only shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Codename One and Only is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Codename One and Only?
The registered promoter entity is LODHA DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Codename One and Only?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Codename One and Only?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Codename One and Only?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Codename One and Only?
The professionals named in the filing: Architect: Pradeep Kamble; Engineer: Hiroji Rane; Engineer: MEHUL SHAH; Chartered Accountant: M S K A & Associates; Chartered Accountant: Chirag Sarvaiya & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Codename One and Only?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback