Home / Browse projects / Thane, Maharashtra / DOSTI GREATER THANE - PHASE 1
DOSTI GREATER THANE - PHASE 1
By ADRIKA DEVELOPERS PRIVATE LIMITED
RG-MH-28157 · RERA P51700024923 · Last updated on MahaRERA portal: 12 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 6 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DOSTI GREATER THANE - PHASE 1 is a Others project by ADRIKA DEVELOPERS PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700024923 on 12 Mar 2020. Possession was promised by 1 Apr 2026 and is now 6 months past that date. 1,790 of the 1,806 units on this registration are recorded sold or booked, and 32 of 44 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameDOSTI GREATER THANE - PHASE 1
- TypeOthers
- Location
- JUNCTION OF KALHER PIPELINE ROAD AND BUNDER ROAD
- NEAR UMIYA COMPLEX AND S S HOSPITAL
- Kopar
- Bhiwandi
- Thane
- 421302
- Pincode421302
- RERA no.P51700024923
- ReraGenie IDRG-MH-28157
Builder
- NameADRIKA DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
- Managing DirectorDEEPAK KISHAN GORADIA
- DirectorsRAJESH PREMJI SHAH, RAJUL VRAJLAL VORA
- Other registrations8 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on12 Mar 2020
- Promised completion1 Apr 2026
- Revised completionNone
- Buildings4 building records
- Documents filed124 files
Current status
Figures as on 12 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DOSTI DELIGHT | NA | 26 | 20 | 665 | 0 | 665 |
| DOSTI BLISS | NA | 26 | 20 | 470 | 18 | 488 |
| DOSTI GLORY | NA | 26 | 20 | 235 | 0 | 235 |
| DOSTI FORTUNE | NA | 26 | 17 | 400 | 18 | 418 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 12 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
32 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 96%.
DOSTI DELIGHT81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
DOSTI BLISS81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 96% |
DOSTI GLORY81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 96% |
DOSTI FORTUNE81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 96% |
Progress on shared amenities16
As on 12 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 95% |
| Water Supply | Yes | 95% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 95% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | Yes | 80% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 95% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 95% |
| Energy managemcnt | Yes | 90% |
| Fire protection and fire safety requirements | Yes | 95% |
| Electrical meter room, sub-station, receiving station | Yes | 85% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| MULTIPURPOSE LAWN SEATING POCKETS REFLEXOLOGY PATH KIDS PLAY AREA MEDITATION GAZEBO OUTDOOR GYM JOGG | Yes | 0% |
Parking filed334
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| DOSTI DELIGHT | 69 | 69 | 138 |
| DOSTI BLISS | 20 | 46 | 66 |
| DOSTI GLORY | 27 | 23 | 50 |
| DOSTI FORTUNE | 28 | 52 | 80 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JAY VORA |
| Engineer | SWAPNIL RAMESH LONDHE |
| Chartered Accountant | MANISH BARDIA |
| Chartered Accountant | BAGADE & ASSOCIATES |
| Partner | Role in project |
|---|---|
| ADRIKA DEVELOPERS PRIVATE LIMITED | - |
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 119/2019 | CIVIL JUDGE JUNIOR DIVISION | FOR HEARING OF EXHIBIT FIVE |
| 238/2017 | CIVIL JUDGE SENIOR DIVISION | FILLING OF SAY ON CONDONATION OF DELAY |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12603618 | Raj Chavan | ADRIKA DEVELOPERS PRIVATE LIMITED | 12/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Mar 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Oct 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Oct 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed124
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 124 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: Adrika DGT Novocity PH1.pdf | 12 Nov 2025 |
| Form 1File: DGT Novocity PHASE1 ARCH Certificate June2025.pdf | 28 Jul 2025 |
| Form 2File: DGT Novocity Phase1 Engg Certificate June2025.pdf | 28 Jul 2025 |
| Form 3File: DGT Novocity Phase1 CA Certificate June2025.pdf | 28 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DGT PH1-Bliss_merged_compressed.pdf | 28 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DGT PHASE-1 ARCH Certificate.pdf | 14 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DGT Phase-1 CA Certificate.pdf | 14 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DGT PHASE-1 Engg Certificate.pdf | 14 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: DGT PHASE-1 Quality Certificate.pdf | 14 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: ADPL DGT PH 1 Bliss Delight Fortune Glory_compressed (2).pdf | 12 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate DGT Phase 1.pdf | 13 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate DGT Phase 1.pdf | 13 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate DGT Phase 1.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DGT PH 1_compressed.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DGT Phase-1.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DGT Phase-1 Form1 Sep24.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DGT Phase-1 Form3 Sep24.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DGT Phase-1 Form2 Sep24.pdf | 15 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: DGT Phase-1.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 5-0 DGT Novocity Phase-1- Bliss Fortune Delight.pdf | 9 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DGT Phase-1- Form1 Arch Cert June 2024.pdf | 22 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DGT Phase-1- Form2 CA Cert June 2024.pdf | 22 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DGT Phase-1- Form3 CA Cert June 2024.pdf | 22 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Dosti Novocity Phase-1.pdf | 10 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate DGT Novocity Phase 1.pdf | 26 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate DGT Novocity Phase 1.pdf | 26 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: DGT Novocity Phase 1 Bliss Delight fortune Glory.pdf | 24 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate DGT Phase 1.pdf | 23 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Dosti Bliss Delight fortune Glory.pdf | 5 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certifi-DGT-Ph-I-Dec23.pdf | 29 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certifi-DGT-Ph-I-Dec23.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate DGT Phase 1.pdf | 17 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Dosti Greater Thane Phase 1.pdf | 16 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5-DGT-PH-I.pdf | 28 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Rera Form 5 - Adrika -DGT PH -1 March 31, 2022.pdf | 18 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate DGT Phase 1.pdf | 15 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg-Form-2-DGT-PH-I.pdf | 13 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA-Form-3-DGT-PH-I- Paradise.pdf | 13 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate DGT Phase 1 Glory Delight Bliss Fortune.pdf | 23 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DGT Phase 1 Bliss Delight Fortune Glory.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dosti greater thane Ph1.pdf | 5 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dosti greater thane Ph1.pdf | 5 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Dosti greater Thane Phase 1.pdf | 18 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: DGT - Phase 1.pdf | 11 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate DGT Phase 1.pdf | 20 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 DGT Ph1 March 2023.pdf | 19 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Dosti Greater Thane - Phase 1 - Bliss-Fortune Shops - Sold-Unsold Data.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dosti greater Thane Phase 1_compressed.pdf | 11 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dosti greater thane Phase 1_compressed.pdf | 11 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch certificate Dosti Greater Thane PH1 dated March 2020 Signed.pdf | 6 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 DGT PH1 March 2021.pdf | 6 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate DGT Ph1.pdf | 6 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Dosti Greater Thane Ph 1 March 2020.pdf | 6 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No 2 DGT PH 1 March 2021.pdf | 6 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Dosti Greater thane Phase 1 Dec 2022.pdf | 6 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Dosti Greater Thane PH 1 March 2020.pdf | 6 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 DGT PH1 signed march 2021.pdf | 6 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: DGT - Sold and Unsold Inventory.pdf | 31 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate DGT Phase 1.pdf | 25 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-DGT-Phase 1.pdf | 21 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate DGT Phase 1.pdf | 12 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate DGT.pdf | 12 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5-DGT-PH1.pdf | 12 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5-DGT-PARADISE.pdf | 12 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate-DGT PH1.pdf | 23 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate-DGT PH1.pdf | 23 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-DGT PH1.pdf | 23 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dosti Greater Thane-Sept 2022.pdf | 7 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate DGT PHASE 1.pdf | 18 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate DGT PHASE 1.pdf | 18 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate DGT PHASE 1.pdf | 18 Jul 2022 |
| Details of encumbrancesFile: Index II - DGT Phase 1 - Details of Encumbrances_compressed.pdf | 4 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate DGT Ph1.pdf | 2 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate DGT Ph1.pdf | 2 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate DGT Ph 1.pdf | 2 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Dosti Greater Thane Phase 1Form 5.pdf | 7 Jan 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form No 3 CA Certificate Sept 2021 DGT Ph 1_compressed.pdf | 20 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 DGT PH 1.pdf | 12 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: FORTUNE AND BLISS COMPILED.pdf | 8 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: DELIGHT AND GLORY COMPRESSED.pdf | 8 Oct 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations, which the RERA portal never shows together
- All 124 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DOSTI GREATER THANE - PHASE 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR UMIYA COMPLEX AND S S HOSPITAL7,600+ in Thane
GODREJ UPAVAN
PRAKHHYAT DWELLINGS LLP
DGT - Sector 3A - Cluster 2 - Phase 1
ADRIKA DEVELOPERS PRIVATE LIMITED
Dosti Greater Thane - Sector 3A - Cluster 1B -
ADRIKA DEVELOPERS PRIVATE LIMITED
USHA RESIDENCY
SHREE BUDHDEV INFRA
NARAYANI DHAM BUILDING NO 2A AND 2B
MAYA DEVELOPER
DGT - Sector 3A - Cluster 2 - Phase 2
ADRIKA DEVELOPERS PRIVATE LIMITED
See every Thane project, with the district possession charts
Builder: ADRIKA DEVELOPERS PRIVATE LIMITED
ADRIKA DEVELOPERS PRIVATE LIMITED has 9 registrations on MahaRERA, including DOSTI GREATER THANE - PHASE 1 and DOSTI GREATER THANE- PHASE 1 - DOSTI PARADISE. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that DOSTI GREATER THANE - PHASE 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DOSTI GREATER THANE - PHASE 1 is delayed beyond 1 Apr 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DOSTI GREATER THANE - PHASE 1?
The registered promoter entity is ADRIKA DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DOSTI GREATER THANE - PHASE 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DOSTI GREATER THANE - PHASE 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DOSTI GREATER THANE - PHASE 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DOSTI GREATER THANE - PHASE 1?
The professionals named in the filing: Architect: JAY VORA; Engineer: SWAPNIL RAMESH LONDHE; Chartered Accountant: MANISH BARDIA; Chartered Accountant: BAGADE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DOSTI GREATER THANE - PHASE 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.