Home / Browse projects / Pune, Maharashtra / CLOVER HIGHLANDS
CLOVER HIGHLANDS
RG-MH-10393 · RERA P52100005703 · Last updated on MahaRERA portal: 10 Dec 2025
Source: official MahaRERA filing
Red flags
- 3 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CLOVER HIGHLANDS is a Residential / Group Housing project by Clover Developers Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100005703 on 11 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2026. 56 of the 168 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameCLOVER HIGHLANDS
- TypeResidential / Group Housing
- Location
- NIBM ROAD
- KONDHWA
- kondhwa khurd
- Haveli
- Pune
- 411048
- Pincode411048
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100005703
- ReraGenie IDRG-MH-10393
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on11 Aug 2017
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings2 building records
- Documents filed122 files
Current status
Figures as on 10 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING 8 | NA | 26 | 21 | 84 | 0 | 84 |
| WING 9 | NA | 26 | 21 | 84 | 0 | 84 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 10 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 99%.
WING 899%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 99% |
WING 999%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 99% |
Progress on shared amenities15
As on 10 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 99% |
| Water Supply | Yes | 98% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 99% |
| Storm Water Drains | Yes | 99% |
| Landscaping & Tree Planting | Yes | 99% |
| Street Lighting | Yes | 99% |
| Community Buildings | Yes | 98% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 99% |
| Solid Waste Management And Disposal | Yes | 99% |
| Water conservation /Rain water harvesting | Yes | 99% |
| Energy managemcnt | Yes | 10% |
| Fire protection and fire safety requirements | Yes | 99% |
| Electrical meter room, sub-station, receiving station | Yes | 99% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 99% |
Parking filed396
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING 8 | 195 | 10 | 205 |
| WING 9 | 182 | 9 | 191 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| EVERJOY CO-OP HSG SOCTY LTD | kondhwa khurd | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING 8 | NA | Rs 47.55 cr | Rs 45.75 cr |
| WING 9 | NA | Rs 47.55 cr | Rs 45.75 cr |
| - | NA | Rs 14.97 cr | Rs 12.50 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rameshwari Sangani Sangani |
| Engineer | Shubhangi Harpale |
| Chartered Accountant | PARAM & CO |
| Chartered Accountant | CA Manojkumar Agarwal |
| Partner | Role in project |
|---|---|
| Clover Developers Pvt Ltd | - |
Litigation declared10
| Case | Court | Status |
|---|---|---|
| C C 467/2016/2016 | District Consumer Disputes Redressal Forum Pune | case is withdrawal by the complainnant |
| SCS No 867/2018/2018 | In the Court of Civil Judge Senior Division Pune | suit is decreed |
| ST- No 19946/2018/2018 | Mumbai High Court | case is withdrawal by the complainnant |
| ST NO 19174/2019 | Bombay High Court | Disposed |
| ST NO 19176/2019 | Bombay High Court | Application Rejected |
| 1005092/2018 | DDR Cooperative Societies and Competent Authority Pune | Rejected Dismissed |
| 281/0 | High Court of Bombay | Appeal admitted and Pending |
| 419/2021 | DDR Cooperative Societies and Competent Authority Pune | DISPOSED |
| 7247/2023 | Mumbai High Court | Petition Admitted |
| 12687/2023 | Supreme Court of India | DISPOSED |
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000022943 | PRAVIN S. NADKARNI | CLOVER DEVELOPERS PVT. LTD. | 21/04/2019 |
| CC005000000022298 | VICE ADMIRAL D. SAI PRASAD VARMA | RAJ KANAKSEN BHANSALI | 26/11/2018 |
| CC005000000043696 | Rakhee Sachdev | CLOVER DEVELOPERS PVT LTD | 22/11/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Jan 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Jan 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 1 Jul 2022
Documents filed122
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 10 Dec 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 10 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 (2).pdf | 10 Dec 2025 |
| Form 1File: F1.pdf | 3 Jul 2025 |
| Form 2File: F2.pdf | 3 Jul 2025 |
| Form 3File: F3.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: list.pdf | 3 Jul 2025 |
| Form 1File: F1.pdf | 3 Jul 2025 |
| Form 2File: F2.pdf | 3 Jul 2025 |
| Form 3File: F3.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: List.pdf | 3 Jul 2025 |
| Form 1File: F1.pdf | 3 Jul 2025 |
| Form 2File: F2.pdf | 3 Jul 2025 |
| Form 3File: F3.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: List.pdf | 3 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1.pdf | 28 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2.pdf | 28 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1.pdf | 3 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2.pdf | 3 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1.pdf | 21 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2.pdf | 21 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf | 14 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2.pdf | 14 Nov 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: reg.pdf | 14 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 18 Jul 2023 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 11 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SCAN-CBPL_04052023_125920_088592.pdf | 10 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SCAN-CBPL_04052023_125942_088598.pdf | 10 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SCAN_20230117_164937_081064.pdf | 13 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SCAN_20230117_164840_081056.pdf | 13 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf | 21 Feb 2023 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 8 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 24 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf | 30 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2.pdf | 30 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 9 Aug 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate_compressed.pdf | 9 Aug 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PHOTO-2022-05-30-16-27-29 (1).pdf | 1 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Wing No 8_compressed _compressed.pdf | 12 May 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Wing No 9_compressed fin.pdf | 12 May 2022 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 12 May 2022 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 12 May 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion.pdf | 12 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 16-04-2022.pdf | 9 May 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Form 16-04-2022_compressed (1).pdf | 9 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - 16-01-2022.pdf | 6 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Form 2 15-01-2022_compressed_compressed.pdf | 6 Apr 2022 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 24 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect July 2021-compressed.pdf | 23 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Form 2 July 2021-compressed.pdf | 23 Aug 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 13 Aug 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 13 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5-CD.pdf | 13 Aug 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion.pdf | 10 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Clover Highlands 8 Bldg.pdf | 6 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Clover Highlands 9 Bldg.pdf | 6 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5.pdf | 4 Aug 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 7 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH - DEC 2019.pdf | 15 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH - DEC 2021.pdf | 15 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH - JUN 2020.pdf | 15 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH - MAR 2020.pdf | 15 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH - MAR 2021.pdf | 15 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH - SEP 2020.pdf | 15 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ENGG - SEP 2020.pdf | 15 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG - DEC 2019.pdf | 15 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG - DEC 2020.pdf | 15 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG - JUN 2020.pdf | 15 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG - JUN 2020.pdf | 15 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG - MAR 2020.pdf | 15 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG - MAR 2021.pdf | 15 Jun 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 26 May 2021 |
| Certificates of CA (Form 3)File: CA certificate_dev.pdf | 12 May 2021 |
| Certificates of CA (Form 3)File: CA Certificate_Mar 20.pdf | 23 Apr 2021 |
| Details of Restarting of Construction work post lockdownFile: COVID 19 - LETTER.pdf | 24 Jul 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5-Clover Developers.pdf | 5 Apr 2020 |
| Certificates of CA (Form 3)File: clover developers dec19_.pdf | 27 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: cdpl archi.pdf | 13 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: cdpl archi.pdf | 13 Jan 2020 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Clover Higlands | Nibm road | 446 | Completed | Mar 2007 | Mar 2007 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 122 filed documents as one ZIP, foldered, with a manifest
Keep CLOVER HIGHLANDS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KONDHWA13,700+ in Pune
Filed coordinates, straight-line distance. 198 registered projects within 2 km.
Dwarikadham
Yashodhan Affordable Landmark LLP
UNITAS FASHION CENTER
UNITATIS DEVELOPMENTS PVT. LTD
Millennium Park
Xrbia Epoch Creations LLP
BABAR CLASSIC VISTA WING E, F, G
Classic Properties
JITO NAGAR
JAIN ASHAPURI DEVELOPER UNIT II
Wellwisher West Views
Bhansali Infrastructure LLP
Builder: Clover Developers Pvt Ltd
Clover Developers Pvt Ltd has 2 registrations on MahaRERA, including CLOVER HIGHLANDS and Clover Business Center. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if CLOVER HIGHLANDS is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CLOVER HIGHLANDS?
The registered promoter entity is Clover Developers Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CLOVER HIGHLANDS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against CLOVER HIGHLANDS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for CLOVER HIGHLANDS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CLOVER HIGHLANDS?
The professionals named in the filing: Architect: Rameshwari Sangani Sangani; Engineer: Shubhangi Harpale; Chartered Accountant: PARAM & CO; Chartered Accountant: CA Manojkumar Agarwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CLOVER HIGHLANDS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback