CLASSIC PRIDE
RG-MH-18343 · RERA P52000056368 · Last updated on MahaRERA portal: 24 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 8 months past the filed date
- Completion date moved by 9 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CLASSIC PRIDE is a Residential / Group Housing project by SHIV CLASSIC ENTERPRISES in Raigarh, Maharashtra, registered with MahaRERA as P52000056368 on 31 May 2024. Possession was promised by 28 Feb 2026 and is now 8 months past that date. The completion date has moved by 9 months from the original filing. 13 of the 41 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameCLASSIC PRIDE
- TypeResidential / Group Housing
- Location
- SECTOR 16 E
- KALAMBOLI
- Panvel
- Raigarh
- 410218
- Pincode410218
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000056368
- ReraGenie IDRG-MH-18343
Builder
- NameSHIV CLASSIC ENTERPRISES
- Entity typePartnership
- PartnersMEHUL BHARAT SHAH, Datta Maruti Thorat
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 May 2024
- Promised completion28 Feb 2026
- Revised completionRevised to 28 Feb 2026 (originally 30 May 2025)
- Buildings1 building record
- Documents filed115 files
Current status
Figures as on 24 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CLASSIC PRIDE | NA | 8 | 8 | 36 | 5 | 41 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
CLASSIC PRIDE: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed39
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership5
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| NAMDEV KANHA PATIL | Rodpali | Raigarh |
| RAMCHANDRA KANHA PATIL | Rodpali | Raigarh |
| GURUNATH KANHA PATIL | Rodpali | Raigarh |
| NIRMALA VISHNU BHOIR | Waje | Raigarh |
| CHHABI LAXMAN PATIL | Navi Mumbai (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| CLASSIC PRIDE | NA | Rs 7.71 cr | Rs 7.48 cr |
| - | NA | Rs 11.00 lakh | Rs 4.40 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AMIT N PATIL Architects and Planners |
| Engineer | AGHARKAR CONSULTANTS |
| Chartered Accountant | A T Upadhye & Co |
| Partner | Role in project |
|---|---|
| SHIV CLASSIC ENTERPRISES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe, Shiv Classic Enterprises, promoters of the registered project "Classic Pride" (Registration No. P52000056368), humbly submit this application for an extension of the project registration, originally valid up to 30/05/2025, and now sought to be extended to 31/08/2025. The primary reason for seeking this extension is the delay in the issuance of the Occupation Certificate (OC) despite the construction of the project being completed well within the stipulated timeline. We have proactively submitted all necessary documentation and complied with the procedural requirements of the concerned auth
Reason as filed by the promoterWe have diligently completed the construction of the project and applied for the Occupation Certificate (OC) well in advance. However, the issuance of the OC has been delayed due to procedural timelines set by the relevant authorities, which are beyond our control. Despite our continuous efforts to expedite the process and comply with all necessary requirements, the delay in obtaining the OC has impacted our ability to hand over possession as per the original schedule. Therefore, we respectfully request an extension of the possession date to accommodate this unforeseen delay.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 May 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 May 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 May 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed115
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form 1 architechts certificate december.pdf | 24 Jun 2026 |
| Withdrawal Update Form 1File: form 1 architechts certificate december.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: Shiv classic - Q3 - Form 2.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: Shiv classic - Q3 - Form 2.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: form 3 3-10-25.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: form 3 3-10-25.pdf | 24 Jun 2026 |
| Withdrawal Update Form 1File: form -1.pdf | 26 Mar 2026 |
| Withdrawal Update Form 2File: form -2.pdf | 26 Mar 2026 |
| Withdrawal Update Form 3File: form 3 3-10-25.pdf | 26 Mar 2026 |
| Form 5 (FY 2024-2025)File: Shiv Classic form 5.pdf | 26 Sep 2025 |
| Form 2A (FY 2024-2025)File: Form 2A shiv classic.pdf | 18 Sep 2025 |
| Form 2A (FY 2025-2026)File: Form 2A (1).pdf | 18 Sep 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 9 Sep 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 9 Sep 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 9 Sep 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 9 Sep 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 9 Sep 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 9 Sep 2025 |
| Withdrawal Update Form 3File: SHIV CLASSIC form 3 signed.pdf | 9 Sep 2025 |
| Withdrawal Update Form 3File: SHIV CLASSIC form 3 signed.pdf | 9 Sep 2025 |
| Withdrawal Update Form 3File: SHIV CLASSIC form 3 signed.pdf | 9 Sep 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 8 Sep 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 8 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 - Dec 24.pdf | 8 Sep 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 - Dec 24.pdf | 30 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 - Dec 24.pdf | 30 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 - Dec 24.pdf | 30 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 - Dec 24.pdf | 30 Aug 2025 |
| Withdrawal Update Form 1File: shiv classic from 1-31-3-2025.pdf | 29 Aug 2025 |
| Withdrawal Update Form 2File: shiv classic from 2-31-3-2025.pdf | 29 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 - Dec 24.pdf | 29 Aug 2025 |
| Withdrawal Update Form 1File: Form 1 s.pdf | 23 Aug 2025 |
| Withdrawal Update Form 1File: shiv classic From 1-Architect.pdf | 23 Aug 2025 |
| Withdrawal Update Form 1File: Form 1 - Dec 24.pdf | 23 Aug 2025 |
| Withdrawal Update Form 2File: Form 2 e.pdf | 23 Aug 2025 |
| Withdrawal Update Form 2File: Shiv classic From 2-Enginear.pdf | 23 Aug 2025 |
| Withdrawal Update Form 2File: Form 2 - Dec 24.pdf | 23 Aug 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 23 Aug 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 23 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 - Dec 24.pdf | 23 Aug 2025 |
| Form 1File: Form 1 s.pdf | 21 Aug 2025 |
| Form 2File: Form 2 e.pdf | 21 Aug 2025 |
| Form 3File: Form 3.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: sold booked inventory plot no - 85.pdf | 21 Aug 2025 |
| Form 1File: shiv classic From 1-Architect.pdf | 21 Aug 2025 |
| Form 2File: Shiv classic From 2-Enginear.pdf | 21 Aug 2025 |
| Form 3File: Form 3.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold signed final.pdf | 21 Aug 2025 |
| Form 1File: Form 1 - Dec 24.pdf | 21 Aug 2025 |
| Form 2File: Form 2 - Dec 24.pdf | 21 Aug 2025 |
| Form 3File: Form 3 - Dec 24.pdf | 21 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked - Dec 24.pdf | 21 Aug 2025 |
| Form 1File: Form 1 - Mar 25.pdf | 6 Jun 2025 |
| Form 2File: Form 2 - Mar 25.pdf | 6 Jun 2025 |
| Form 3File: Form 3.pdf | 6 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked.pdf | 6 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: compliance with QPR final.pdf | 6 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mar 25.pdf | 8 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: shiv classic sold inventory -31-3-2025.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mar 25.pdf | 4 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 24_compressed.pdf | 30 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 24.pdf | 8 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 24.pdf | 8 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Booked - Dec 24.pdf | 8 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 shiv classic_compressed.pdf | 20 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 shiv classic_compressed.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: shiv classic From 1-Architect.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv classic From 2-Enginear.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold signed.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf | 12 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 s.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 e.pdf | 20 Jul 2024 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| CLASSIC AMRUTP52100054029 | RAJGURUNAGAR, Pune | 71 | Dec 2023 | Ongoing | Oct 2026 | Not due yet |
| TURTLE SPARSHP52000053646 | SECTOR 18, Raigarh | 14 | Nov 2023 | Ongoing | Dec 2025 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 115 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep CLASSIC PRIDE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KALAMBOLI5,900+ in Raigarh
Filed coordinates, straight-line distance. 75 registered projects within 2 km.
Plot No -77 Sector -17 Kalamboli Bus Depot
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
BHAVESHWAR AQUA - 1
BHAVESHWAR INFRATECH
ETERNIA
GREENSCAPE DEVELOPERS PRIVATE LIMITED
MONARCH BROOKEFIELDS
MONARCH BROOKEFIELDS LLP
BHAVESHWAR AQUA - 2
BHAVESHWAR INFRATECH
OM REGENCY
OSCAR INFRASTRUCTURE PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: SHIV CLASSIC ENTERPRISES
SHIV CLASSIC ENTERPRISES has 1 registration on MahaRERA, including CLASSIC PRIDE. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that CLASSIC PRIDE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if CLASSIC PRIDE is delayed beyond 28 Feb 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CLASSIC PRIDE?
The registered promoter entity is SHIV CLASSIC ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CLASSIC PRIDE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CLASSIC PRIDE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CLASSIC PRIDE?
The professionals named in the filing: Architect: AMIT N PATIL Architects and Planners; Engineer: AGHARKAR CONSULTANTS; Chartered Accountant: A T Upadhye & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CLASSIC PRIDE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback