Home / Browse projects / Raigarh, Maharashtra / OM REGENCY

Completed Litigation declared Others project

OM REGENCY

By OSCAR INFRASTRUCTURE PRIVATE LIMITED

RG-MH-28800 · RERA P52000027435 · Last updated on MahaRERA portal: 1 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
21 of 218Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

OM REGENCY is a Others project by OSCAR INFRASTRUCTURE PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000027435 on 10 Dec 2020. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 6 months from the original filing. 197 of the 218 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameOM REGENCY
  • TypeOthers
  • Location
    • SECTOR 15
    • TALOJA
    • Taloje Panchnad
    • Panvel
    • Raigarh
    • 410218
  • Pincode410218
  • RERA no.P52000027435
  • ReraGenie IDRG-MH-28800

Builder

  • NameOSCAR INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsRAHUL JAGANNATH JOSHI, Harmesh Rahul Joshi, Kamesh Rahul Joshi
  • Other registrations6 more →
  • Completed3 of 7
  • Declared earlier projects3 →

Key dates

this monthRegisteredDec 2020First promiseJun 2025Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Dec 2020
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed89 files

Current status

90%197 of 218 units booked
100.0%Work done, per cost certificate

Figures as on 1 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OM REGENCYNA191519424218

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

OM REGENCY: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed160

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots160
Closed/Covered151
Open Space9

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,250 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI7874.37
Proposed, not sanctioned7,874 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLBS MARGH MULUND WEST
Estimated costRs 46.20 cr
Cost incurredRs 46.20 cr
Work done100.0%
BuildingWingEstimatedIncurred
OM REGENCYNARs 23.10 crRs 23.10 cr
-NARs 23.10 crRs 23.10 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL PATEL
EngineerRAVIN PATEL
Chartered AccountantA ABHISHEK & COMPANY
Chartered AccountantHimmat Shethia
PartnerRole in project
OSCAR INFRASTRUCTURE PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000026059Jun 2025 → Dec 2025

Reason as filed by the promoterWe are writing to bring to your attention that due to unforeseen challenges, including a shortage of manpower and delays in material supply, the completion timeline for our project has been extended. Despite these setbacks, we are pleased to inform you that all major work for both wings of the project has been successfully completed. To support this, we have attached the architect’s certificate confirming the completion of major works. We are currently in the process of obtaining the Occupancy Certificate (OC) and are committed to ensuring all requirements are met promptly. In light of the abo

Litigation declared3

CaseCourtStatus
190/2010PANVELOngoing
341/2013PANVELOngoing
190/2010PanvelOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: OC.pdf1 Jun 2026
Withdrawal Update Form 1File: OC date August 25.pdf30 May 2026
Withdrawal Update Form 1File: Form 4 signed.pdf30 May 2026
Withdrawal Update Form 2File: Rera Form 2 Om Regency Sep 2025.pdf30 May 2026
Withdrawal Update Form 2File: Rera Form 2 Om Regency dec 2025.pdf30 May 2026
Withdrawal Update Form 3File: Form 3 - Regency OC date.pdf30 May 2026
Withdrawal Update Form 3File: Form 3 - Regency dec 25.pdf30 May 2026
Withdrawal Update Form 1File: Form 1 - june 25.pdf26 May 2026
Withdrawal Update Form 2File: Rera Form 2 - Om Regency - June 2025.pdf26 May 2026
Withdrawal Update Form 3File: Form 3 - Regency june25.pdf26 May 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Regency mar 25 new.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera_Form_2_-_Taloja_March_2025.pdf26 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera_Form_2_-_Taloja_March_2025.pdf26 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: March 25.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Regency june24.pdf4 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Regency Dec 24.pdf4 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Regency sept 24.pdf4 Jan 2025
Declaration about Commencement CertificateFile: DECLARATION ABOUT cc.pdf4 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA 2.pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2024 MARCH).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2024 JUNE).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2023 SEPTEMBER).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2022 SEP).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2022 MARCH).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2022 JUNE).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2023 SEPTEMBER).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2022 MARCH).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2022 MARCH).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2022 JUNE).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA (2020 DEC).pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1) june 20.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Revised Form 2 - Oscar Infra - Taloja March 2024.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Form 2A - OM Residency - Taloja - March 2024.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Form 2 - Oscar Infra - Taloja March 2024.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Form 2 - Oscar Infra - Taloja Dec 2023.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Form 2 - OM Regency - Taloja - Sep 23.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Form 2 - Om Regency - Sep 2022.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- OM Regency - June 2024.pdf3 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - OM Regency - March 2021.pdf3 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - OM Regency - March 2022.pdf3 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Rera Form 2A - OM Residency - Taloja - March 2024.pdf3 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21 - signed.pdf26 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21 - Signed.pdf26 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22 - Signed.pdf26 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22 - signed.pdf26 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 2021.pdf11 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March 2022.pdf11 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June 2022.pdf11 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sep 2022.pdf11 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 2022.pdf11 Mar 2023
Details of encumbrancesFile: New Encumbrances Certificate.pdf2 Feb 2023
OtherFile: Work Completion Photos Oscar.pdf5 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Taloja Form 3.pdf21 Jun 2022
OtherFile: Work Completion Photos OSCAR.pdf20 Apr 2022
OtherFile: 21 Work Completion Photos - Oscar.pdf22 Jan 2022
OtherFile: Work Completion Photos Oscar.pdf24 Oct 2021
OtherFile: Work Completion Photos PL4-4A.pdf22 Jul 2021
OtherFile: Work completion Photos OSCAR INFRASTRUCTURE.pdf12 Apr 2021
OtherFile: Work completion Photos OSCAR INFRASTRUCTURE.pdf12 Apr 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf3 Dec 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf26 Nov 2020
Copy of the legal title reportFile: Title Certificate.pdf10 Nov 2020
Copy of the legal title reportFile: Search Report No 4.pdf10 Nov 2020
Copy of the legal title reportFile: Search Report Plot No 4A.pdf10 Nov 2020
Copy of the legal title reportFile: Search Report plot no 5.pdf10 Nov 2020
Layout approvalFile: blue print-1-4.pdf4 Nov 2020
Layout approvalFile: blue print-5-8.pdf4 Nov 2020
Layout approvalFile: blue print-9-12.pdf4 Nov 2020
Layout approvalFile: blue print-13-16.pdf4 Nov 2020
Building plan approvalFile: blue print-1-4.pdf4 Nov 2020
Building plan approvalFile: blue print-5-8.pdf4 Nov 2020
Building plan approvalFile: blue print-9-12.pdf4 Nov 2020
Building plan approvalFile: blue print-13-16.pdf4 Nov 2020
Copy of Layout Approval (in case of layout)File: blue print-1-4.pdf4 Nov 2020
Copy of Layout Approval (in case of layout)File: blue print-5-8.pdf4 Nov 2020
Copy of Layout Approval (in case of layout)File: blue print-9-12.pdf4 Nov 2020
Copy of Layout Approval (in case of layout)File: blue print-13-16.pdf4 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: blue print-1-4.pdf4 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: blue print-5-8.pdf4 Nov 2020

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
OM Neelkanth DarshanP51800032659Ghatkopar East, Mumbai SuburbanJan 2022CompletedJun 2025Registered original: Dec 2023Mar 2025
OM RESIDENCYP51800026044Mulund west, Mumbai SuburbanAug 2020CompletedJun 2023Mar 2023

How this compares with Raigarh

90%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 6 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OM REGENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TALOJA5,900+ in Raigarh

Builder: OSCAR INFRASTRUCTURE PRIVATE LIMITED

Oscar Infrastructure Private Limited has 7 registrations on MahaRERA, including OM RESIDENCY and OM REGENCY. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if OM REGENCY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OM REGENCY?

The registered promoter entity is OSCAR INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OM REGENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OM REGENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OM REGENCY?

The professionals named in the filing: Architect: ATUL PATEL; Engineer: RAVIN PATEL; Chartered Accountant: A ABHISHEK & COMPANY; Chartered Accountant: Himmat Shethia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM REGENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM REGENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM REGENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.