Home / Browse projects / CHESTERFIELD WING A AND WING B
CHESTERFIELD WING A AND WING B
By KALYANEE FORTUNE PROPERTIES
RG-MH-19923 · RERA P52100003511 · Last updated on MahaRERA portal: 18 Feb 2023
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CHESTERFIELD WING A AND WING B is a Others project by KALYANEE FORTUNE PROPERTIES in 411015, registered with MahaRERA as P52100003511 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2022. The completion date has moved by 18 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameCHESTERFIELD WING A AND WING B
- TypeOthers
- Location
- 411015
- Pincode411015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100003511
- ReraGenie IDRG-MH-19923
Builder
- NameKALYANEE FORTUNE PROPERTIES
- Entity typePartnership
- PartnersMOHANLAL BHURMALJI JAIN, SHEKHAR RAJNIKANT SHAH, NAYAN MOHANLAL JAIN, HITESH KISHORE JAIN, ROHIT KISHORE JAIN, KHUSHALCHAND JASRAJJI SANGHVI, MITESH KISHORE JAIN, DEEPAK MOHANLAL JAIN, TULSIBEN KHUSHALCHAND SANGHVI, SANJAY SHAMLAL AGARWAL
- Other registrations1 more →
- Completed2 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on5 Aug 2017
- Promised completion30 Dec 2022
- Revised completionRevised to 30 Dec 2022 (originally 30 Jun 2021)
- Buildings4 building records
- Documents filed37 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WiNG A | NA | 12 | 0 | 0 | 0 | 0 |
| WING B | NA | 12 | 0 | 0 | 0 | 0 |
| WING C COMMMERCIAL/ MHADA | NA | 5 | 0 | 0 | 0 | 0 |
| WING D FUTURE EXPANSION | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 18 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
28 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.
WiNG A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C COMMMERCIAL/ MHADA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING D FUTURE EXPANSION0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 18 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| WINNER PROMOTERS | Pune (CB) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CUBIX ARCHITECT |
| Partner | Role in project |
|---|---|
| KALYANEE FORTUNE PROPERTIES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have already completed and handed over possession of flats/shops/offices to Wing A, Wing B & Wing C Commercial/Mhada. We are still in process for finalization of Wing D with the society, which has received Commencement Certificate from Pune Municipal Corporation (Sanctioning Authority) on 15/12/2020. So the proposed date of completion needs to be changed to 30/06/2022
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000279837 | Avi Gangaram Jadhav | Mohanlal Bhurmalji Jain | 09/12/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Mar 2021
Documents filed37
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of Formation of Legal Entity (Society/Co Op etc.)File: CF C WING Society Registration Certificate.pdf | 18 Feb 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Chesterfield Society Registration Certificate.pdf | 17 Feb 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate - Wing A.pdf | 5 Mar 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate - Wing B.pdf | 5 Mar 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate - Wing C.pdf | 5 Mar 2021 |
| Certificates of CA (Form 5)File: KFP Chesterfield.pdf | 15 Oct 2018 |
| Certificates of CA (Form 3)File: Form 3 final.pdf | 29 Aug 2018 |
| Certificates of CA (Form 3)File: FINAL - FORM 3 CA CERTIFICATE-Dhanori 5-05-18.PDF | 19 May 2018 |
| Building plan approvalFile: Temp00231.pdf | 29 Jul 2017 |
| Layout approvalFile: Temp00232.pdf | 29 Jul 2017 |
| PAN CardFile: 001B nilesh agarwal.pdf | 29 Jul 2017 |
| PAN CardFile: 01B mohanlal jain pan card.pdf | 29 Jul 2017 |
| PAN CardFile: 02B pan card of shekhar shah.pdf | 29 Jul 2017 |
| PAN CardFile: 03B pancard deepak jain.pdf | 29 Jul 2017 |
| PAN CardFile: 04B pan card of nayan jain.pdf | 29 Jul 2017 |
| PAN CardFile: 05B pan card of hitesh jain.pdf | 29 Jul 2017 |
| PAN CardFile: 06B pan card of mitesh jain.pdf | 29 Jul 2017 |
| PAN CardFile: 07B pan card of rohit jain.pdf | 29 Jul 2017 |
| PAN CardFile: 08B pan card of tulsiban sangvi.pdf | 29 Jul 2017 |
| PAN CardFile: 09B pan card of khushalchand sanghvi.pdf | 29 Jul 2017 |
| PAN CardFile: 010B pancard of agarwal sanjay.pdf | 29 Jul 2017 |
| PAN CardFile: pan card of kfp.pdf | 29 Jul 2017 |
| PAN CardFile: pancard of Kishore Jain.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: Search Report07242017.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: no encumbrance letter kfp.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: no encumbrances letter.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Temp00232.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Temp00231.pdf | 29 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: SKMBT_C22017072919420.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: Form B - Winner Promoter- Chesterfield (2).pdf | 29 Jul 2017 |
| Declaration in FORM BFile: declaration- Form B-1.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: dh.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate revise chesterfield.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: Form 3 - Dhanori.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: Allotment letter revised final.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: dhanori ATS.pdf | 29 Jul 2017 |
| OtherFile: 7-12.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 37 filed documents as one ZIP, foldered, with a manifest
Keep CHESTERFIELD WING A AND WING B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near this project
Kohinoor Viva Pixel- Phase II
RISING ASSOCIATES
VIVACITY
REALCON LANDMARKS LLP
TRIAA VASANTAM CITY CENTER PHASE 1
Triaa Realtors LLP
QUE 101 PHASE I
ANNR Unique Realty LLP
NYATI ERA I
NYATI CONSTRUCTION PRIVATE LIMITED
ONE ARETHA PHASE 1
Triaa Landmarks LLP
Builder: KALYANEE FORTUNE PROPERTIES
Kalyanee Fortune Properties has 2 registrations on MahaRERA, including KALASH PHASE 2 WING A AND B and CHESTERFIELD WING A AND WING B. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What are my rights if CHESTERFIELD WING A AND WING B is delayed beyond 30 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CHESTERFIELD WING A AND WING B?
The registered promoter entity is KALYANEE FORTUNE PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CHESTERFIELD WING A AND WING B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against CHESTERFIELD WING A AND WING B?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for CHESTERFIELD WING A AND WING B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CHESTERFIELD WING A AND WING B?
The professionals named in the filing: Architect: CUBIX ARCHITECT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CHESTERFIELD WING A AND WING B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.