CHAVAN TOWERS

By CHAVAN BUILDCON LLP

RG-MH-30001 · RERA P51500052851 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken
  • Rs 4.24 crore secured on the land, in favour of State Bank Of India

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 18 months from the original
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
49 of 60Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

CHAVAN TOWERS is a Others project by CHAVAN BUILDCON LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500052851 on 5 Oct 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 18 months from the original filing. 11 of the 60 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameCHAVAN TOWERS
  • TypeOthers
  • Location
    • Plot No 01 To 06
    • CTS No 16034/2/27
    • 16034/2/29
    • 16034/2/31
    • 16034/2/33
    • 16034/2/35
    • 16034/2/36
    • At Sahakar Nagar
    • Sahakar Nagar
    • Aurangabad (M Corp.)
    • ...
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500052851
  • ReraGenie IDRG-MH-30001

Builder

  • NameCHAVAN BUILDCON LLP
  • Entity typePartnership
  • PartnersSATISH BHANUDASRAO CHAVAN, PRADEEP BHANUDAS CHAVAN, DEELIP BHANUDAS CHAVAN

Key dates

this monthRegisteredOct 2023First promiseJun 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Oct 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 15 Jun 2026)
  • Buildings2 building records
  • Documents filed81 files

Current status

18%11 of 60 units booked
72.7%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A Type BuildingNA76201030
B Type BuildingNA76201030

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

A Type Building63%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B Type Building61%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed91

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots91
Closed/Covered91
BuildingClosed/CoveredTotal
A Type Building4141
B Type Building5050

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,554 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofState Bank Of India
Secured amountRs 4.24 crore
CERSAI search filedYes
Declared on14 Aug 2025
LandownerVillageDistrict
Satish Bhanudasrao ChavanAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI5300.0
Proposed, not sanctioned5,045 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchIndustrial Branch Aurangabad
Estimated costRs 14.02 cr
Cost incurredRs 10.19 cr
Work done72.66%
BuildingWingEstimatedIncurred
A Type BuildingNARs 5.03 crRs 3.65 cr
B Type BuildingNARs 4.99 crRs 3.63 cr
-NARs 4.00 crRs 2.91 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSARTHAK ASSOCIATES
EngineerYASHVANT PATIL AND ASSOCAITES
EngineerYashwant Patil & Assocaites
Chartered AccountantCA YASH NAGAR Nagar
Chartered AccountantSonawane Sahane & Associates
PartnerRole in project
CHAVAN BUILDCON LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA28042620760Jun 2026 → Dec 2027

Reason as filed by the promoterrespectfully request an extension of time for the completion of the project due to unforeseen delays. The slab work has been delayed owing to the migration of laborers during the festival season and poor coordination between contractors. Additionally, the progress of the wall and brickwork has been affected by supply chain issues, particularly fluctuations in cement prices. Financial constraints, stemming from a lack of demand from the allottee, have also contributed to the delay. In view of these challenges, we seek the authority’s kind consideration for an extension of time to complete the p

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECTE CERTIFICATE.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 2025-26 Q4..pdf20 Jul 2026
Withdrawal Update Form 3File: CA CERTIFICATE.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-26.pdf28 Apr 2026
Form 5 (FY 2025-2026)File: Form 5 signed..pdf28 Apr 2026
Withdrawal Update Form 1File: Form 1 2025-26 Q4.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 2025-26 Q4..pdf24 Apr 2026
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf24 Apr 2026
Building plan approvalFile: New Building Plan.pdf24 Feb 2026
Form 5 (FY 2024-2025)File: Form 5 2024-25 Sign.pdf21 Feb 2026
Withdrawal Update Form 1File: Form 1 2025-26 Q2.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1 2025-26 Q3..pdf12 Feb 2026
Withdrawal Update Form 2File: Form 2 2025-26 Q2.pdf12 Feb 2026
Withdrawal Update Form 2File: Form 2 2025-2 6Q3.pdf12 Feb 2026
Withdrawal Update Form 3File: Form 3 2025-26 Q2.pdf12 Feb 2026
Withdrawal Update Form 3File: Form 3 2025-26 Q3.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1 2025-26 Q1.pdf14 Aug 2025
Withdrawal Update Form 2File: Form 2 2025-26 Q1.pdf14 Aug 2025
Withdrawal Update Form 3File: Form 3 2025-26 Q1.pdf14 Aug 2025
Form 1File: FORM 1 -2023-24-Q3.pdf12 Aug 2025
Form 2File: FORM 2-2023-24-Q3.pdf12 Aug 2025
Form 3File: F0RM 3-2023-24 Q3.pdf12 Aug 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_2023-24-Q3.pdf12 Aug 2025
Form 1File: FORM 1 2024-25-Q2.pdf12 Aug 2025
Form 2File: FORM 2-2024-25-Q2.pdf12 Aug 2025
Form 3File: FORM 3-2024-25-2.pdf12 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold 2024-25 Q2.pdf12 Aug 2025
Form 1File: FORM 1-2024-25-Q1.pdf12 Aug 2025
Form 2File: FORM 2 -2024-25-Q1.pdf12 Aug 2025
Form 3File: FORM 3-2024-25-Q1.pdf12 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold 2024-25-Q1.pdf12 Aug 2025
Form 1File: FORM 1 -2024-25-Q3.pdf12 Aug 2025
Form 2File: FORM 2 -2024-25-Q3.pdf12 Aug 2025
Form 3File: FORM 3-2024-25 Q3.pdf12 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ 2024-25-Q3.pdf12 Aug 2025
Building plan approvalFile: 1734501076_DDMCB-24-ENTRY-105554_R1pdf_8_34DSE_Si_250416_155725.pdf3 Jul 2025
Form 1File: Form 1 2024-25 Q4.pdf23 May 2025
Form 2File: Form 2 2024-25 Q4.pdf23 May 2025
Form 3File: Form 3 2024-25 Q4 Sign.pdf23 May 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 2024-25 Q4.pdf23 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 2024-25 Q2.pdf7 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 2024-25 Q3 Revised.pdf7 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2024-25 Q2.pdf6 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2024-25 Q3.pdf6 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 2024-25 Q2.pdf6 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 2024-25 Q3.pdf6 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold 2024-25 Q2.pdf6 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold 2024-25 Q3.pdf6 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 2024-25 Q1.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2024-25 Q1.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 2024-25 Q1.pdf15 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold 2024-25 Q1.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CRETIFICATE.pdf12 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf12 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf12 Feb 2024
Details of encumbrances concerned to FinanceFile: ilovepdf_merged.pdf26 Aug 2023
Details of encumbrances concerned to LegalFile: ilovepdf_merged.pdf26 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: _Decleration of Commencement Certificate_page-0001.pdf26 Aug 2023
Other - FinanceFile: DocScanner 25-Aug-2023 1-16 pm.pdf26 Aug 2023
Copy of the legal title reportFile: Revised Maharera Search Report.pdf9 Aug 2023
PAN CardFile: Firms PAN Card.pdf14 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200273816966_For_Asset_Based_Search_09_07_2023_15_45_44_756.pdf14 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ - Copy.pdf6 Jul 2023
Declaration in FORM BFile: CCF30062023.pdf30 Jun 2023
Layout approvalFile: Amalgamation Layout Plan.pdf27 Jun 2023
Copy of Layout Approval (in case of layout)File: Amalgamation Layout Plan.pdf27 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations_page-0001.pdf22 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Saperate Bank Account Declaration.pdf22 Jun 2023
Deviation Report with respect to Allotment letterFile: Deviation Report With Respect To Allotment Letter.pdf22 Jun 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report With Respect To Model Copy of Agreement.pdf22 Jun 2023
Building plan approvalFile: Approved Plan 1-1.pdf21 Jun 2023
Building plan approvalFile: Approved Plan 2-2.pdf21 Jun 2023
Details of encumbrances concerned to FinanceFile: No encumbrance and legal merged.pdf21 Jun 2023
Details of encumbrances concerned to LegalFile: No encumbrance and legal merged.pdf21 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan 1-1.pdf21 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan 2-2.pdf21 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_rotated.pdf21 Jun 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf21 Jun 2023
Proforma of Agreement for saleFile: Agreement To Sale_11zon.pdf21 Jun 2023

How this compares with Aurangabad

18%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 18 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep CHAVAN TOWERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sahakar Nagar1,400+ in Aurangabad

2 kmCHAVAN TOWERSCompleted 46Lapsed / revoked 38Other 52Dot size: filed unitsN

Filed coordinates, straight-line distance. 136 registered projects within 2 km.

Builder: CHAVAN BUILDCON LLP

CHAVAN BUILDCON LLP has 1 registration on MahaRERA, including CHAVAN TOWERS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if CHAVAN TOWERS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CHAVAN TOWERS?

The registered promoter entity is CHAVAN BUILDCON LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CHAVAN TOWERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CHAVAN TOWERS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CHAVAN TOWERS?

The professionals named in the filing: Architect: SARTHAK ASSOCIATES; Engineer: YASHVANT PATIL AND ASSOCAITES; Engineer: Yashwant Patil & Assocaites; Chartered Accountant: CA YASH NAGAR Nagar; Chartered Accountant: Sonawane Sahane & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CHAVAN TOWERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CHAVAN TOWERS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CHAVAN TOWERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.