ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Chandraprabha

Completed No litigation declared Residential / Group Housing project

Chandraprabha

By Manisha Supreme Realty LLP

RG-MH-88671 · RERA P51800048875 · Last updated on MahaRERA portal: 7 Feb 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
May 2026Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
65 of 89Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

Chandraprabha is a Residential / Group Housing project by Manisha Supreme Realty LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800048875 on 24 Jan 2023. The registration is recorded completed; possession was promised by 31 May 2026. 24 of the 89 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameChandraprabha
  • TypeResidential / Group Housing
  • Location
    • Junction of Murar Road and Baba Praduman Singh Road
    • Mulund West
    • Mumbai
    • Mulund
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800048875
  • ReraGenie IDRG-MH-88671

Builder

  • NameManisha Supreme Realty LLP
  • Entity typePartnership
  • PartnersGirish Govind Naidu, Govindrajulu Papa Naidu

Key dates

this monthRegisteredJan 2023PromisedMay 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Jan 2023
  • Promised completion31 May 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed88 files

Current status

27%24 of 89 units booked
98.7%Work done, per cost certificate

Figures as on 7 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ChandraprabhaNA181389089

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

Chandraprabha: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 7 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed108

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots108
Closed/Covered76
Open Space32

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,673 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Chandra Prabha Co Operative Housing Society LtdMulundMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4927.18
Proposed, not sanctioned2,004 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 04, Runwal Anthurium Retail, LBS Marg, Veena Nagar, Mumbai - 400080
Estimated costRs 22.10 cr
Cost incurredRs 21.81 cr
Work done98.67%
BuildingWingEstimatedIncurred
ChandraprabhaNARs 21.00 crRs 20.72 cr
-NARs 1.10 crRs 1.09 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNASA Architectural Consultants Pvt. Ltd.
EngineerSK Consultants & Engineers
Chartered AccountantRutuja Narsingh & Associates
Chartered AccountantNB Sayed & Associates
PartnerRole in project
Manisha Supreme Realty LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Chandraprabha as on Dec 2025.pdf7 Feb 2026
Withdrawal Update Form 2File: Form 2 - Chandraprabha as on Dec 2025.pdf7 Feb 2026
Withdrawal Update Form 3File: Form 3 - Chandraprabha as on Dec 2025.pdf7 Feb 2026
Form 5 (FY 2024-2025)File: Form 5 Chandraprabha 2024-2025.pdf31 Dec 2025
Withdrawal Update Form 1File: Form 1 - Chandraprabha as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 2File: Form 2 - Chandraprabha as on Sept 2025.pdf1 Nov 2025
Withdrawal Update Form 3File: Form 3 - Chandraprabha as on Sept 2025.pdf1 Nov 2025
Withdrawal Update Form 1File: Form 1 - Chandraprabha as on Sep 2025.pdf20 Oct 2025
Withdrawal Update Form 2File: Form 2 - Chandraprabha as on Sept 2025.pdf20 Oct 2025
Withdrawal Update Form 3File: Form 3 - Chandraprabha as on Sept 2025.pdf20 Oct 2025
Form 1File: Form 1 - Chandraprabha as on June 2025.pdf20 Jul 2025
Form 2File: Form 2 - Chandraprabha as on June 2025.pdf20 Jul 2025
Form 3File: Form 3 - Chandraprabha as on June 2025.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Chandraprabha as on June 2025.pdf20 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Chandraprabha as on March 2025.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on 31-03-2025.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Chandraprabha as on March 2025.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Chandraprabha as on Dec 2024.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on Dec 2024.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Chandraprabha as on Dec 2024.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Cp-Circular 29.pdf14 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Chandraprabha as on 30-09-2024.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on 30-09-2024.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Chandraprabha as on 30-09-2024.pdf20 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Chandraprabha 31st March 2024.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Chandraprabha as on June 2024.pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Chandraprabha as on June 2024.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on 30-06-2024.pdf18 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: 2432899_FurtherCC_signed (1).pdf26 Jun 2024
Disclosure of sold/ booked inventoryFile: Circular 29 - Chandraprabha as on Mar-24.pdf20 Jun 2024
Proforma of Agreement for saleFile: CHANDRAPRABHA SALE AGREEMENT DRAFT AU(1).pdf24 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Chandraprabha as on March 2024.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Chandraprabha as on March 2024.pdf15 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on 31-03-2024.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: RERA_Chandraprabha.pdf1 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Chandraprabha as on Dec 2023.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Chandraprabha as on Dec 2023.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Final Chandraprabha as on 31-12-2023.pdf17 Jan 2024
Layout approvalFile: ilovepdf_merged (1).pdf6 Jan 2024
Layout approvalFile: ilovepdf_merged (2).pdf6 Jan 2024
Building plan approvalFile: 12108 CP Amended Approval Letter.pdf6 Jan 2024
Copy of Layout Approval (in case of layout)File: ilovepdf_merged (1).pdf6 Jan 2024
Copy of Layout Approval (in case of layout)File: ilovepdf_merged (2).pdf6 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 12108 CP Amended Approval Letter.pdf6 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: 2404800_FurtherCC_signed.pdf6 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Chandraprabha as on March 2023.pdf14 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Chandraprabha as on Sept 2023.pdf14 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Chandraprabha as on March 2023.pdf14 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Chandraprabha as on June 2023.pdf14 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Chandraprabha as on Sept 2023.pdf14 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on March 2023.pdf14 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on June 2023.pdf14 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on Sept 2023.pdf14 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A.pdf5 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 CP.pdf24 Nov 2023
Details of encumbrances concerned to FinanceFile: Chandraprabha- Encumbrance Letter (Finance).pdf23 Nov 2023
Details of encumbrances concerned to LegalFile: Chandraprabha- Encumbrance Letter (Finance).pdf23 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Chandraprabha as on 27-10-2023.pdf28 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Chandraprabha as on Sept 2023.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Chandraprabha as on 30-09-2023.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Chandraprabha as on 22-23.pdf24 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Chandraprabha.pdf11 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Chandraprabha as on June 2023.pdf21 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Chandraprabha as on 30-06-2023.pdf21 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Certificate (2).pdf16 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Chandraprabha as on March 2023.pdf25 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Chandraprabha as on 31-03-2023.pdf25 Apr 2023
Copy of the legal title reportFile: Short Title_18012023_11zon (1).pdf18 Jan 2023
Proforma of Agreement for saleFile: Final AFS Manisha 180123.pdf18 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged (1).pdf11 Jan 2023
Proforma of Allotment letterFile: Final Allotment Letter_Manisha Supreme_Chandraprabha_06012023.pdf11 Jan 2023
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment Letter CP.pdf11 Jan 2023
Declaration about Commencement CertificateFile: Format D -Manisha.pdf6 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200256879991_For_Asset_Based_Search_06_01_2023_10_52_13_499.pdf6 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ilovepdf_merged (3).pdf6 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement CP_compressed.pdf6 Jan 2023
Layout approvalFile: PLAN MANISHA_1-1_compressed.pdf5 Jan 2023
Building plan approvalFile: PLAN MANISHA_2-end.pdf5 Jan 2023
Details of encumbrances concerned to FinanceFile: Encumbrance letter Finance CP.pdf5 Jan 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Letter Legal CP.pdf5 Jan 2023

How this compares with Mumbai Suburban

27%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Chandraprabha on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund West, Mumbai6,700+ in Mumbai Suburban

2 kmChandraprabhaCompleted 116Lapsed / revoked 94Other 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 351 registered projects within 2 km.

Builder: Manisha Supreme Realty LLP

Manisha Supreme Realty LLP has 1 registration on MahaRERA, including Chandraprabha. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Chandraprabha is delayed beyond 31 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Chandraprabha?

The registered promoter entity is Manisha Supreme Realty LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Chandraprabha?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Chandraprabha?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Chandraprabha?

The professionals named in the filing: Architect: NASA Architectural Consultants Pvt. Ltd.; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Chandraprabha?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Chandraprabha. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Chandraprabha to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.