Completed No litigation declared Residential / Group Housing project

CHAFA

By Mahalaxmi Realty and Infrastructures

RG-MH-33446 · RERA P50500017931 · Last updated on MahaRERA portal: 14 Jun 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Mar 2024Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

CHAFA is a Residential / Group Housing project by Mahalaxmi Realty and Infrastructures in Nagpur, Maharashtra, registered with MahaRERA as P50500017931 on 27 Sep 2018. The registration is recorded completed; possession was promised by 31 Mar 2024. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameCHAFA
  • TypeResidential / Group Housing
  • Location
    • GOKUL JORAS CO-OP HOUSING SOCIETY
    • BORGAON
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440013
  • Pincode440013
  • RERA no.P50500017931
  • ReraGenie IDRG-MH-33446

Builder

  • NameMahalaxmi Realty and Infrastructures
  • Entity typePartnership
  • PartnerRAJESH SUKHDEORAO DEHANKAR
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects3 →

Key dates

this monthRegisteredSep 2018First promiseMar 2022Revised toMar 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Sep 2018
  • Promised completion31 Mar 2024
  • Revised completionRevised to 31 Mar 2024 (originally 30 Mar 2022)
  • Buildings1 building record
  • Documents filed96 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CHAFANA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

CHAFA: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 14 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
EXTERNAL METER ROOMYes30%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered1
Open Space4

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area712 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI925.0
Proposed, not sanctioned712 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPPOSITE AGRESEN CHATTRALAYA AMRAVATI ROAD NAGPUR

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRahul Junghare
EngineerArun Uttarwar
PartnerRole in project
Mahalaxmi Realty and Infrastructures-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500010901Mar 2022 → Dec 2022

Reason as filed by the promoterProject Extension is required due to delay in the construction activities due to the lockdowns during the Covid-19 Pandemic. As a result of the restriction due by the government on construction activities and unavailability of labour and material the project got delayed.

EXT50500017712Mar 2022 → Mar 2024

Reason as filed by the promoterThe main cause of delay for completion of the project within stipulated time period was the severe financial crunch faced post Covid. The real estate market specially in the kind of areas in which this project is, are hit very badly, we did not get the bookings of flats in the project, and have to arrange the major portion of the funds required to complete the project on our own. It could easily be assessed from the disclosure of sold/booked inventory submitted herewith. We have registered the project with MahaRERA on 27/09/2018,and although the construction work was in progress in full swing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Sep 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Sep 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jun 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Jun 2024

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: chafa completion certificate_compressed.pdf14 Jun 2024
Architect’s Certificate on Completion of Project (Form 4)File: architect completion chafa_compressed.pdf14 Jun 2024
Declaration in FORM BFile: format B consent.pdf10 Feb 2024
Declaration in FORM BFile: format B consent_NOTARY.pdf10 Feb 2024
Certificates of CA (Form 3)File: mahalaxmi form 3 march .pdf10 Feb 2024
Certificates of CA (Form 3)File: FORM 3 JUNE .pdf10 Feb 2024
Certificates of CA (Form 3)File: FORM 3 SEPT.pdf10 Feb 2024
Certificates of CA (Form 3)File: FORM 3 DEC .pdf10 Feb 2024
Disclosure of sold/ booked inventoryFile: disclosure of sold unsold.pdf8 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects chafa march_compressed.pdf9 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect chafa june_compressed.pdf9 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect sept chafa_compressed.pdf9 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 march chafa_compressed.pdf9 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 june chafa_compressed.pdf9 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 sept chafa_compressed.pdf9 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2a sept chafa_compressed.pdf9 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a march chafa_compressed.pdf9 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a june chafa_compressed.pdf9 Oct 2023
Certificates of CA (Form 3)File: NEW UPDATED JUNE 2021.pdf15 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 30-6-21.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 30-09-21.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 31-12-21.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 31-03-22.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 30-6-22.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 30-9-22.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 31-12-22.pdf13 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A MARCH 21-22.pdf13 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22 .pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 30-6-21.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 30-9-21.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 31-12-21.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 31-3-22.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 30-6-22.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 30-9-22.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 31-12-22.pdf9 Feb 2023
Certificates of CA (Form 3)File: 1 30-6-21.pdf9 Feb 2023
Certificates of CA (Form 3)File: 2 30-9-21.pdf9 Feb 2023
Certificates of CA (Form 3)File: 3 31-12-21.pdf9 Feb 2023
Certificates of CA (Form 3)File: 4 31-03-22.pdf9 Feb 2023
Certificates of CA (Form 3)File: 5 30-6-22.pdf9 Feb 2023
Certificates of CA (Form 3)File: 6 30-9-22.pdf9 Feb 2023
Certificates of CA (Form 3)File: 7 31-12-22.pdf9 Feb 2023
Declaration about Commencement CertificateFile: dcc.pdf18 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: MAHALAXMI 2018-19.pdf28 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 mahalaxmi 2019-20.pdf28 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 mahalaxmi 2020-21.pdf28 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QCJUNE2019.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QCSEPT2019.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QCDEC2019.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QCMARCH2020.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QCJUNE2020.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QCSEPT2020.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QCDEC2020.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QCMARCH2021.pdf27 Sep 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD BOOKING (2).pdf27 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE.pdf21 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERTIFICATE FIN.pdf21 Sep 2021
Certificates of CA (Form 3)File: CA CERTIFICATE FINAL.pdf21 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE-FORM 1-FOR ONGOING PROJECT 2.pdf17 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE (1).pdf17 Aug 2021
Certificates of CA (Form 3)File: CA CERTIFICATE june 21 ramahalaxmi.pdf17 Aug 2021
Building plan approvalFile: 1.pdf12 Jun 2020
Building plan approvalFile: 2.pdf12 Jun 2020
Building plan approvalFile: 3.pdf12 Jun 2020
Building plan approvalFile: 4.pdf12 Jun 2020
Building Plan Approval (IOD)File: 1.pdf12 Jun 2020
Building Plan Approval (IOD)File: 2.pdf12 Jun 2020
Building Plan Approval (IOD)File: 3.pdf12 Jun 2020
Building Plan Approval (IOD)File: 4.pdf12 Jun 2020
Commencement Certificates / NA Order for plotted developmentFile: 20200612_124335_compressed.pdf12 Jun 2020
Commencement Certificates / NA Order for plotted developmentFile: 20200612_123619_compressed.pdf12 Jun 2020
Annual Audit Report of Statutory CA (Form 5)File: FORM 5.pdf30 Sep 2019
Building plan approvalFile: PDF.pdf25 Sep 2018
Layout approvalFile: RL PDF-min.pdf25 Sep 2018
Layout approvalFile: LAYOUT PDF-min.pdf25 Sep 2018
Copy of Layout Approval (in case of layout)File: RL PDF-min.pdf25 Sep 2018
Copy of Layout Approval (in case of layout)File: LAYOUT PDF-min.pdf25 Sep 2018
Building Plan Approval (IOD)File: PDF.pdf25 Sep 2018
Declaration in FORM BFile: dec 1.pdf6 Sep 2018
Declaration in FORM BFile: dec2.pdf6 Sep 2018

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VISHVA138 NELCO SOCIETY SUBHASH NAGAR ROAD NAGPUR8CompletedJan 2017Late, Mar 2017
GOKUL PARK LITEPLOT NO. 18 GOKUL JORAS HOUSING SOCIETY BOREGAON NAGPUR6CompletedMar 2015Mar 2014
GOKUL PARK DELIGHTPlot No. 19 Gokul Joras Housing Society Boregaon Nagpur12CompletedOct 2014Oct 2014

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 24 months
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CHAFA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORGAON2,800+ in Nagpur

Builder: Mahalaxmi Realty and Infrastructures

Mahalaxmi Realty and Infrastructures has 2 registrations on MahaRERA, including CHAFA and GURUKRUPA APARTMENTS. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if CHAFA is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CHAFA?

The registered promoter entity is Mahalaxmi Realty and Infrastructures, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CHAFA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CHAFA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CHAFA?

The professionals named in the filing: Architect: Rahul Junghare; Engineer: Arun Uttarwar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CHAFA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CHAFA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CHAFA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.