Home / Browse projects / Mumbai City, Maharashtra / CCIL Bhavan

Registered Litigation declared Commercial project

CCIL Bhavan

By SURAJ ESTATE DEVELOPERS LTD

RG-MH-63185 · RERA P51900021953 · Last updated on MahaRERA portal: 4 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 5 cases
  • Completion date moved by 32 months
  • 2 extensions taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Aug 2027Possession promisedmoved 32 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
0 of 3Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

CCIL Bhavan is a Commercial project by SURAJ ESTATE DEVELOPERS LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900021953 on 25 Aug 2019. Possession is promised by 31 Aug 2027. The completion date has moved by 32 months from the original filing. 3 of the 3 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameCCIL Bhavan
  • TypeCommercial
  • Location
    • College Lane
    • Agar Bazar
    • GNorth-400028
    • Ward GNorth
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900021953
  • ReraGenie IDRG-MH-63185

Builder

  • NameSURAJ ESTATE DEVELOPERS LTD
  • Entity typeCompany
  • CINU99999MH1986PTC040873
  • GSTIN27AAACS8375H1Z0
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorTHOMAS RAJAN
  • Other registrations14 more →
  • Completed4 of 15
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2019First promiseDec 2024Revised toAug 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Aug 2019
  • Promised completion31 Aug 2027
  • Revised completionRevised to 31 Aug 2027 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed101 files

Current status

100%3 of 3 units booked
88.1%Work done, per cost certificate

Figures as on 4 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CCIL BHAVANNA33033

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

CCIL BHAVAN: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered17

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,325 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 May 2026

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3784.62
Proposed, not sanctioned1,285 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOWER PAREL
Estimated costRs 12.00 cr
Cost incurredRs 10.57 cr
Work done88.09%
BuildingWingEstimatedIncurred
-NARs 12.00 crRs 10.57 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPriyanka Rahate
EngineerSarthak Tekade
EngineerRohan Thanedar
Chartered AccountantNaveen Tripathi
Chartered AccountantV S C & Associates
Chartered AccountantVSC ASSOCIATES
Chartered AccountantAbhishek Bajaj
PartnerRole in project
SURAJ ESTATE DEVELOPERS LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900025840Dec 2024 → Jun 2026

Reason as filed by the promoterWe have registered our project known as "CCIL Bhavan" under registration No. P51900021953. The completion date as per the certificate is 30th December, 2024. This project envisages the addition of 3 floors over an existing commercial building of Ground + 6 floors. We have earlier obtained the occupation certificate for the existing building up to 6th floor on 13th February, 2012 ( O.C copy attached in other technical tab). We have received the commencement certificate from BMC on 2nd May, 2024 and same is revalidated up to 07.12.2025 (Revalidation letter attached in CC Tab) and the actual cons

EA28072621896Dec 2024 → Aug 2027

Reason as filed by the promoterSub.: Redevelopment of property known as "CCIL Bhavan" on property bearing F.P. 822, TPS IV of Mahim Division, situate at S.K.Bole Road, Dadar (West), Mumbai - 400 028. We have registered our project known as "CCIL Bhavan" under registration No.P51900021953. The completion date as per the certificate is 4th June,2026. This project envisages the addition of 3 floors over an existing commercial building of Ground + 6 floors. We have received the Commencement Certificate from BMC on 2nd May, 2024 and the construction work could only commence after the cessation of the monsoon season i.e. in the m

Litigation declared5

CaseCourtStatus
1652/2015Bombay City Civil CourtClosed
1653/2015Bombay City Civil CourtClosed
1654/2015Bombay City Civil CourtClosed
1870/2008Small Causes Court at BombayClosed
52/2021Bombay City Civil CourtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Aug 2027

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: FORM 5.pdf4 Aug 2026
Form 5 (FY 2024-2025)File: FORM 5.pdf4 Aug 2026
Form 5 (FY 2023-2024)File: Form 5 CCIL Bhavan March 2023.pdf4 Aug 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 (1) CCIL Bhavan.pdf24 Jul 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE -CCIL - June 26.pdf24 Jul 2026
Withdrawal Update Form 3File: RERA Form 3_CCIL Bhavan_24072026.pdf24 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A 2025.pdf24 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A 2024.pdf24 Jul 2026
Form 2A (FY 2023-2024)File: Form 2A 2024.pdf24 Jul 2026
Withdrawal Update Form 1File: CCIL_822.pdf22 May 2026
Withdrawal Update Form 2File: FORM 2 March 26.pdf22 May 2026
Withdrawal Update Form 3File: CCIL Singed Copy Mar 2026 SIGNED FORM 3.pdf22 May 2026
Form 1File: June 25 Form 1.pdf21 May 2026
Form 2File: FORM 2.pdf21 May 2026
Form 3File: CCIL Singed Copy June2025 signed FORM 3.pdf21 May 2026
Disclosure of Sold and Booked InventoryFile: CCIL June 2025 SOLD UNSOLD.pdf21 May 2026
Form 1File: Architects Certificate sept 2025.pdf21 May 2026
Form 2File: FORM 2.pdf21 May 2026
Form 3File: CCIL Singed Copy Sep 2025 SIGNED FORM 3.pdf21 May 2026
Disclosure of Sold and Booked InventoryFile: CCIL Sep 2025 SOLD UNSOLD.pdf21 May 2026
Form 1File: Architects Certificate December 25.pdf21 May 2026
Form 2File: FORM 2.pdf21 May 2026
Form 3File: CCIL Singed Copy Dec 2025 SIGNED FORM 3.pdf21 May 2026
Disclosure of Sold and Booked InventoryFile: CCIL Dec 2025 SOLD UNSOLD.pdf21 May 2026
Form 1File: Architects Certificate March 26.pdf21 May 2026
Form 2File: FORM 2 March 26.pdf21 May 2026
Form 3File: CCIL Singed Copy Mar 2026 SIGNED FORM 3.pdf21 May 2026
Disclosure of Sold and Booked InventoryFile: CCIL March 2026 SOLD UNSOLD.pdf21 May 2026
Declaration in FORM BFile: FORM B DECLARATION.pdf11 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Declaration.pdf11 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certficate -1 oct 24 to 31 dec 24.pdf11 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate 1 jan 25 to 31 jan 25.pdf11 Jun 2025
Certificates of CA (Form 3)File: FORM 3 December 2024.pdf11 Jun 2025
Certificates of CA (Form 3)File: Form-3 Jan to March 2025.pdf11 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Declaration.pdf11 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate up to DEC 2024.pdf11 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM NO Jan to March 2025.pdf11 Jun 2025
Declaration about Commencement CertificateFile: Format -D.pdf11 Jun 2025
Other - TechnicalFile: Table - A-CPM-PERT -Balance completion work.pdf11 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Declaration.pdf11 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Declaration.pdf11 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: CA Form 5 FY 2024-25.pdf11 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: FORM 5 (2).pdf11 Jun 2025
Commencement Certificates / NA Order for plotted developmentFile: CCIL - CC Revalidation Letter.pdf6 Jun 2025
Other - TechnicalFile: OC LETTER.pdf6 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: REGULATION 39.pdf6 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Certificate - Form 5 CCIL FY 24-25 sg.pdf2 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf30 May 2025
Certificates of CA (Form 3)File: FORM 3.pdf30 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf30 May 2025
Commencement Certificates / NA Order for plotted developmentFile: 822 - Sale FCC - 02052024.pdf30 May 2025
Disclosure of sold/ booked inventoryFile: sold.pdf30 May 2025
Declaration about Commencement CertificateFile: Declaration cc.pdf30 May 2025
Other - TechnicalFile: Pert-Chart.pdf30 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: CCIL BHAVAN -FORM -2A.pdf30 May 2025
Certificates of CA (Form 3)File: Form 3 CCIL March 2025_compressed.pdf5 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - CCIL FP822 - March 2025.pdf5 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 822_CCIL_AR.pdf11 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CCIL BHAVAN -Form 2A.pdf8 Apr 2025
Building plan approvalFile: Letter.pdf25 Mar 2025
Building plan approvalFile: Sheet 1.pdf25 Mar 2025
Building plan approvalFile: Sheet 4.pdf25 Mar 2025
Building plan approvalFile: Sheet 5.pdf25 Mar 2025
Building plan approvalFile: Sheet 6.pdf25 Mar 2025
Building plan approvalFile: Sheet 3_compressed.pdf25 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Sheet 2.pdf25 Mar 2025
Building Plan Approval (IOD)File: Letter.pdf25 Mar 2025
Building Plan Approval (IOD)File: Sheet 1.pdf25 Mar 2025
Building Plan Approval (IOD)File: Sheet 4.pdf25 Mar 2025
Building Plan Approval (IOD)File: Sheet 5.pdf25 Mar 2025
Building Plan Approval (IOD)File: Sheet 6.pdf25 Mar 2025
Building Plan Approval (IOD)File: Sheet 3_compressed.pdf25 Mar 2025
Declaration in FORM BFile: AFFIDAVIT-CUM-DECLARATION FOR CCIL BHAVAN.pdf27 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CCIL_822.pdf17 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 822_CCL.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - CCIL FP822 - September 23.pdf3 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 CCIL Bhavan March 2023.pdf28 Sep 2023
Certificates of CA (Form 3)File: Final_Form 3 CCIL Bhavan Dec 2022_compressed (1).pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CCIL.pdf17 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE - FP 822 - CCIL.pdf17 Nov 2022

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
PALETTEP51900008207DADAR-WEST, Mumbai City152Aug 2017OngoingDec 2025Registered original: Jun 2023Not delivered
HALLMARKCS 104 BHIMWADI WADALA EAST MUMBAI7-CompletedJul 2016Late, Nov 2016
ETERNITY APARTMENTFP 469 MMC CROSS ROAD MAHIM WEST MUMBAI 40001616-CompletedAug 2011Aug 2011
PARK SIDEFP 888 DATTA RAUL ROAD DADAR WEST MUMBAI 40002828-CompletedJul 2010Late, Feb 2011

How this compares with Mumbai City

100%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 32 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CCIL Bhavan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Agar Bazar780+ in Mumbai City

2 kmCCIL BhavanCompleted 57Lapsed / revoked 54Other 92Dot size: filed unitsN

Filed coordinates, straight-line distance. 203 registered projects within 2 km.

Builder: SURAJ ESTATE DEVELOPERS LTD

SURAJ ESTATE DEVELOPERS LTD has 15 registrations on MahaRERA, including ST ANTHONY APARTMENT and TRANQUIL BAY. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if CCIL Bhavan is delayed beyond 31 Aug 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CCIL Bhavan?

The registered promoter entity is SURAJ ESTATE DEVELOPERS LTD, a company as per the filing. Its CIN U99999MH1986PTC040873 and GSTIN 27AAACS8375H1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CCIL Bhavan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CCIL Bhavan?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CCIL Bhavan?

The professionals named in the filing: Architect: Priyanka Rahate; Engineer: Sarthak Tekade; Engineer: Rohan Thanedar; Chartered Accountant: Naveen Tripathi; Chartered Accountant: V S C & Associates; Chartered Accountant: VSC ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CCIL Bhavan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CCIL Bhavan. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CCIL Bhavan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.