Home / Browse projects / Dakshina Kannada, Karnataka / Castle Green

Registration approved No litigation declared Residential/Group Housing project

Castle Green

By Nidhi Land Infrastructure Developers India (P) Ltd , Karunakara Shetty & K Vimal Kumar

RG-KA-70988 · RERA PRM/KA/RERA/1257/334/PR/200626/008733 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0 of 19Construction stages donefurthest along: Earth work and other leveling..., 80%
4 of 14Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 94 documents Report an error

Castle Green is a Residential/Group Housing project by Nidhi Land Infrastructure Developers India (P) Ltd , Karunakara Shetty & K Vimal Kumar in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/200626/008733 on 20 Jun 2026. Possession is promised by 31 Dec 2029. 10 of the 14 units on this registration are recorded sold or booked, and 0 of 19 construction stages are filed complete.

At a glance

Project

  • NameCastle Green
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575004
  • Pincode575004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/200626/008733
  • ReraGenie IDRG-KA-70988

Builder

  • NameNidhi Land Infrastructure Developers India (P) Ltd , Karunakara Shetty & K Vimal Kumar
  • Entity typeOther ( Land Owners )
  • GSTIN29AADCN8891L1ZK
  • Authorized SignatoryPrashanth K. Sanil
  • Declared earlier projects6 →

Key dates

this monthRegisteredJun 2026PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jun 2026
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed94 files

Current status

71%10 of 14 units booked
9.7%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Castle Green---14014

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 19 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 80%.

Building: 13% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work80%
Foundation footing work65%
Upto Plinth Level45%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)35%
Retaining wall (All types)22%
RCC or MS Framed structure8%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area887 sq m
Named landowners9
LandownerVillageDistrict
Nidhi Land Infrastructure Developers India (P) Ltd.,--
Karunakara Shetty--
Kuruankanndy Vimal Kumar--
Nidhi Land Infrastructure Developers India (P) Ltd.,--
Karunakara Shetty--
Kuruankanndy Vimal Kumar--
Nidhi Land Infrastructure Developers India (P) Ltd.,--
Karunakara Shetty--
Kuruankanndy Vimal Kumar--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.00 cr
Cost incurredRs 48.62 lakh
Spent of the estimate9.73%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 5.00 crRs 48.62 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDharmaraj
EngineerDharmaraj
Chartered AccountantShantharama Shetty

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed94

As listed on the registration, under the names the promoter filed them with; the newest 80 of 94 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/200626/008733 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, CA Certificate_Q2-2026-27.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Castle Green- Architects Certificate - Q2-2026-27.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Castle Green- Engineers Certificate _Q2-2026-27.pdf14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 CGN.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect - Castle Green.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENG - Castle Green.pdf15 Jul 2026
G.P.A. - KARUNAKARA SHETTYFile: GPA- Karunakara Shetty- CGN.pdf11 Jun 2026
G.P.A. - KURUANKANNDY VIMAL KUMARFile: GPA-Kurankanndy Vimal Kumar- CGN.pdf11 Jun 2026
FLAT WISE BREAK-UPFile: Unit Break-Up_Castle Green.pdf11 Jun 2026
AFS - AS SUGGESTED, RELATED CLAUSES HAVE BEEN UPDATED IN THE DRAFT OF AFS.File: Agreement For Sale_Draft_Revised_CastleGreen_RERA_R2_11062026.pdf11 Jun 2026
THIS PROJECT IS DEVELOPED BY THE LAND OWNERS THEMSELVES; HENCE THE AFFIDAVIT IS UPLOADED.File: CGN- Affidavit Cum Declaration.pdf6 Jun 2026
FLAT BREAK-UP DIMENSION DETAILS - UPDATEDFile: Flat BreakUp_Dimensions_Castle Green.pdf6 Jun 2026
WATER NOC APPLICATION UPLOADED, UPON RECEIPT OF WATER NOC, WILL UPLOAD AT THE TIME OF QTRLY FILINGFile: Water Noc_Letter Acknowledgement.pdf6 Jun 2026
LAND COST - CLARIFICATIONS - SALE DEED COPY UPDATEDFile: Sale Deed_Castle Green.pdf6 Jun 2026
QUERIES-3 - CLARIFICATIONSFile: Queries-3_Castle Green_Clarification.pdf6 Jun 2026
DIMENSION WISE UNIT DETAILSFile: Dimension Wise Unit Details_Castle Green.pdf9 May 2026
SIGNED PROJECT SPECIFICATIONSFile: Project Specifications_Castle Green.pdf9 May 2026
WATER NOC APPLICATION UPLOADED, UPON RECEIPT OF WATER NOC, WILL UPLOAD AT THE TIME OF QTRLY FILINGFile: Water Noc_Letter Acknowledgement.pdf9 May 2026
LAND COST_ACTUAL VALUE & GUIDANCE VALUE_CLARIFICATIONSFile: Land Cost & Guidance Value_Clarifications_Castle Green.pdf9 May 2026
AS SUGGESTED, RELATED CLAUSES HAVE BEEN INCORPOORATED IN THE DRAFT OF AFSFile: Agreement for Sale_Revised Draft_Sky Garden_RERA_R1.pdf9 May 2026
DETAILS AND THE CLARIFICATIONS ON THE QUERIES RAISED BY RERAFile: Queries_2_RERA_Castle Green_06052026_R1.pdf9 May 2026
RTCFile: RTC_Castle Green.pdf13 Apr 2026
CONNECTED MRFile: Connected MR_Castle Green.pdf13 Apr 2026
EC FROM 01-04-2010 TO 06-04-2026File: EC_01042010_06042026.pdf13 Apr 2026
SINGLE SITE LAYOUT PLAN APROVAL ORDERFile: CGN_Single Site.pdf13 Apr 2026
SINGLE SITE LAYOUT APPROVED PLANFile: CGN_Single Site.pdf13 Apr 2026
BUILDING LICENCEFile: Building Licence_Castle Green.pdf13 Apr 2026
ADLR CERTIFIED SURVEY SKETCHFile: Revenue or Survey Sketch.pdf13 Apr 2026
LOCATION DETAILS OF THE PROJECTFile: Location details including Latitude & Longitude_Castle Green.pdf13 Apr 2026
APPROVED SANCTIONED DRAWINGSFile: Approved Plans_All Floors_Castle Green.pdf13 Apr 2026
COMMENCEMENT CERTIFICATEFile: Building Licence_Castle Green.pdf13 Apr 2026
APPROVED MASTER PLANFile: Master Plan.pdf13 Apr 2026
VILLAGE MAPFile: Castle Green- Village Map.pdf13 Apr 2026
APPROVAL_NOC UNDER SECTION 14 OF THE KTCP ACTFile: Building Licence_Castle Green.pdf13 Apr 2026
DETAILS OF THE FACILITIES PROVIDED IN THE PROJECTFile: Details of Amenities_Castle Green.pdf13 Apr 2026
PROJECT AMENITIES_SPECIFICATIONS OF THE PROJECTFile: Project Specifications_Castle Green.pdf13 Apr 2026
REVISED AFS DRAFTFile: Agreement For Sale_Draft_Revised_CastleGreen_RERA_R1.pdf13 Apr 2026
MESCOM & WATER NOCFile: Mescom & Water Noc.pdf13 Apr 2026
PROJECT ESTIMATIONFile: Project Estimation_Castle Green.pdf13 Apr 2026
LAND COST GUIDANCE VALUEFile: Certified Land Cost Details_Castle Green_DA.pdf13 Apr 2026
STRUCTURAL STABILITY CERTIFICATEFile: Stability Certificate Merged- Castle Green.pdf13 Apr 2026
CLARIFICATIONS ON THE QUERIES - CASTLE GREENFile: Queries_RERA_Castle Green_02042026_R3_CLARIFICATIONS.pdf13 Apr 2026
RTC, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Mutation, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Encumbrance Certificate, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Conversion/Alienation Order, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Sale/Title/Gift Deed, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Khatha, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
RTC, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Mutation, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Encumbrance Certificate, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Conversion/Alienation Order, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Sale/Title/Gift Deed, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Khatha, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
RTC, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Mutation, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Encumbrance Certificate, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Conversion/Alienation Order, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Sale/Title/Gift Deed, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Khatha, survey 10-2B1 (As per Conversion Order 10-2B1AP)-
Registration CertificateFile: Incorparation certificate.pdf-
GST CertificateFile: Amended gst certifiate.pdf-
Certificate issued by CA Form 1File: C A Certificate Form -1 .pdf-
Certificate issued by Architect Form 2File: Castle Green Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Castle Green Engineers Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: CGN_Non Dispute.pdf-
Balance Sheet 2024 - 2025File: P&L And Balance Sheet.pdf-
Balance Sheet 2023 - 2024File: Balance Sheet & Profit and Loss With Shedule_compressed.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet 2022-23.pdf-
Audited Profit and Loss Statement 2024 - 2025File: P&L And Balance Sheet.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Balance Sheet & Profit and Loss With Shedule_compressed.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Proft and Loss statement -2022-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Tax Return Acknowledgment.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Tax return Acknowledge.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Tax return Acknowledgment 2022-23 .pdf-
Building Licence_Castle Green-
Approved Plans_All Floors_Castle Green-

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 under way, not due yet2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Shakthi HeightsNear Gopal Krishna Temple Road, Shakthi Nagar, MangaloreOngoingJun 2031Not due yet
White RoseWhite Rose, Near Cordel Church Hall, Kulshekar, MangaloreOngoingOct 2030Not due yet
PoorvajPoorvaj, Shivabagh, Kadri, MangaloreOngoingNov 2029Not due yet
Smrithi HeightsSmrithi Heights, Nanthoor - Pumpwell Road, MangaloreOngoingJun 2029Not due yet
Sudham ResidencesSudham Residences, Abbakka Nagar, Kottara Chowki, MangaloreCompleted-No date filed
Sankalp ResidencesSankalp Residences, J.B. Lobo Road, Kottara Chowki, MangaloreCompleted-No date filed

How this compares with Dakshina Kannada

71%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep Castle Green on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmCastle GreenOther 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 122 registered projects within 2 km.

Builder: Nidhi Land Infrastructure Developers India (P) Ltd , Karunakara Shetty & K Vimal Kumar

Nidhi Land Infrastructure Developers India (P) Ltd , Karunakara Shetty & K Vimal Kumar has 1 registration on RERA Karnataka, including Castle Green. Its filings declare 6 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if Castle Green is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Castle Green?

The registered promoter entity is Nidhi Land Infrastructure Developers India (P) Ltd , Karunakara Shetty & K Vimal Kumar, an other ( land owners ) as per the filing. Its GSTIN 29AADCN8891L1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Castle Green?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Castle Green?

The professionals named in the filing: Architect: Dharmaraj; Engineer: Dharmaraj; Chartered Accountant: Shantharama Shetty. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Castle Green?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Castle Green. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Castle Green to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.