ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / PALACE GARDENS BLOCK C

Registration approved No litigation declared Residential/Group Housing project

PALACE GARDENS BLOCK C

By M/S MAC & VK ASSOCIATES

RG-KA-28910 · RERA PRM/KA/RERA/1257/334/PR/211223/006507 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
6 of 14Construction stages donefurthest along: Plastering inside, 95%
22 of 40Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 122 documents Report an error

PALACE GARDENS BLOCK C is a Residential/Group Housing project by M/S MAC & VK ASSOCIATES in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/211223/006507 on 21 Dec 2023. Possession is promised by 31 Dec 2028. 18 of the 40 units on this registration are recorded sold or booked, and 6 of 14 construction stages are filed complete.

At a glance

Project

  • NamePALACE GARDENS BLOCK C
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575004
  • Pincode575004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/211223/006507
  • ReraGenie IDRG-KA-28910

Builder

  • NameM/S MAC & VK ASSOCIATES
  • Entity typePartnership Firm
  • GSTIN29ABAFM7319R1ZJ
  • Authorized SignatoryROGER MACQUEEN PINTO

Key dates

this monthRegisteredDec 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Dec 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed122 files

Current status

45%18 of 40 units booked
52.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PALACE GARDENS BLOCK C---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 14 construction stages are filed complete. The stage furthest along is Plastering inside, at 95%.

Building: 85% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling95%
Joinery: Doors, Windows, Ventilators etc45%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)85%
Railing and Grill fixing85%
Electrification, Water supply and Sanitary Finishing65%
Painting55%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work80%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes70%
LiftsYes0%
Corridor/LobbiesYes70%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes90%
Outer WallNoNot applicable
Open parking areasYes0%
Provision for lodging of management staff and security staffYes50%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,778 sq m
Named landowners2
LandownerVillageDistrict
POORNIMA H & OTHER--
POORNIMA H & OTHERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 10.86 cr
Cost incurredRs 5.65 cr
Spent of the estimate52.03%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 10.86 crRs 5.65 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHALINI SURESH
EngineerSANTHOSH KUMAR SHETTY
Chartered AccountantSHANTHARAM SHETTY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed122

As listed on the registration, under the names the promoter filed them with; the newest 80 of 122 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/211223/006507 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Palace Gardens Q1 26-27 (1).pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate (1).pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Palace Gardens Q1 26-27-SIGNED (2).pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: SS Engineers Architects certificate Form 5.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: engineers certificate Form 6.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Palace Gardens Q4 25-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architects Certificate.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineers Certificate.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Palace Gardens Q3 25-26.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architects certificate.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineers certificate.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Occupancy certificateFile: OC-palace garden.pdf14 Dec 2023
architect certificateFile: ARCHITECT CERTIFICATE FORM 2.pdf9 Dec 2023
FAR COPYFile: FAR.pdf9 Dec 2023
certified Carpet area calculationFile: Carpet area statement Palace Gardens block C .pdf9 Dec 2023
CDP mapFile: CDP PLAN.pdf9 Dec 2023
DANAPATRAFile: Dana pathra.pdf9 Dec 2023
CLARIFICATION ON Relinquishment deedFile: clarification dana patra mac & vk.pdf9 Dec 2023
CLARIFICATIONFile: clarification.pdf9 Dec 2023
ARCHITECT COA CERTIFICATEFile: registration certificate.jpeg9 Dec 2023
licence challanFile: licence payment challan.pdf9 Dec 2023
RTC, survey 24/3A-
Mutation, survey 24/3A-
Encumbrance Certificate, survey 24/3A-
Conversion/Alienation Order, survey 24/3A-
JDA, survey 24/3A-
Khatha, survey 24/3A-
RTC, survey 24/3A-
Mutation, survey 24/3A-
Encumbrance Certificate, survey 24/3A-
Conversion/Alienation Order, survey 24/3A-
JDA, survey 24/3A-
Khatha, survey 24/3A-
Registration CertificateFile: firm registartion certiifcate.jpg-
Partnership DeedFile: partnership deed_compressed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: form 1 ca report.PDF-
Certificate issued by Architect Form 2File: ARCHITECT CERTIFICATE FORM 2.pdf-
Certificate issued by Engineer Form 3File: Engineer cirtificate (1).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Litigation affidavit .pdf-
Certificate from Chartered AccountFile: form 1 ca report.PDF-
Balance Sheet 2022 - 2023File: BS AY 2023-24.pdf-
Balance Sheet 2021 - 2022File: BS AY 2022-23.pdf-
Balance Sheet 2020 - 2021File: BS AY 2021-22.pdf-
Audited Profit and Loss Statement 2022 - 2023File: PL AY 2023-24.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL AY 2022-23.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL AY 2021-22.pdf-
Director's Report 2021 - 2022File: Schedule to PL AY 2022-23.pdf-
Director's Report 2020 - 2021File: Schedule to PL AY 2021-22.pdf-
Cash Flow Statement 2022 - 2023File: IS AY 2023-24.pdf-
Cash Flow Statement 2021 - 2022File: IS AY 2022-23.pdf-
Auditor's Report 2022 - 2023File: AR AY 2023-24.pdf-
Auditor's Report 2021 - 2022File: AR AY 2022-23.pdf-
Auditor's Report 2020 - 2021File: AR AY 2021-22.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR AY 2023-24.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR AY 2022-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2021-22.pdf-
building licence-
sanction plan-
single layout-
sanction plan-
sanction plan-
sanction plan-
specifications Palace Gardens block c -
single layout-
single layout-
stability certificate-

How this compares with Dakshina Kannada

45%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep PALACE GARDENS BLOCK C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmPALACE GARDENS BLOCK COther 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: M/S MAC & VK ASSOCIATES

M/S MAC & VK ASSOCIATES has 1 registration on RERA Karnataka, including PALACE GARDENS BLOCK C. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if PALACE GARDENS BLOCK C is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of PALACE GARDENS BLOCK C?

The registered promoter entity is M/S MAC & VK ASSOCIATES, a partnership firm as per the filing. Its GSTIN 29ABAFM7319R1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in PALACE GARDENS BLOCK C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PALACE GARDENS BLOCK C?

The professionals named in the filing: Architect: SHALINI SURESH; Engineer: SANTHOSH KUMAR SHETTY; Chartered Accountant: SHANTHARAM SHETTY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PALACE GARDENS BLOCK C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PALACE GARDENS BLOCK C. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PALACE GARDENS BLOCK C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.