ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / UDBHAV CHINMAYA

Registration approved No litigation declared Residential/Group Housing project

UDBHAV CHINMAYA

By UDBHAV DEVELOPERS

RG-KA-59853 · RERA PRM/KA/RERA/1257/334/PR/311225/008371 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
4 of 14Construction stages donefurthest along: RCC or MS Framed structure, 60%
24 of 40Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 155 documents Report an error

UDBHAV CHINMAYA is a Residential/Group Housing project by UDBHAV DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/311225/008371 on 31 Dec 2025. Possession is promised by 31 Dec 2028. 16 of the 40 units on this registration are recorded sold or booked, and 4 of 14 construction stages are filed complete.

At a glance

Project

  • NameUDBHAV CHINMAYA
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575004
  • Pincode575004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/311225/008371
  • ReraGenie IDRG-KA-59853

Builder

  • NameUDBHAV DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29AADFU3048B1ZD
  • Authorized SignatoryKIRAN BANGRA KULUR
  • Other registrations4 more →
  • Declared earlier projects8 →

Key dates

this monthRegisteredDec 2025PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on31 Dec 2025
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed155 files

Current status

40%16 of 40 units booked
68.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
UDBHAV CHINMAYA---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 14 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 60%.

Building: 37% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure60%
Masonry Construction40%
Plastering inside , outside & Ceiling10%
Joinery: Doors, Windows, Ventilators etc5%
Basic work of Water supply, Sanitary and Electrification5%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes5%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes10%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolNoNot applicable
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes60%
LiftsYes30%
Corridor/LobbiesYes40%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,478 sq m
Named landowners2
LandownerVillageDistrict
RAMACHANDRA MALYA--
RAMACHANDRA MALYA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 27.49 cr
Cost incurredRs 18.93 cr
Spent of the estimate68.84%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 25.22 crRs 15.13 cr
Payment of taxesRs 1.52 cr-
On-site expenditure-Consultants FeesRs 50.00 lakhRs 4.00 lakh
Administrative CostsRs 25.00 lakh-
On-site expenditure-Site Overhead-Rs 3.75 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBABA ALANKAR
EngineerBABA ALANKAR
Chartered AccountantKRISHNA MOORTHY ALAPE

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed155

As listed on the registration, under the names the promoter filed them with; the newest 80 of 155 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/311225/008371 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form - 4 CA Certificate.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect's Certificate.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer's Certificate.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Labour and Education Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Chartered Accountant.pdf11 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect's Certificate.pdf11 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer's Certificate.pdf11 Jul 2026
Q1 2026-27 Water supply and sewage board11 Jul 2026
Q1 2026-27 KPTCL- BESCOM11 Jul 2026
Q1 2026-27 Labour and Education Department11 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Forn-4 Chartered Accountant.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5-Architect Certificate.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6-Engineers Certificate.pdf11 Apr 2026
Q4 2025-26 Water supply and sewage board11 Apr 2026
Q4 2025-26 KPTCL- BESCOM11 Apr 2026
Q4 2025-26 Labour and Education Department11 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form - 4 CA Certificate.pdf18 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form - 5 Architect's Certificate.pdf18 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form - 6 Engineer's Certificate.pdf18 Feb 2026
Q3 2025-26 Water supply and sewage board18 Feb 2026
Q3 2025-26 KPTCL- BESCOM18 Feb 2026
Q3 2025-26 Labour and Education Department18 Feb 2026
Structural Stabilty Certificate clarificationsFile: Structural Engineers,Stability,Clarification.pdf30 Dec 2025
STP Declaration ,Septic Tank and Drainage Drawing LayoutFile: STP Declaration and Drawing.pdf30 Dec 2025
ClarificationFile: Clarifications-30-12-2025.pdf30 Dec 2025
Structural Stability CertificateFile: Structural Stability Certificate -Udbhav Chinmaya.pdf26 Dec 2025
Clarification of Stuctural EngineersFile: Clarification Structural engineers.pdf26 Dec 2025
Septic tank/sewer line/soak pit drawingFile: Manhole.pdf26 Dec 2025
ClarificationFile: Clarification-26-12-2025.pdf26 Dec 2025
PRM/KA/RERA/1257/334/PR/210219/003923 and PRM/KA/RERA/1257/334/PR/090322/004748File: Quarter details 004748.pdf19 Dec 2025
quarter updationFile: Quarter details UPDATED 100%.pdf19 Dec 2025
completion detailsFile: RERA MARCELS MAISON COMPLETION DETAILS.pdf19 Dec 2025
completion detailsFile: RERA UDBHAV SQUARE COMPLETION DETAILS.pdf19 Dec 2025
completion detailsFile: RERA completion UDBHAV Shanti.pdf19 Dec 2025
completion detailsFile: RERA Project List K R K AYUSH completion details.pdf19 Dec 2025
source of fundFile: Source of Fund.pdf19 Dec 2025
Structual Engineer clarificationFile: Clarification Structural engineers.pdf19 Dec 2025
WELLFile: well 2.jpeg19 Dec 2025
WellFile: well 3.jpeg19 Dec 2025
Septic Tank drawingFile: Manhole.pdf19 Dec 2025
PRM/KA/RERA/1257/334/PR/210219/003923File: KRK AAYUSH - COMPLETION CERTIFICATE.pdf19 Dec 2025
PRM/KA/RERA/1257/334/PR/210219/003923File: form-4 CC-CA.pdf19 Dec 2025
PRM/KA/RERA/1257/334/PR/090322/004748File: Udbhav Shanthi-Completion Certificate.pdf19 Dec 2025
PRM/KA/RERA/1257/334/PR/090322/004748File: Form - 4CC.pdf19 Dec 2025
Structual Stability CertificateFile: Structural Stability Certificate.pdf19 Dec 2025
ClarificationsFile: Clarifications-18-12-2025.pdf19 Dec 2025
Non Litigation AffidavitFile: Non Litigation Affidavit.pdf19 Dec 2025
Quater updationFile: Quarter details 004748.pdf15 Dec 2025
Quater updationFile: Quarter details UPDATED 100%.pdf15 Dec 2025
ECFile: 24)EC No-1&2 01-04-1994 To 31-03-2004.pdf15 Dec 2025
ECFile: 25)EC No-3&4 01-04-1994 To 31-03-2004.pdf15 Dec 2025
ECFile: 26)EC No-1&2 01-04-2004 To 17-04-2025.pdf15 Dec 2025
EcFile: 27)EC No-3&4 01-04-2004 To 17-04-2025.pdf15 Dec 2025
Original Single Plot layout planFile: single site plan with order.pdf15 Dec 2025
Original Single Plot layout plan orderFile: single site plan with order.pdf15 Dec 2025
Building LicenseFile: Udbhav Chinmaya Building Licence.pdf15 Dec 2025
original sanctioned drawings, floor plan, sectional drawings and elevationFile: Approved Plan 1.pdf15 Dec 2025
original sanctioned drawings, floor plan, sectional drawings and elevationFile: Approved plan 2.pdf15 Dec 2025
original sanctioned drawings, floor plan, sectional drawings and elevationFile: Approved plan 3.pdf15 Dec 2025
structural stability certificateFile: Structural stability Certificate.jpeg15 Dec 2025
AFSFile: AOS.pdf15 Dec 2025
Estimated CostFile: Estimation.pdf15 Dec 2025
Engineer licenseFile: Engineer license self attested.pdf15 Dec 2025
Water sourceFile: well.jpeg15 Dec 2025
WellFile: well1.jpeg15 Dec 2025
wellFile: well2.jpeg15 Dec 2025
Water NOCFile: Water NOC.pdf15 Dec 2025
STP notificationFile: STP mandatory notification by GoK.pdf15 Dec 2025
Source of FundFile: Source of Fund.pdf15 Dec 2025
Non litigationFile: Non litigation.pdf15 Dec 2025
Notorized AffidavitFile: Notorized Affidavit.pdf15 Dec 2025
ADLRFile: ADLR.pdf15 Dec 2025
ClarificationsFile: Clarification.pdf15 Dec 2025
Structual engineer licenseFile: Certificate anil hegde.pdf15 Dec 2025
RTC, survey 55-3C-
Mutation, survey 55-3C-
Encumbrance Certificate, survey 55-3C-
Conversion/Alienation Order, survey 55-3C-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
UDBHAV SHANTHIKADRI TEMPLE ROAD MANGALORECompleted-No date filed
MARCELS MAISONATTAVARA VILLAGE MANGALORE TALUK , MANGALORECompleted-No date filed
K R K AAYUSHNEAR SKATE CITY URWA HOIGEBAIL MANGALORECompleted-No date filed

How this compares with Dakshina Kannada

40%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep UDBHAV CHINMAYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmUDBHAV CHINMAYAOther 113Dot size: filed unitsN

Filed coordinates, straight-line distance. 113 registered projects within 2 km.

Builder: UDBHAV DEVELOPERS

UDBHAV DEVELOPERS has 5 registrations on RERA Karnataka, including UDBHAV SHANTHI and MARCELS MAISON. Its filings declare 8 earlier projects, 6 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if UDBHAV CHINMAYA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of UDBHAV CHINMAYA?

The registered promoter entity is UDBHAV DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AADFU3048B1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in UDBHAV CHINMAYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at UDBHAV CHINMAYA?

The professionals named in the filing: Architect: BABA ALANKAR; Engineer: BABA ALANKAR; Chartered Accountant: KRISHNA MOORTHY ALAPE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UDBHAV CHINMAYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UDBHAV CHINMAYA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UDBHAV CHINMAYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.