Casa Terraza Phase-3

By R AND J BUILDLINE LLP

RG-MH-62019 · RERA P99000031526 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedmoved 30 months from the original
3 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 40%
103 of 134Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

Casa Terraza Phase-3 is a Residential / Group Housing project by R AND J BUILDLINE LLP in Palghar, Maharashtra, registered with MahaRERA as P99000031526 on 25 Oct 2021. Possession is promised by 30 Jun 2028. The completion date has moved by 30 months from the original filing. 31 of the 134 units on this registration are recorded sold or booked, and 3 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCasa Terraza Phase-3
  • TypeResidential / Group Housing
  • Location
    • Survey No.9B
    • Diwanman
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401202
  • Pincode401202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000031526
  • ReraGenie IDRG-MH-62019

Builder

  • NameR AND J BUILDLINE LLP
  • Entity typePartnership
  • PartnersBhagwan Wadhwani, Ishwar Assandas Dialani, Jagdish Assandas Dialani, Sandeep Jogani, Ramesh Jogani

Key dates

this monthRegisteredOct 2021First promiseDec 2025Revised toJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Oct 2021
  • Promised completion30 Jun 2028
  • Revised completionRevised to 30 Jun 2028 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed86 files

Current status

23%31 of 134 units booked
21.3%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing - DNA24131340134
NANA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 40%.

Wing - D34%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed59

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots59
Closed/Covered59

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,353 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityVasai-Virar City Municipal Corporation
Permissible FSI22955.78
Proposed, not sanctioned6,040 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch101-104 Tulsiani Chambers Free Press Journal Marg Nariman Point Mumbai-400021 Maharashtra
Estimated costRs 75.00 cr
Cost incurredRs 15.96 cr
Work done21.28%
BuildingWingEstimatedIncurred
Wing - DNARs 73.50 crRs 15.96 cr
-NARs 1.50 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMahammed Shakil A Ghanchi
EngineerSK Consultants & Engineers
Chartered AccountantNB Sayed & Associates
Chartered AccountantVikas Abhang & Associates
PartnerRole in project
R AND J BUILDLINE LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000018237Dec 2025 → Dec 2026

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EA16022619858Dec 2025 → Jun 2028

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. request a short extension of time due to temporary constraints in labour availability, along with a few other essential construction-related requirements that are still in progress. These unforeseen factors have resulted in a slight delay in completing the remaining minor works, despite consistent efforts to adhere to the original schedule. Granting additional time would enable proper arrangement of labour resources and completion of all pending activities with due care, ensuring that the work is ex

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600345Bhakti AchrekarR AND J BUILDLINE LLP22/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Casa_Terraza_Phase-3_Form1_Q1_2026-27_20-07-2026_04-09.pdf20 Jul 2026
Withdrawal Update Form 2File: Casa_Terraza_Phase-3_Form2_Q1_2026-27_20-07-2026_04-09.pdf20 Jul 2026
Withdrawal Update Form 3File: Casa_Terraza_Phase-3_Form3_Q1_2026-27_11-07-2026_13-48_doc1.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1 - Casa Terraza Phase - 3 as on March 2026.pdf25 Apr 2026
Withdrawal Update Form 2File: Form 2 - Casa Terraza Phase - 3 as on March 2026.pdf25 Apr 2026
Withdrawal Update Form 3File: Form 3 - Casa Terraza Phase - 3 as on March 2026.pdf25 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 of Casa Terraza phase 3 FY 2024-25.pdf23 Feb 2026
Withdrawal Update Form 1File: Form 1 - Casa Terraza Phase-3 as on Sep 2025.pdf13 Feb 2026
Withdrawal Update Form 1File: Form 1 - Casa Terraza Phase-3 as on Sep 2025.pdf13 Feb 2026
Withdrawal Update Form 1File: Form 1 - Casa Terraza Phase-3 as on Sep 2025.pdf13 Feb 2026
Withdrawal Update Form 1File: Form 1 - Casa Terraza Phase-3 as on Dec 2025.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2 - Casa Terraza Phase-3 as on June 2025.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2 - Casa Terraza Phase-3 as on Sep 2025.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2 - Casa Terraza Phase-3 as on Sep 2025.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2 - Casa Terraza Phase-3 as on Dec 2025.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3 - Casa Terraza Phase-3 as on June 2025.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3 - Casa Terraza Phase-3 as on June 2025.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3 - Casa Terraza Phase 3 as on Sep 2025.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3 - Casa Terraza Phase-3 as on Dec 2025.pdf13 Feb 2026
Withdrawal Update Form 1File: Form 1 - Casa Terraza Phase-3 as on Dec 2025.pdf12 Feb 2026
Withdrawal Update Form 2File: Form 2 - Casa Terraza Phase-3 as on Dec 2025.pdf12 Feb 2026
Withdrawal Update Form 3File: Form 3 - Casa Terraza Phase-3 as on Dec 2025.pdf12 Feb 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Casa Terraza Phase - 3 as on 31st March 2025.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Casa Terraza Phase-3 as on March 2025.pdf20 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 of Casa Terraza phase 3 FY 23-24.pdf26 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Casa Terraza Phase - 3 as on 31st December 2024.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Casa Terraza Phase-3 as on 31-12-2024.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Casa Terraza Phase - 3 as on 30th September 2024.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Casa Terraza Phase-3 as on Sep 2024.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Casa Terraza Phase-3 as on June 2024.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Casa Terraza Phase - 3 as on 30th June 2024.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Casa Terraza Phase-3 as on March 2024.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Casa Terraza Phase-3 as on March 2024.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Casa Terraza Phase-3 as on Dec 2023.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Casa Terraaza Phase -3 as on Dec 2023.pdf15 Jan 2024
Declaration in FORM BFile: Form B.pdf13 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept.pdf13 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From - 2- Engineers certificate.pdf13 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form- 2A ( 21-22).pdf13 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A (22-23).pdf13 Dec 2023
Disclosure of sold/ booked inventoryFile: Circular 29.pdf13 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (2).pdf13 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Report form 5 - 2021-22.pdf13 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Report form 5 - 2022-23.pdf13 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Casa Terraza Phase-3 as on Sep 2023.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Casa Terraaza Phase -3 (Wing D) as on 30th Sept 2023.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Casa Terraza Phase 3 as on 31-03-2023.pdf16 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Casa Terraza Phase 23 as on March 2023.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Casa Terraza Phase 3 as on June 2023.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Casa Terraaza Phase 3 as on March 2023.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Casa Terraaza Phase III as on June 2023.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 of Casa Terraaza as on June 2022.pdf5 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on September 2022.pdf5 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 of Casa Terraza Phase 3 as on December 2022.pdf5 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Casa Terraaza Phase 3 June 2022.pdf5 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Casa Terraaza Phase 3 Sept 2022.pdf5 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Casa Terraaza Phase 3 as on December 2022.pdf5 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Casa Terraza Phase 3 as on 2021-22.pdf5 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Casa Terraza Phase 3 as on 2021-22.pdf5 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Casa Terraza Phase 3 as on 2021-22.pdf5 Jun 2023
Building plan approvalFile: Plan 2A_rotated.pdf20 Oct 2021
Copy of the legal title reportFile: Title_Scanned_R and J buildline_MahaRERA.pdf20 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan 2A_rotated.pdf20 Oct 2021
Declaration about Commencement CertificateFile: rnj declaration.pdf20 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Casa Terraza Phase-3.pdf20 Oct 2021
Proforma of Allotment letterFile: Agreement for Sale_R and J Buildine LLP.pdf20 Oct 2021
Proforma of Allotment letterFile: Allotment Letter_R and J Buildine LLP.pdf20 Oct 2021
Layout approvalFile: Plan 1_compressed.pdf19 Oct 2021
Building plan approvalFile: Plan 2_rotated_compressed.pdf19 Oct 2021
Building plan approvalFile: Plan 3_rotated.pdf19 Oct 2021
Building plan approvalFile: Plan 4_rotated.pdf19 Oct 2021
Building plan approvalFile: Plan 5_rotated.pdf19 Oct 2021
Building plan approvalFile: Plan 6_rotated.pdf19 Oct 2021
Building plan approvalFile: Plan 7_rotated (1).pdf19 Oct 2021
PAN CardFile: IMG-20211018-WA0073 (1).pdf19 Oct 2021
Details of encumbrancesFile: RNJ ENCUMBRANCE.pdf19 Oct 2021
Copy of Layout Approval (in case of layout)File: Plan 1_compressed.pdf19 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan 2_rotated_compressed.pdf19 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan 3_rotated.pdf19 Oct 2021

How this compares with Palghar

23%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 30 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Casa Terraza Phase-3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Diwanman3,200+ in Palghar

2 kmCasa Terraza Phase-3Completed 43Lapsed / revoked 25Other 52Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: R AND J BUILDLINE LLP

R AND J BUILDLINE LLP has 1 registration on MahaRERA, including Casa Terraza Phase-3. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Casa Terraza Phase-3 is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Casa Terraza Phase-3?

The registered promoter entity is R AND J BUILDLINE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Casa Terraza Phase-3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Casa Terraza Phase-3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Casa Terraza Phase-3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Casa Terraza Phase-3?

The professionals named in the filing: Architect: Mahammed Shakil A Ghanchi; Engineer: SK Consultants & Engineers; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Vikas Abhang & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Casa Terraza Phase-3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Casa Terraza Phase-3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Casa Terraza Phase-3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.