Completed Litigation declared Residential / Group Housing project

CAFER at L and T Realty Elixir Reserve

By Larsen & Toubro Ltd. (Realty Division)

RG-MH-58323 · RERA P51800034053 · Last updated on MahaRERA portal: 20 Apr 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2025Possession promisedregistration recorded completed
1 of 11Construction stages donefurthest along: Podiums (if any), 75%
0Complaints at MahaRERAon this registration
Jump to the 119 documents Report an error

CAFER at L and T Realty Elixir Reserve is a Residential / Group Housing project by Larsen & Toubro Ltd. (Realty Division) in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800034053 on 17 Mar 2022. The registration is recorded completed; possession was promised by 30 Apr 2025.

At a glance

Project

  • NameCAFER at L and T Realty Elixir Reserve
  • TypeResidential / Group Housing
  • Location
    • Saki Vihar Road
    • Powai
    • Paspoli
    • Kurla
    • Mumbai Suburban
    • 400072
  • Pincode400072
  • RERA no.P51800034053
  • ReraGenie IDRG-MH-58323

Builder

  • NameLarsen & Toubro Ltd. (Realty Division)
  • Entity typeCompany
  • CINL99999MH1946PLC004768
  • GSTIN27AAACL0140P5ZF
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Chairman & Managing DirectorSekharipuram Narayanan Subrahmanyan
  • President, Whole-time Director & CFORamamurthi Shankar Raman
  • Whole-time Director & President (Energy)Subramanian Sudarsanam Sarma
  • Whole time Director and Senior ExecutivesSudhindra Vasantrao Desai, Tharayil Madhava Das
  • Whole-time Director & Senior ExecutiveAnil Vithal Parab
  • Other registrations24 more →
  • Completed7 of 25
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects30 →

Key dates

this monthRegisteredMar 2022PromisedApr 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Mar 2022
  • Promised completion30 Apr 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed119 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CAFER at L and T Realty Elixir ReserveNA320000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 75%.

CAFER at L and T Realty Elixir Reserve: 21% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)30%
Podiums (if any)75%
Plinth30%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed273

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots273
Closed/Covered273

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area928 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Sep 2024

Approvals and building plan

Permissible FSI17017.12
Proposed, not sanctioned17,017 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAndheri East Mumbai

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Larsen & Toubro Ltd. (Realty Division)-

Litigation declared2

CaseCourtStatus
2019/9486/2019HIGH COURT OF JUDICATURE AT BOMBAYPetition is not admitted till date As per TC uploaded Title of Land is clear and marketable
2019/9486/2019HIGH COURTOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Mar 2025

Documents filed119

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Cafer.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Cafer.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Cafer.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory-Cafer.pdf20 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Cafer.pdf20 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2465473_OC_signed.pdf21 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Cafer.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Cafer.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Cafer.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Cafer.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory-Cafer.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Cafer.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Cafer.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Cafer.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Cafer.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory-Cafer.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Cafer.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Cafer.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Cafer.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory-Cafer.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Cafer.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-T2-Cafer.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-T2-Cafer.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-T2-Cafer.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA-Form-2-Cafer-Q2-FY 24-25.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RERA-Form-2A-Cafer-Q2-FY 24-25.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Q2-FY-24-25-Cafer.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Inventory-ER-Cafer.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA-Form-2-Cafer-Q2-FY 24-25.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RERA-Form-2A-Cafer-Q2-FY 24-25.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Q2-FY-24-25-Cafer.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Inventory-ER-Cafer.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Q2-FY-24-25-Cafer.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA-Form-2-Cafer-Q2-FY 24-25.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Inventory-ER-Cafer.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RERA-Form-2A-Cafer-Q2-FY 24-25.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Tower Cafer.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Tower Cafer.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Tower Cafer.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Cafer Form 1.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: ER-T02-Cafer.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Q1_FY 24-25_CAFER.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Caf- form 2.pdf19 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Cafer-2A.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: ER Tower Cafer.pdf25 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Cafer_form 1 Mar'24.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 caf.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A caf.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Q4_FY 2324_T2 CAFER.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- T2_Cafer.pdf26 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form -2A-T2_Cafer.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: Elixir_Cafer.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Cafer.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - T2-CAFER.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form 2 Cafer.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Cafer_sold unsold.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Q2_FY 23-24_Cafer.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Cafer.pdf30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Cafer.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - CAFER.PDF2 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Cafer.pdf2 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cafer.pdf2 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA Form 2 Cafer.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: Cafer.pdf21 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cafer.pdf21 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: CC-Powai West Resi.pdf13 Jul 2023
Disclosure of sold/ booked inventoryFile: Elixir Cafer.pdf14 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - CAFER.PDF21 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Cafer.pdf21 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form 2 T2(Q4).pdf20 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - CAFER-T2.pdf20 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form 2 T2-Cafer.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: Cafer_compressed.pdf20 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Cafer_Q3_FY 22-23.pdf20 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Cafer_dec22.PDF19 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CAFER_SEP22.pdf20 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_sep22CAFER .pdf19 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form 2_caferT2_SEP22.pdf19 Oct 2022
Disclosure of sold/ booked inventoryFile: Sep22_Sold_cafer.pdf19 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Cafer Final.pdf5 Oct 2022

Promoter's earlier projects12

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

10 delivered on promise2 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Emerald Isle - T16P51800013504Kurla, Mumbai Suburban127Oct 2017OngoingDec 2024Registered original: Dec 2023Not delivered
TestTest1-OngoingNov 2024Not delivered
Emerald Isle - T15Saki Vihar Road Powai208-CompletedJun 2023Jun 2023
Emerald Isle - T10Saki Vihar Road Powai203-CompletedJun 2023Jun 2023
Emerald Isle - T9Saki Vihar Road Powai150-CompletedJun 2021Apr 2021
Emerald Isle - T8Saki Vihar Road Powai72-CompletedDec 2018Dec 2018
Emerald Isle - T7Saki Vihar Road Powai72-CompletedJun 2018Apr 2018
Emerald Isle - T4, T5, T6Saki Vihar Road Powai371-CompletedJun 2018Sep 2017
EMERALD ISLE TOWER 3LT Emerald Isle Near LT Business Park Saki Vihar Road Powai 400072139-CompletedAug 2016Jul 2016
EMERALD ISLE TOWER 2LT Emerald Isle Near LT Business Park Saki Vihar Road Powai 40007293-CompletedAug 2016Jul 2016
EMERALD ISLE TOWER 1LT Emerald Isle Near LT Business Park Saki Vihar Road Powai 40007242-CompletedAug 2016Jul 2016
SanofiSanofi House No 117B Near L&T Business Park Saki Vihar Road Mumbai 4000721-CompletedMar 2015Mar 2015

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CAFER at L and T Realty Elixir Reserve on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Powai6,700+ in Mumbai Suburban

Builder: Larsen & Toubro Ltd. (Realty Division)

Larsen & Toubro Ltd. (Realty Division) has 25 registrations on MahaRERA, including Emerald Isle - T7 and Emerald Isle - T8. Its filings disclose 30 earlier MahaRERA projects: declares 19 of 19 past projects completed on time. Litigation is declared on 14 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if CAFER at L and T Realty Elixir Reserve is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CAFER at L and T Realty Elixir Reserve?

The registered promoter entity is Larsen & Toubro Ltd. (Realty Division), a company as per the filing. Its CIN L99999MH1946PLC004768 and GSTIN 27AAACL0140P5ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CAFER at L and T Realty Elixir Reserve?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CAFER at L and T Realty Elixir Reserve?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in CAFER at L and T Realty Elixir Reserve?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CAFER at L and T Realty Elixir Reserve. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CAFER at L and T Realty Elixir Reserve to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.