Home / Browse projects / Mumbai Suburban, Maharashtra / Emerald Isle - T16

Registered Litigation declared Residential / Group Housing project

Emerald Isle - T16

By Larsen & Toubro Ltd. (Realty Division)

RG-MH-89139 · RERA P51800013504 · Last updated on MahaRERA portal: 3 Oct 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • 6 complaints at MahaRERA
  • Completion date moved by 41 months
  • 2 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
May 2027Possession promisedmoved 41 months from the original
6 of 11Construction stages donefurthest along: Installation of Lifts, 98%
11 of 127Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 311 documents Report an error

Emerald Isle - T16 is a Residential / Group Housing project by Larsen & Toubro Ltd. (Realty Division) in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013504 on 9 Oct 2017. Possession is promised by 31 May 2027. The completion date has moved by 41 months from the original filing. 116 of the 127 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameEmerald Isle - T16
  • TypeResidential / Group Housing
  • Location
    • Saki Vihar Road
    • Kurla
    • Mumbai Suburban
    • 400072
  • Pincode400072
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800013504
  • ReraGenie IDRG-MH-89139

Builder

  • NameLarsen & Toubro Ltd. (Realty Division)
  • Entity typeCompany
  • CINL99999MH1946PLC004768
  • GSTIN27AAACL0140P5ZF
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Chairman & Managing DirectorSekharipuram Narayanan Subrahmanyan
  • President, Whole-time Director & CFORamamurthi Shankar Raman
  • Whole-time Director & President (Energy)Subramanian Sudarsanam Sarma
  • Whole time Director and Senior ExecutivesSudhindra Vasantrao Desai, Tharayil Madhava Das
  • Whole-time Director & Senior ExecutiveAnil Vithal Parab
  • Other registrations24 more →
  • Completed7 of 25
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects30 →

Key dates

this monthRegisteredOct 2017First promiseDec 2023Revised toMay 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Oct 2017
  • Promised completion31 May 2027
  • Revised completionRevised to 31 May 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed311 files

Current status

91%116 of 127 units booked
86.0%Work done, per cost certificate

Figures as on 3 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Emerald Isle - T16NA22191270127

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 98%.

Emerald Isle - T16: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 3 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes80%
Street LightingYes80%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed206

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots206
Closed/Covered206

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,014 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Jul 2026

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI19306.3
Proposed, not sanctioned6,039 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch5C/II, GF, Mittal Court, Mumbai -400021
Estimated costRs 125.89 cr
Cost incurredRs 108.33 cr
Work done86.05%
BuildingWingEstimatedIncurred
Emerald Isle - T16NARs 99.89 crRs 75.18 cr
-NARs 26.00 crRs 33.16 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHITEN SETHI
EngineerSwapnil Joshi
EngineerPankaj More
Chartered AccountantUrmit Shah
Chartered AccountantM S K A & Associates
PartnerRole in project
Larsen & Toubro Ltd. (Realty Division)-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017977Dec 2023 → Dec 2024

Reason as filed by the promoterDue to certain mitigating circumstances beyond the control of the promoter

EA07072621691Dec 2023 → May 2027

Reason as filed by the promoterWe, Larsen & Toubro Ltd. (Realty Division), being the Promoter of the real estate project "Emerald Isle - T16", registered with the Maharashtra Real Estate Regulatory Authority under Registration No. P51800013504, submit this explanation in support of our application seeking extension of the registration of the project. The project consists of 127 units, out of which 116 units have already been sold. The registration of the project under MahaRERA was valid up to 03/10/2023. The Competent Authority has granted a Part Occupancy Certificate for the Upper basement, Ground Floor, First Podium, Seco

Litigation declared3

CaseCourtStatus
2755 of 2011/2011HIGH COURT OF JUDICATURE AT BOMBAYSuit is pending for final hearing
2593 of 2012/2012HIGH COURT OF JUDICATURE AT BOMBAYSuit is pending for final hearing on August Two Thousand Ninteen
2755 of 2011/2011HIGH COURT OF JUDICATURE AT BOMBAYOngoing

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000591415Kavita Sudesh KejriwalLarsen and Toubro Ltd.03/08/2024
CC006000000591419Kavita Sudesh KejriwalLarsen and Toubro Ltd.03/08/2024
CC006000000591464Kavita Sudesh KejriwalLARSEN AND TOUBRO LIMITED13/08/2024
CC12400296Kavita Sudesh KejriwalLarsen & Toubro Ltd. (Realty Division)01/10/2024
CC12604263Niloofer Cyurus RajaLarsen & Toubro Ltd. (Realty Division)07/07/2026
CC12604261Cyrus RajaLarsen & Toubro Ltd. (Realty Division)07/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Feb 2025

Documents filed311

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 311 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: form 5 T16.pdf3 Oct 2026
Form 1File: Form 1.pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3.pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1.pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3.pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1.pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3.pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1.pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3.pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Tower 16.pdf7 Jul 2026
Form 1File: Form 1 (1).pdf7 Jul 2026
Form 2File: Form 2.pdf7 Jul 2026
Form 3File: Form 3 (1).pdf7 Jul 2026

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

10 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsStatusPromisedDelivered
TestTest1OngoingNov 2024Not delivered
Emerald Isle - T15Saki Vihar Road Powai208CompletedJun 2023Jun 2023
Emerald Isle - T10Saki Vihar Road Powai203CompletedJun 2023Jun 2023
Emerald Isle - T9Saki Vihar Road Powai150CompletedJun 2021Apr 2021
Emerald Isle - T8Saki Vihar Road Powai72CompletedDec 2018Dec 2018
Emerald Isle - T7Saki Vihar Road Powai72CompletedJun 2018Apr 2018
Emerald Isle - T4, T5, T6Saki Vihar Road Powai371CompletedJun 2018Sep 2017
EMERALD ISLE TOWER 3LT Emerald Isle Near LT Business Park Saki Vihar Road Powai 400072139CompletedAug 2016Jul 2016
EMERALD ISLE TOWER 2LT Emerald Isle Near LT Business Park Saki Vihar Road Powai 40007293CompletedAug 2016Jul 2016
EMERALD ISLE TOWER 1LT Emerald Isle Near LT Business Park Saki Vihar Road Powai 40007242CompletedAug 2016Jul 2016
SanofiSanofi House No 117B Near L&T Business Park Saki Vihar Road Mumbai 4000721CompletedMar 2015Mar 2015

How this compares with Mumbai Suburban

91%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 41 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Emerald Isle - T16 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmEmerald Isle - T16Completed 56Lapsed / revoked 24Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 118 registered projects within 2 km.

Builder: Larsen & Toubro Ltd. (Realty Division)

Larsen & Toubro Ltd. (Realty Division) has 25 registrations on MahaRERA, including Emerald Isle - T7 and Emerald Isle - T8. Its filings disclose 30 earlier MahaRERA projects: declares 19 of 19 past projects completed on time. Litigation is declared on 14 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Emerald Isle - T16 is delayed beyond 31 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Emerald Isle - T16?

The registered promoter entity is Larsen & Toubro Ltd. (Realty Division), a company as per the filing. Its CIN L99999MH1946PLC004768 and GSTIN 27AAACL0140P5ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Emerald Isle - T16?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Emerald Isle - T16?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Emerald Isle - T16?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Emerald Isle - T16?

The professionals named in the filing: Architect: HITEN SETHI; Engineer: Swapnil Joshi; Engineer: Pankaj More; Chartered Accountant: Urmit Shah; Chartered Accountant: M S K A & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Emerald Isle - T16?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Emerald Isle - T16. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Emerald Isle - T16 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.