Home / Browse projects / Mumbai Suburban, Maharashtra / Bhalla CHSL Jupiter - Venus

Registered No litigation declared Residential / Group Housing project

Bhalla CHSL Jupiter - Venus

By Chetna Global

RG-MH-11123 · RERA P51800000906 · Last updated on MahaRERA portal: 16 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 84 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 84 months from the original
14 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
30 of 54Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

Bhalla CHSL Jupiter - Venus is a Residential / Group Housing project by Chetna Global in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000906 on 25 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 84 months from the original filing. 24 of the 54 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBhalla CHSL Jupiter - Venus
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000906
  • ReraGenie IDRG-MH-11123

Builder

  • NameChetna Global
  • Entity typePartnership
  • PartnersBIPIN PURSHOTTAM CHOTALIYA, MANGALPRASAD KAMTAPRASAD AGRAHARI, NEHAL MUKESH SAVLA

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Jul 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed93 files

Current status

44%24 of 54 units booked
67.1%Work done, per cost certificate

Figures as on 16 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JupiterNA221527229
Venus B WingNA211325025

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

Jupiter88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)91%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Venus B Wing80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises53%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 16 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed107

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots107
Closed/Covered107
BuildingClosed/CoveredTotal
Jupiter5454
Venus B Wing5353

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,617 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 May 2026

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI5222.15
Proposed, not sanctioned3,783 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJambhli Naka Branch, Vaidya Building, Veer Savarkar Road, Charai, Thane 400601
Estimated costRs 25.22 cr
Cost incurredRs 16.93 cr
Work done67.11%
BuildingWingEstimatedIncurred
-NARs 12.22 crRs 8.27 cr
JupiterNARs 6.50 crRs 4.33 cr
Venus B WingNARs 6.50 crRs 4.33 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR P Asundaria
EngineerReji Kunjukutty
EngineerShahji Tanpure
EngineerIMPACT DESIGNERR
Chartered AccountantR S L & CO
Chartered AccountantMANISH K RAMAWATI & COMPANY
PartnerRole in project
Chetna Global-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005677Dec 2019 → Dec 2020

Reason as filed by the promoterWE REQUEST TO EXTEND OUR COMPLETION DATE TO 30TH DEC 2020

EXT51800012236Dec 2019 → Mar 2023

Reason as filed by the promotercovid - 19

EXT51800017483Dec 2019 → Dec 2024

Reason as filed by the promoterThe project was delayed for reasons beyond our control on account of various unforeseen events.

EXT51800027664Dec 2019 → Dec 2025

Reason as filed by the promoterThe primary reason for the delay is the underperformance of the appointed contractor, M/s. Nirvana Home Realty Elite LLP. Despite our repeated efforts to address performance issues, the contractor was unable to allocate sufficient resources, including labour and materials, to ensure the timely completion of the work. As a result, there were significant delays in the construction process. After repeated warnings and discussions, it became evident that the contractor was not in a position to meet the project requirements. Consequently, we made the decision to terminate the contract with M/s. Nir

EA12052620906Dec 2019 → Dec 2026

Reason as filed by the promoterThe project has been substantially completed; however, the Occupation Certificate (OC) is pending due to administrative delays beyond the Promoter’s control despite timely submission of all required documents and continuous follow-up with the authorities. Hence, we request the Authority to kindly grant an extension of the project registration till 31/12/2026 for obtaining the OC and completing the statutory compliances.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000199204Bhalla CHSL Jupiter - Venus through Representative Mr. Lalit Vazirani and L. SreedharChetan Global30/11/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect certificate- Form 1.pdf16 Jun 2026
Withdrawal Update Form 2File: Engineer Certificate form 2.pdf16 Jun 2026
Withdrawal Update Form 3File: Form 3 Final.pdf16 Jun 2026
Form 2A (FY 2024-2025)File: 2A Quality Assurance Certificate .pdf12 May 2026
Withdrawal Update Form 1File: Architect certificate- Form 1.pdf11 May 2026
Withdrawal Update Form 1File: Architect certificate- Form 1.pdf11 May 2026
Withdrawal Update Form 1File: Architect certificate- Form 1.pdf11 May 2026
Withdrawal Update Form 2File: Engineer Certificate form 2.pdf11 May 2026
Withdrawal Update Form 2File: Engineer Certificate form 2.pdf11 May 2026
Withdrawal Update Form 2File: Engineer Certificate form 2.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 Final.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 Final.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 Final.pdf11 May 2026
Declaration in FORM BFile: form b .pdf21 Mar 2025
Other - TechnicalFile: pert chart.pdf21 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf11 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 21.pdf20 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 22.pdf20 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: March 24.pdf20 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 24.pdf20 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 24.pdf20 Feb 2025
Building plan approvalFile: Plan Highlighted-1-3.pdf12 Feb 2025
Building plan approvalFile: Plan- Highlighted-4-6.pdf12 Feb 2025
Building plan approvalFile: Plan Highlighted-7-8.pdf12 Feb 2025
Details of encumbrances concerned to FinanceFile: Encumbrances to finance_compressed.pdf12 Feb 2025
Details of encumbrances concerned to FinanceFile: Legal Encumbrances_compressed.pdf12 Feb 2025
Declaration in FORM BFile: Form B- Promoter_compressed.pdf12 Feb 2025
Certificates of CA (Form 3)File: FORM_3 Signed by Rishabh.pdf12 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 2024.pdf12 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2024.pdf12 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sept 24.pdf12 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 24.pdf12 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: Highlighted CC.pdf12 Feb 2025
Building Plan Approval (IOD)File: Plan Highlighted-1-3.pdf12 Feb 2025
Building Plan Approval (IOD)File: Plan Highlighted-7-8.pdf12 Feb 2025
Building Plan Approval (IOD)File: Plan- Highlighted-4-6.pdf12 Feb 2025
CERSAI detailsFile: CERSAI downloaded report.pdf12 Feb 2025
CERSAI detailsFile: CERSAI Undertaking_compressed.pdf12 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Seperate bank details_compressed.pdf12 Feb 2025
Deviation Report with respect to Allotment letterFile: Deviation report of Allotment letter_compressed.pdf12 Feb 2025
Details of encumbrances concerned to LegalFile: Legal Encumbrances_compressed.pdf12 Feb 2025
Details of encumbrances concerned to LegalFile: Encumbrances to finance_compressed.pdf12 Feb 2025
Other - TechnicalFile: Annexure A OP OR_compressed.pdf12 Feb 2025
Deviation Report with respect to model copy of AgreementFile: Deviation report of AFS_compressed.pdf12 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Bipin- Disclosure of other projects_compressed.pdf12 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Mangal-Disclosure of other projects_compressed.pdf12 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Nehal-Disclosure of other projects_compressed.pdf12 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Umesh-Disclosure of other projects_compressed.pdf12 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 2022-23.pdf3 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf3 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 FY 2023-24.pdf3 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Sep 2024.pdf3 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Dec 24.pdf3 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Sep 2024.pdf3 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Dec 24.pdf3 Jan 2025
Declaration in FORM BFile: Form B.pdf30 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: form 5 scan 17-18.pdf30 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 scan 18-19.pdf30 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 scan 19-20.pdf30 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 scan 20-21.pdf30 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 scan 21-22.pdf30 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf28 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf7 Jul 2023
Declaration about Commencement CertificateFile: Declaration about CC.pdf4 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf4 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf4 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_31_03_23.pdf4 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure.pdf4 Jul 2023
Proforma of Agreement for saleFile: Model_AFS.pdf4 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ilovepdf_merged.pdf2 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ilovepdf_merged (2).pdf2 Aug 2022
OtherFile: scan20220723_16454821 - Copy.pdf2 Aug 2022
OtherFile: scan20220723_16460862 - Copy.pdf2 Aug 2022
Disclosure of sold/ booked inventoryFile: Disclourse1_merged.pdf21 Jul 2022
Disclosure of sold/ booked inventoryFile: DISCLOUSER.pdf24 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 1.pdf19 Aug 2021
OtherFile: PARTNERSHIP DEED.pdf19 Aug 2021
OtherFile: RESOLUTION FOR CHANGE IN PARTNERSHIP BHALLA CHSL_compressed.pdf11 Aug 2018
Details of encumbrancesFile: Title Certificate_compressed.pdf21 Jul 2017
Declaration in FORM BFile: NOTARISED FORM B.pdf21 Jul 2017

How this compares with Mumbai Suburban

44%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 84 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Bhalla CHSL Jupiter - Venus on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmBhalla CHSL Jupiter - VeCompleted 95Lapsed / revoked 71Other 129Dot size: filed unitsN

Filed coordinates, straight-line distance. 295 registered projects within 2 km.

Builder: Chetna Global

Chetna Global has 1 registration on MahaRERA, including Bhalla CHSL Jupiter - Venus. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Bhalla CHSL Jupiter - Venus is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Bhalla CHSL Jupiter - Venus?

The registered promoter entity is Chetna Global, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Bhalla CHSL Jupiter - Venus?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Bhalla CHSL Jupiter - Venus?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Bhalla CHSL Jupiter - Venus?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Bhalla CHSL Jupiter - Venus?

The professionals named in the filing: Architect: R P Asundaria; Engineer: Reji Kunjukutty; Engineer: Shahji Tanpure; Engineer: IMPACT DESIGNERR; Chartered Accountant: R S L & CO; Chartered Accountant: MANISH K RAMAWATI & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhalla CHSL Jupiter - Venus?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhalla CHSL Jupiter - Venus. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhalla CHSL Jupiter - Venus to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.