Home / Browse projects / Palghar, Maharashtra / BHAGWATI AND JEEVAN HEIGHTS

Registration lapsed No litigation declared Others project

BHAGWATI AND JEEVAN HEIGHTS

By SHREE GANESH BUILDERS & DEVELOPERS

RG-MH-25161 · RERA P99000004178 · Last updated on MahaRERA portal: 20 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 69 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
9 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
44 of 69Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

BHAGWATI AND JEEVAN HEIGHTS is a Others project by SHREE GANESH BUILDERS & DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000004178 on 8 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 69 months from the original filing. 25 of the 69 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete.

At a glance

Project

  • NameBHAGWATI AND JEEVAN HEIGHTS
  • TypeOthers
  • Location
    • NA
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401209
  • Pincode401209
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000004178
  • ReraGenie IDRG-MH-25161

Builder

  • NameSHREE GANESH BUILDERS & DEVELOPERS
  • Entity typePartnership
  • PartnersJAYWANT KASHINATH RAUT, RANJAN HASHA PATIL, SUSHIL RAM PATIL, RAVINDRA SURYAKANT CHAVAN, NINAD NANDAN PATIL
  • Other registrations6 more →
  • Completed2 of 7
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Aug 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 20 Mar 2019)
  • Buildings2 building records
  • Documents filed44 files

Current status

36%25 of 69 units booked

Figures as on 20 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JEEVAN HEIGHTSNA161247047
BHAGWATI HEIGHTNA8814822

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

JEEVAN HEIGHTS60%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BHAGWATI HEIGHT71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 20 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed37

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots37
Closed/Covered11
Open Space26
BuildingClosed/CoveredOpen SpaceTotal
JEEVAN HEIGHTS112233
BHAGWATI HEIGHT044

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,225 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityvvcmc
Permissible FSI2225.0
Proposed, not sanctioned2,225 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGAJANAN SMRUTI, PHULPADA RD, VIRAR EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY NARANG
EngineerMUKESH KUMAR
Chartered AccountantSANKHALA & CO.
PartnerRole in project
SHREE GANESH BUILDERS & DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000011431Mar 2019 → Dec 2024

Reason as filed by the promoterDue to Covid 19 Project was at stand still.As the situation is better we would like to complete the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 march 22.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 march 23.pdf20 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 march 24.pdf20 Feb 2025
Layout approvalFile: layout.pdf22 Jun 2023
Details of encumbrances concerned to FinanceFile: encumbrances.pdf22 Jun 2023
Details of encumbrances concerned to LegalFile: encumbrances.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: layout.pdf22 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: revised cc_compressed.pdf22 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1_compressed.pdf22 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf22 Jun 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf22 Jun 2023
Certificates of CA (Form 3)File: form 3_compressed.pdf22 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank acct.pdf22 Jun 2023
Deviation Report with respect to Allotment letterFile: deviation.pdf22 Jun 2023
Deviation Report with respect to model copy of AgreementFile: deviation.pdf22 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE 21-compressed.pdf19 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A.pdf19 Jun 2023
CERSAI detailsFile: shree ganesh builders Notary.pdf17 Feb 2022
Disclosure of sold/ booked inventoryFile: shree ganesh builders disclosure of sold.pdf17 Feb 2022
CERSAI detailsFile: CERSAI.pdf11 Feb 2022
PAN CardFile: PAN.pdf9 Feb 2022
Declaration about Commencement CertificateFile: DECLARATION CERTIFICATE.pdf9 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY ASSURANCE 2020.pdf9 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE 21-compressed.pdf9 Feb 2022
CERSAI detailsFile: CERSAI.pdf9 Feb 2022
Disclosure of sold/ booked inventoryFile: DISCLSURE OF SOLD -BOOKING INVENTORY.pdf9 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: ANNUAL REPORT 2018.pdf9 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ANNUAL REPORT 2019.pdf9 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ANNUAL REPORT 2020.pdf9 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ANNUAL REPORT 2021.pdf9 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architects certificate.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineers certificate.pdf28 Jul 2017
Certificates of CA (Form 3)File: form -3.pdf28 Jul 2017
OtherFile: LIST.pdf28 Jul 2017
Layout approvalFile: MYSCAN_20170727_0001.pdf27 Jul 2017
Building plan approvalFile: MYSCAN_20170727_0002.pdf27 Jul 2017
Copy of the legal title reportFile: title_of_Jeevan_Heights.pdf27 Jul 2017
Details of encumbrancesFile: title_of_Bhagwati_Heights ENCUMBRANCES.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: MYSCAN_20170727_0001.pdf27 Jul 2017
Building Plan Approval (IOD)File: MYSCAN_20170727_0002.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: bldg_1___bldg_2_CC (2).pdf27 Jul 2017
Declaration in FORM BFile: form b.pdf27 Jul 2017
Proforma of Allotment letterFile: FLAT AGR ALLOTMENT.pdf27 Jul 2017

How this compares with Palghar

36%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 69 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHAGWATI AND JEEVAN HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA3,200+ in Palghar

2 kmBHAGWATI AND JEEVAN HEIGCompleted 50Lapsed / revoked 38Other 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: SHREE GANESH BUILDERS & DEVELOPERS

SHREE GANESH BUILDERS & DEVELOPERS has 7 registrations on MahaRERA, including DURGA RESIDENCY and BHAGWATI AND JEEVAN HEIGHTS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that BHAGWATI AND JEEVAN HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BHAGWATI AND JEEVAN HEIGHTS is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHAGWATI AND JEEVAN HEIGHTS?

The registered promoter entity is SHREE GANESH BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHAGWATI AND JEEVAN HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BHAGWATI AND JEEVAN HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHAGWATI AND JEEVAN HEIGHTS?

The professionals named in the filing: Architect: SANJAY NARANG; Engineer: MUKESH KUMAR; Chartered Accountant: SANKHALA & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHAGWATI AND JEEVAN HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHAGWATI AND JEEVAN HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHAGWATI AND JEEVAN HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.