ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / BASIL MAXIMUS WING D AND E

Registered No litigation declared Others project

BASIL MAXIMUS WING D AND E

By BASIL AVANTE LLP

RG-MH-79102 · RERA P52100051323 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 75%
12 of 305Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

BASIL MAXIMUS WING D AND E is a Others project by BASIL AVANTE LLP in Pune, Maharashtra, registered with MahaRERA as P52100051323 on 8 Jun 2023. Possession is promised by 31 Dec 2027. 293 of the 305 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameBASIL MAXIMUS WING D AND E
  • TypeOthers
  • Location
    • PUNAWALE
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051323
  • ReraGenie IDRG-MH-79102

Builder

  • NameBASIL AVANTE LLP
  • Entity typePartnership
  • LLPINABB-7740
  • GSTIN27AAZFB8127G1ZY
  • LLPIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • PartnersCHETAN TANAJI MANGADE, KISAN SHIVRAJ VARMA, GOPAL SHIVRAJ VARMA, BASIL INFRA REALTY PRIVATE LTD, Ankit Soni
  • Other registrations4 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredJun 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Jun 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed104 files

Current status

96%293 of 305 units booked
90.8%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING DNA212010527132
WING ENA212014033173

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 75%.

WING D62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING E64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,159 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Aug 2025
LandownerVillageDistrict
Abeda P InamdarPune (M Corp.)Pune
P A INAMDARPune (M Corp.)Pune
Iftekhar P InamdarPune (M Corp.)Pune
Parvez P InamdarPune (M Corp.)Pune
Tanveer P InamdarPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI26510.95
Proposed, not sanctioned26,511 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHANKAWADI
Estimated costRs 92.94 cr
Cost incurredRs 84.41 cr
Work done90.82%
BuildingWingEstimatedIncurred
WING DNARs 45.72 crRs 41.60 cr
WING ENARs 45.72 crRs 41.60 cr
-NARs 1.50 crRs 1.20 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCUBIX ARCHITECTS ASSOCIATES
EngineerCTM ENGINEER AND CONSULTANT
Chartered AccountantKJS and Associates
PartnerRole in project
Basil Avante LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 D and E Wing- Jun.pdf16 Jul 2026
Withdrawal Update Form 2File: F2 D and E Wing - Jun.pdf16 Jul 2026
Withdrawal Update Form 3File: CA Certificate D and E Wing- Jun - converted.pdf16 Jul 2026
Withdrawal Update Form 1File: F1.pdf16 Apr 2026
Withdrawal Update Form 1File: F1.pdf16 Apr 2026
Withdrawal Update Form 2File: Engineers certificate.pdf16 Apr 2026
Withdrawal Update Form 2File: Engineers certificate.pdf16 Apr 2026
Withdrawal Update Form 3File: CA certificate.pdf16 Apr 2026
Withdrawal Update Form 3File: CA certificate.pdf16 Apr 2026
Withdrawal Update Form 1File: Architect Certificate Wing D E.pdf21 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate D E wing.pdf21 Jan 2026
Withdrawal Update Form 3File: CA Certificate Wing D E_compressed.pdf21 Jan 2026
Form 5 (FY 2024-2025)File: Basil Maximus Wing Wing D & E - Form 5.pdf19 Nov 2025
Withdrawal Update Form 1File: Basil_Maximus_Wing_Wing D_u0026_E_Architect Certificate_Sep_25.pdf14 Oct 2025
Withdrawal Update Form 2File: Basil_Maximus_Wing_Wing_D_u0026_E_Engineer_Certificate_Sep_2025.pdf14 Oct 2025
Withdrawal Update Form 3File: Basil_Maximus_Wing_Wing_D_u0026_E_CA_Certificate_Sep_2025.pdf14 Oct 2025
Form 1File: Form 1.pdf6 Aug 2025
Form 2File: Form 2.pdf6 Aug 2025
Form 3File: Form 3.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf6 Aug 2025
Form 1File: Form 1.pdf6 Aug 2025
Form 2File: Form 2.pdf6 Aug 2025
Form 3File: Form 3_compressed.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Discolsure_compressed.pdf6 Aug 2025
Withdrawal Update Form 1File: Form 1.pdf6 Aug 2025
Withdrawal Update Form 2File: Form 2.pdf6 Aug 2025
Withdrawal Update Form 3File: Form 3.pdf6 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Basil Maximus Wing D E final.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold and Unsold List 30 12 2024 final.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate - Basil Maximus Wing D and E.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - Basil Maximus Wing D and E.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Basil Maximus Wing D E final.pdf23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sold unsold compressed.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate compressed.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold unsold compressed.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf1 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate D and E Wing (Basil Maximus)_11zon.pdf1 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate D and E Wing (Basil Maximus).pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Basil Maximus D and E Wing.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Certificate for Quality Assurance Basil Maximus D and E Wing.pdf15 Jul 2024
Layout approvalFile: HPSC0120-compressed.pdf28 Apr 2024
Copy of Layout Approval (in case of layout)File: HPSC0120-compressed.pdf28 Apr 2024
Building plan approvalFile: HPSC0115_Wing D.pdf12 Apr 2024
Building plan approvalFile: HPSC0105_Wing E.pdf12 Apr 2024
Building plan approvalFile: HPSC0106_Wing E.pdf12 Apr 2024
Building plan approvalFile: HPSC0107_Wimg E.pdf12 Apr 2024
Building plan approvalFile: HPSC0108_Wing E.pdf12 Apr 2024
Building plan approvalFile: HPSC0109_Wing E.pdf12 Apr 2024
Building plan approvalFile: HPSC0110_Wing E.pdf12 Apr 2024
Building plan approvalFile: HPSC0112_Wing D.pdf12 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0115_Wing D.pdf12 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0105_Wing E.pdf12 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0106_Wing E.pdf12 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0107_Wimg E.pdf12 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0108_Wing E.pdf12 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0109_Wing E.pdf12 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0110_Wing E.pdf12 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC0112_Wing D.pdf12 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Punawale CC2024_.pdf12 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Wing D (31-12-2023).pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Wing D Q2.pdf17 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate wing D Q2.pdf17 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Wing D and E Q3.pdf17 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 Wing D and E Q2.pdf17 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Wing D and E Q3.pdf17 Feb 2024
Proforma of Allotment letterFile: Proforma of Agreement for Sale.pdf16 Dec 2023
Proforma of Agreement for saleFile: Proforma of Agreement for Sale.pdf16 Dec 2023
Proforma of Agreement for saleFile: maharera agreement.pdf18 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf8 May 2023
Layout approvalFile: Copy of Layout Approval.pdf1 May 2023
Building plan approvalFile: 1Building Plan Approval NA Order for plotted development.pdf1 May 2023
Building plan approvalFile: 2Building Plan Approval NA Order for plotted development.pdf1 May 2023
Building plan approvalFile: 3Building Plan Approval NA Order for plotted development.pdf1 May 2023
Building plan approvalFile: 4Building Plan Approval NA Order for plotted development.pdf1 May 2023
Building plan approvalFile: 5Building Plan Approval NA Order for plotted development.pdf1 May 2023
Building plan approvalFile: 6Building Plan Approval NA Order for plotted development.pdf1 May 2023
Building plan approvalFile: 7Building Plan Approval NA Order for plotted development.pdf1 May 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
BASIL MAXIMUS WING GP52100080092Punawale, Pune109Apr 2025OngoingDec 2029Not due yet
BASIL MAXIMUS WING FP52100056356-, Pune152May 2024OngoingDec 2028Not due yet
BASIL MAXIMUS WING CP52100050916Punawale, Pune48May 2023OngoingDec 2026Not due yet

How this compares with Pune

96%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BASIL MAXIMUS WING D AND E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNAWALE13,700+ in Pune

2 kmBASIL MAXIMUS WING D ANDCompleted 76Lapsed / revoked 25Other 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 202 registered projects within 2 km.

Builder: BASIL AVANTE LLP

BASIL AVANTE LLP has 5 registrations on MahaRERA, including BASIL MAXIMUS WING C and BASIL MAXIMUS WING D AND E. Its filings disclose 4 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if BASIL MAXIMUS WING D AND E is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BASIL MAXIMUS WING D AND E?

The registered promoter entity is BASIL AVANTE LLP, a partnership as per the filing. Its LLPIN ABB-7740 and GSTIN 27AAZFB8127G1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BASIL MAXIMUS WING D AND E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BASIL MAXIMUS WING D AND E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BASIL MAXIMUS WING D AND E?

The professionals named in the filing: Architect: CUBIX ARCHITECTS ASSOCIATES; Engineer: CTM ENGINEER AND CONSULTANT; Chartered Accountant: KJS and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BASIL MAXIMUS WING D AND E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BASIL MAXIMUS WING D AND E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BASIL MAXIMUS WING D AND E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.