Home / Browse projects / Mumbai Suburban, Maharashtra / BANDRA NORTH GULMOHAR AVENUE
BANDRA NORTH GULMOHAR AVENUE
By SHIVALIK VENTURES PRIVATE LIMITED
RG-MH-45269 · RERA P51800014036 · Last updated on MahaRERA portal: 13 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 34 complaints at MahaRERA
- Completion date moved by 40 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 6 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BANDRA NORTH GULMOHAR AVENUE is a Others project by SHIVALIK VENTURES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800014036 on 7 Nov 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 40 months from the original filing. 34 complaints are on record with the regulator.
At a glance
Project
- NameBANDRA NORTH GULMOHAR AVENUE
- TypeOthers
- Location
- GOLIBAR ROAD
- BANDRA NORTH
- Andheri
- Mumbai Suburban
- 400051
- Pincode400051
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800014036
- ReraGenie IDRG-MH-45269
Builder
- NameSHIVALIK VENTURES PRIVATE LIMITED
- Entity typeCompany
- DirectorsPRANAV RAJIV JAVERI, VIVEK SHANKAR JADHAV, PIYUSH ARUN VORA, ROHAN JITENDRA MEHTA, PRAKASH VASANT AJGAONKAR, SHARAD RAMCHANDRA JADHAV, LAKSHMIPATHY VADERAHALLI KODANDARAMY
- Other registrations1 more →
- Completed1 of 2
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Nov 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 27 Aug 2023)
- Buildings14 building records
- Documents filed182 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GULMOHAR AVENUE WING A | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING B | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING C | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING D | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING E | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING F | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING G | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING H | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING I | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING J | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING K | NA | 19 | 15 | 0 | 0 | 0 |
| GULMOHAR AVENUE WING L | NA | 19 | 15 | 0 | 0 | 0 |
| DELETED | NA | 0 | 0 | 0 | 0 | 0 |
| DELETED | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building14
As on 13 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
59 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is Basement (if any), at 25%.
GULMOHAR AVENUE WING A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GULMOHAR AVENUE WING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
GULMOHAR AVENUE WING C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
GULMOHAR AVENUE WING D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
GULMOHAR AVENUE WING E91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
GULMOHAR AVENUE WING F91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
GULMOHAR AVENUE WING G38%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GULMOHAR AVENUE WING H36%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GULMOHAR AVENUE WING I14%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 25% |
| Podiums (if any) | 0% |
| Plinth | 25% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GULMOHAR AVENUE WING J0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GULMOHAR AVENUE WING K0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GULMOHAR AVENUE WING L0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DELETED0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DELETED0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities20
As on 13 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 42% |
| Electrical meter room, sub-station, receiving station | Yes | 42% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 50% |
| Stilt Parking | Yes | 50% |
| SPACE FOR FITNESS CENTER | Yes | 0% |
| Passenger Elevators | Yes | 60% |
| DG SETS | Yes | 0% |
| CHILDERNS PLAY AREA | Yes | 0% |
Parking filed192
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| GULMOHAR AVENUE WING A | 9 | 9 |
| GULMOHAR AVENUE WING B | 12 | 12 |
| GULMOHAR AVENUE WING C | 9 | 9 |
| GULMOHAR AVENUE WING D | 12 | 12 |
| GULMOHAR AVENUE WING E | 9 | 9 |
| GULMOHAR AVENUE WING F | 12 | 12 |
| GULMOHAR AVENUE WING G | 39 | 39 |
| GULMOHAR AVENUE WING H | 48 | 48 |
| GULMOHAR AVENUE WING I | 12 | 12 |
| GULMOHAR AVENUE WING J | 9 | 9 |
| GULMOHAR AVENUE WING K | 12 | 12 |
| GULMOHAR AVENUE WING L | 9 | 9 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PAARSHAD ASSOCIATES |
| Engineer | GOKANI CONSULTANTS PRIVATE LIMITED |
| Chartered Accountant | Meghal Jain & Associates |
| Partner | Role in project |
|---|---|
| SHIVALIK VENTURES PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir, The sale building is proposed to be constructed as part of sale component in a Slum Rehabilitation scheme. The 3 wings of the building are almost completed and shall be handed over to Allottees soon. Work on remaining wings could not be started in time due to delay in evacuation of slum structures encroaching upon the sale plot. Currently, work on most of the wings in the building has been started after evacuation of major portion of the sale plot and we plan to finish the construction at earliest. Accordingly, we have discussed the revised timeline with Allottees and obtained their
Reason as filed by the promoter1) Our project Bandra North Gulmohar Avenue consiss of 12 wings having ground + 15 upper floors is part of Slum Rehabilitation Scheme at Village Bandra (East) under Regulation 33 (10) read with Appendix IV of the DCR, 1991 and DCPR 2034 for Greater Mumbai read with the provisions of the Maharashtra Slum Areas (I. C. & R) Act, 1971. 2) The construction status is as under: wing D, E and F -Completed: terrace slab with OHT tank; terrace water proofing; Flooring & tilling work up to 14th floor in Wing E & F and up to 11th floor in wing D; Internal Plastering up to 15th floor in all 3 wings. Wing B
Complaints filed with MahaRERA34
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000209709 | Mrs.Bianca Dsa Vincent and Mr.Sneeden AnthonyVincent | Shivalik Ventures Pvt. Ltd. | 17/01/2022 |
| CC006000000500473 | Jay Bhoite | Shivalik Ventures Pvt Ltd | 21/07/2024 |
| CC006000000210521 | Neeta Sandeep Poyekar | Shivalik Ventures Pvt. Ltd. | 29/03/2022 |
| CC006000000292446 | Poonam Sharma | SHIVALIK VENTURES PRIVATE LIMITED | 24/08/2022 |
| CC006000000397461 | Poonam Sharma | Shivalik Ventures Private Limited | 11/09/2023 |
| CC006000000292480 | SEJAL GAIKWAD | SHIVALIK VENTRUES PRIVATE LIMITED | 26/08/2022 |
| CC006000000292485 | Jaya Midya | SHIVALIK VENTURES PRIVATE LIMITED | 27/08/2022 |
| CC006000000292490 | Anthony Dias | SHIVAILIK VENTURES PRIVATE LIMITED | 28/08/2022 |
| CC006000000292499 | NADEEM SYED & NAUSHEEN SHAIKH | shivalik ventures Private Limited | 28/08/2022 |
| CC006000000292510 | Ronit Bhattacharya | SHIVALIK VENTURES PRIVATE LIMITED | 30/08/2022 |
| CC006000000397448 | Ronit Bhattacharya | Shivalik Ventures Private Limited | 11/09/2023 |
| CC006000000354510 | MANISHA VIJAY KASARALKAR | SHIVALIK VENTURES PVT LTD | 04/03/2023 |
| CC006000000375409 | Subhash Nathuram Shiwtarkar | Shivalik Ventures Pvt Ltd | 27/04/2023 |
| CC006000000375414 | Kiran Subhash Shiwtarkar | Shivalik Ventures Pvt Ltd | 27/04/2023 |
| CC006000000292496 | Shukla Rani Midya | shivalik Ventures Private limnited | 28/08/2022 |
| CC006000000397073 | Mamta Gupta | Vishal Jadhav | 13/08/2023 |
| CC006000000439694 | Sharokh Allarakhia | Shivalik Ventures Private Limited | 17/03/2024 |
| CC12400085 | Sushil Raheja | SHIVALIK VENTURES PRIVATE LIMITED | 12/09/2024 |
| CC12400832 | Rajiv Ashim Bhattacharya | SHIVALIK VENTURES PRIVATE LIMITED | 20/11/2024 |
| CC12401099 | Jagannath Mukund Gawas | SHIVALIK VENTURES PRIVATE LIMITED | 11/12/2024 |
| CC12400716 | Jyoti Jagannath Gawas | SHIVALIK VENTURES PRIVATE LIMITED | 09/11/2024 |
| CC12401218 | SHIVALIK VENTURES PRIVATE LIMITED | Poonam Sharma | 24/12/2024 |
| CC12500003 | SHIVALIK VENTURES PRIVATE LIMITED | Romit Bhattacharya | 01/01/2025 |
| CC12500185 | SHIVALIK VENTURES PRIVATE LIMITED | Farah Gulamwaris Thakur and Gulamwaris Thakur | 20/01/2025 |
| CC12500298 | SHIVALIK VENTURES PRIVATE LIMITED | Rajabhau Shriram Phad | 27/01/2025 |
| CC12500308 | SHIVALIK VENTURES PRIVATE LIMITED | Rajabhau Shriram Phad | 28/01/2025 |
| CC12500338 | SHIVALIK VENTURES PRIVATE LIMITED | Rajendra Kumar Jeer | 31/01/2025 |
| CC12500339 | SHIVALIK VENTURES PRIVATE LIMITED | Dr Prakhar Dharamchand Jain | 31/01/2025 |
| CC12500573 | Rajiv Ashim Bhattacharya | SHIVALIK VENTURES PRIVATE LIMITED | 19/02/2025 |
| CC12500635 | ANUP KUMAR JOTIBA BAGADI | SHIVALIK VENTURES PRIVATE LIMITED | 23/02/2025 |
| CC12501013 | Suraj Umashankar Jaiswar | SHIVALIK VENTURES PRIVATE LIMITED | 24/03/2025 |
| CC12503349 | SHIVALIK VENTURES PRIVATE LIMITED | Tabassum Mohammed Shaikh and Mohammed Yusuf Shaikh | 19/09/2025 |
| CC12503350 | SHIVALIK VENTURES PRIVATE LIMITED | Dinesh Anant Manjrekar and Sonali Dinesh Manjrekar Nee Sonali Shankar Umbalkar | 19/09/2025 |
| SM12500202 | Komal Mundada | SHIVALIK VENTURES PRIVATE LIMITED | 26/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Aug 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed182
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 182 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: BNGA ARch Form 1 202306.pdf | 13 Jan 2026 |
| Form 2File: BNGA Engr Form 2 202306.pdf | 13 Jan 2026 |
| Form 3File: BNGA CA Form 3 202306.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: BNGA SOld Inve Disclr 202306.pdf | 13 Jan 2026 |
| Form 1File: BNGA Arch Form 1 202412.pdf | 13 Jan 2026 |
| Form 2File: BNGA Engr Form 2 202412.pdf | 13 Jan 2026 |
| Form 3File: BNGA CA Form 3 202412.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: BNGA Sold Unsold Inventory Disclosure 202412.pdf | 13 Jan 2026 |
| Form 1File: BNGA Arch Form 1 202406.pdf | 13 Jan 2026 |
| Form 2File: BNGA Engr Form 2 202406.pdf | 13 Jan 2026 |
| Form 3File: BNGA CA Form 3 202406.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: BNGA Sold Inve Disclr 202406.pdf | 13 Jan 2026 |
| Form 1File: BNGA Arch Form 1 202503.pdf | 13 Jan 2026 |
| Form 2File: BNGA Er Form 2 202503.pdf | 13 Jan 2026 |
| Form 3File: BNGA CA Form 3 202503.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: BNGA Sold Inve Disclr 202503.pdf | 13 Jan 2026 |
| Form 1File: Form 1 Q1 June 2025 comprs.pdf | 13 Jan 2026 |
| Form 2File: Form 2 Q1 June 2025.pdf | 13 Jan 2026 |
| Form 3File: Form 3 Q1 June 2025 Comprs.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: BNGA Sold Inventory Disclosure 202506.pdf | 13 Jan 2026 |
| Disclosure of sold/ booked inventoryFile: Bandra North GA Sold Inventory Disclosure Q1.pdf | 21 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q1 June 2025 comprs.pdf | 20 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 Q1 June 2025 Comprs.pdf | 20 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q1 June 2025.pdf | 20 Jul 2025 |
| Other - LegalFile: Part OC-Wing DEF.pdf | 15 Jul 2025 |
| Other - LegalFile: Part OC-Wing B and C.pdf | 15 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2_202503_Er.pdf | 20 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 3_202503_Sold.pdf | 20 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 GA S6 Q4 Mar 25.pdf | 19 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: S6Form 1Architect certificate wing wiseJan to Mar 2025.pdf | 8 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 GA S6 Q2.pdf | 17 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1.pdf | 31 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 GA S6 Q3 4.pdf | 31 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 GA S6 Q3.pdf | 31 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Q3 Sold Unsold Inventory Disclosure.pdf | 31 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2023-24_Form-5.pdf | 21 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SVPL_BNGA_Sep-24_Form-1.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: SVPL_BNGA_Sep-24_Form-3.pdf | 20 Oct 2024 |
| Building plan approvalFile: S6_Amended IOA_02-06-2022.pdf | 9 Aug 2024 |
| Building Plan Approval (IOD)File: S6_Amended IOA_02-06-2022.pdf | 9 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A_2023-24.pdf | 22 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 202406_Sold.pdf | 22 Jul 2024 |
| Declaration in FORM BFile: 2 Affidavit.pdf | 20 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202406_Ar.pdf | 20 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202312_Ar.pdf | 20 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202406_Er.pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: 202406_CA.pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: 202403_CA.pdf | 24 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202403_Ar.pdf | 2 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202403_Er.pdf | 2 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202403_CA.pdf | 2 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S6-Form 2-Engineer Certificate_Dec23.pdf | 15 Jan 2024 |
| Certificates of CA (Form 3)File: GA S6 Form 3 CA Cert Dec 2023 BW.pdf | 15 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: S6 Form 5 Annual Audit Report FY 2022-23.pdf | 15 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 21_S6-Form 1 Arch Certificate_Jul-Sept 2019.pdf | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 22_S6-Form 1 Arch Certificate_Oct-Dec 2019.pdf | 20 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S6-Form 2-10_Engineer Certificate_Sept19_ 09012020.pdf | 20 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S6-Form 2-11_Engineer Certificate_Dec19_ 09012020.pdf | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202303_Ar.pdf | 19 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202306_Ar.pdf | 19 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202309_Ar.pdf | 19 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202309_Er.pdf | 11 Oct 2023 |
| Certificates of CA (Form 3)File: 202309_CA.pdf | 11 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202306_Er.pdf | 4 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: 202306_Sold.pdf | 4 Sep 2023 |
| Certificates of CA (Form 3)File: 202306_CA.pdf | 4 Sep 2023 |
| Proforma of Agreement for saleFile: GA_AfS.pdf | 4 Sep 2023 |
| Declaration about Commencement CertificateFile: S6 Declaration Commencement Certificate.pdf | 31 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20_S6-Form 1 Arch Certificate_Apr-Jun 2019.pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GA S6-Form 2-Q1 Jun 2022.pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GA S6-Form 2-Q1 Jun 2022.pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GA S6-Form 2-Q1 Jun 2022.pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GA S6-Form 2-Q1 Jun 2022.pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GA S6-Form 2-Q2 Sept 2022.pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GA S6-Form 2-Q3 Dec 2022.pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 GA S6 Q1 Jun 2023 (1).pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GA S6-Form 2-Q4 Mar 2022.pdf | 31 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GA S6-Form 2-Q4 Mar 2023.pdf | 31 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2 A Bandra North GA Form-2A_2020.pdf | 30 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2 A Bandra North GA Form-2A_2021.pdf | 30 Aug 2023 |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NEW VIDHARBHA | GOLIBAR ROAD SANTACRUZ EAST MUMBAI | 234 | Completed | May 2016 | May 2016 |
| EKTA ASHIYANA | GOLIBAR ROAD SANTACRUZ EAST MUMBAI | 148 | Completed | Sep 2015 | Sep 2015 |
| SAIBABA WING A | GOLIBAR ROAD SANTACRUZ EAST | 300 | Completed | Sep 2015 | Sep 2015 |
| PARAMOUNT | GOLIBAR ROAD SANTACRUZ EAST | 387 | Completed | Sep 2015 | Sep 2015 |
| Sanjivani Wing B | CTS 13 33 GOLIBAR ROAD SANTACRUZ EAST | 285 | Completed | Jun 2012 | Jun 2012 |
| OM SHIVSAKTI | GOLIBAR ROAD SANTACRUZ EAST MUMBAI | 48 | Completed | Jan 2012 | Jan 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 182 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep BANDRA NORTH GULMOHAR AVENUE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BANDRA NORTH6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 383 registered projects within 2 km.
12 PEGASUS
Jayant Enterprises S N Project
Kalpataru Magnus
Kalpataru Properties Pvt. Ltd.
Plotted Development Scheme at Sindhudurhnagari
MAHARASHTRA HOUSING AND AREA DEVELOPMENT A
SAJAY AVENUE 18
Vinca Realtors Private Limited
Sahakar excel Acropolis - I
EXCEL ENTERPRISES REALTY LLP
ADDRESS 51
V LAXMI EKTA DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: SHIVALIK VENTURES PRIVATE LIMITED
SHIVALIK VENTURES PRIVATE LIMITED has 2 registrations on MahaRERA, including PRABHAT DARSHAN and BANDRA NORTH GULMOHAR AVENUE. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if BANDRA NORTH GULMOHAR AVENUE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BANDRA NORTH GULMOHAR AVENUE?
The registered promoter entity is SHIVALIK VENTURES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BANDRA NORTH GULMOHAR AVENUE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against BANDRA NORTH GULMOHAR AVENUE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for BANDRA NORTH GULMOHAR AVENUE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BANDRA NORTH GULMOHAR AVENUE?
The professionals named in the filing: Architect: PAARSHAD ASSOCIATES; Engineer: GOKANI CONSULTANTS PRIVATE LIMITED; Chartered Accountant: Meghal Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BANDRA NORTH GULMOHAR AVENUE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback