Home / Browse projects / Thane, Maharashtra / BAMUBAI SADAN

Completed No litigation declared Others project

BAMUBAI SADAN

By SAMARTH DEVELOPERS

RG-MH-10370 · RERA P51700003704 · Last updated on MahaRERA portal: 18 Feb 2022

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Oct 2021Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Staircases, 75%
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

BAMUBAI SADAN is a Others project by SAMARTH DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700003704 on 6 Aug 2017. The registration is recorded completed; possession was promised by 30 Oct 2021. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameBAMUBAI SADAN
  • TypeOthers
  • Location
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421202
  • Pincode421202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700003704
  • ReraGenie IDRG-MH-10370

Builder

  • NameSAMARTH DEVELOPERS
  • Entity typePartnership
  • PartnersVIJAY BABU MHATRE, SHARMILA VIJAY MHATRE, SANTOSH ANANT BHOIR, POORNIMA SANTOSH BHOIR, SUNANDA RAMESH MHATRE, VAIBHAV VIJAY MHATRE, SHAILA BHIM MHATRE
  • Other registrations21 more →
  • Completed13 of 22
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredAug 2017First promiseOct 2019Revised toOct 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion30 Oct 2021
  • Revised completionRevised to 30 Oct 2021 (originally 31 Oct 2019)
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BAMUBAI SADANNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 75%.

BAMUBAI SADAN: 59% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered10

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,520 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
KISAN MAHADU BHOIRDOMBIVLIThane
AASHISH CORPORATIONDOMBIVLIThane

Approvals and building plan

Permissible FSI2834.58
Proposed, not sanctioned1,541 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, ISHAN APARTMENT, MAHATMA PHULE ROAD, VISHNUNAGAR, DOMBIVLI WEST 421202

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTIBIN TONSON THOMAS
ArchitectVARGHESE JOHN
EngineerMANOHAR VISHNU PATIL
PartnerRole in project
SAMARTH DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700005177Oct 2019 → Oct 2020

Reason as filed by the promoterWe have proposed to construct the said project by using fungible F.S.I. which was expected to be approved during the course of construction. But eventually the same is not approved till date. Further there was scarcity of building material supply. Due to aforementioned reasons, we could not complete the project with in stipulated time and hence are requested you good self to grant extension of registration under Maharera Authority for period of one year from 01/11/2019

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Feb 2022

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_Samarth Developers.pdf18 Feb 2022
Architect’s Certificate on Completion of Project (Form 4)File: Form No 4_Architect.pdf18 Feb 2022
Certificates of CA (Form 5)File: Form 5 RERA Certificate 29092018.pdf29 Sep 2018
Building plan approvalFile: Changes In Plan.pdf7 May 2018
Building plan approvalFile: Plant Sheet 1.pdf7 May 2018
Building plan approvalFile: Plant Sheet 2.pdf7 May 2018
Building Plan Approval (IOD)File: Changes In Plan.pdf7 May 2018
Building Plan Approval (IOD)File: Plant Sheet 1.pdf7 May 2018
Building Plan Approval (IOD)File: Plant Sheet 2.pdf7 May 2018
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE SAMARTH DEVELOPERS.pdf7 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Compressed Samarth Developers-Form 1-December 2017.pdf7 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Compressed Samarth Developers-Form 2-December 2017.pdf7 May 2018
Certificates of CA (Form 3)File: Samarth Developers-Form 3-December 2017.pdf7 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SAMARTH DEVELOPERS.pdf9 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SAMARTH DEVELOPERS.pdf9 Dec 2017
Certificates of CA (Form 3)File: Form_3_Sept_2017-Samarth_Developers_Compressed.pdf9 Dec 2017
Layout approvalFile: Approval Plan 1.pdf27 Jul 2017
Building plan approvalFile: Approval Plan 1.pdf27 Jul 2017
Building plan approvalFile: Approval Plan 2.pdf27 Jul 2017
PAN CardFile: Pan Card Copy.pdf27 Jul 2017
Copy of the legal title reportFile: Title Certificate - 1 page 1 and 2.pdf27 Jul 2017
Copy of the legal title reportFile: Title Certificate - 1 page 3 and 4.pdf27 Jul 2017
Copy of the legal title reportFile: Title Certificate 2.pdf27 Jul 2017
Details of encumbrancesFile: Letter for No encubrance.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Approval Plan 1.pdf27 Jul 2017
Building Plan Approval (IOD)File: Approval Plan 1.pdf27 Jul 2017
Building Plan Approval (IOD)File: Approval Plan 2.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Page 1.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Page 2.pdf27 Jul 2017
Declaration in FORM BFile: Form B.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE Page 1.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf27 Jul 2017
Certificates of CA (Form 3)File: Ca Certificate Page 1 and 2.pdf27 Jul 2017
Certificates of CA (Form 3)File: Ca Certificate Page 3 and 4.pdf27 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale page 1 to 8.pdf27 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale page 9 to 16.pdf27 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale page 17 to 24.pdf27 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale page 25 to 32.pdf27 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BAMUBAI SADAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DOMBIVLI7,600+ in Thane

2 kmBAMUBAI SADANCompleted 88Lapsed / revoked 74Other 126Dot size: filed unitsN

Filed coordinates, straight-line distance. 288 registered projects within 2 km.

Builder: SAMARTH DEVELOPERS

SAMARTH DEVELOPERS has 22 registrations on MahaRERA, including LAKSHMINARAYAN NAGAR and Omkar Residency. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if BAMUBAI SADAN is delayed beyond 30 Oct 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BAMUBAI SADAN?

The registered promoter entity is SAMARTH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BAMUBAI SADAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BAMUBAI SADAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BAMUBAI SADAN?

The professionals named in the filing: Architect: TIBIN TONSON THOMAS; Architect: VARGHESE JOHN; Engineer: MANOHAR VISHNU PATIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BAMUBAI SADAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BAMUBAI SADAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BAMUBAI SADAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.