Home / Browse projects / Pune, Maharashtra / BALAJI NISARG

Registration lapsed No litigation declared Residential / Group Housing project

BALAJI NISARG

By TIRUUPATEE VASTU NIRMAN PVT LTD

RG-MH-20001 · RERA P52100006956 · Last updated on MahaRERA portal: 13 Oct 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
48 of 66Construction stages doneacross 6 buildings; furthest along: Installation of Lifts, 90%
1Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

BALAJI NISARG is a Residential / Group Housing project by TIRUUPATEE VASTU NIRMAN PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100006956 on 16 Aug 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date. The completion date has moved by 18 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBALAJI NISARG
  • TypeResidential / Group Housing
  • Location
    • Kharadi
    • Shiraswadi
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100006956
  • ReraGenie IDRG-MH-20001

Builder

  • NameTIRUUPATEE VASTU NIRMAN PVT LTD
  • Entity typeCompany
  • Managing DirectorAJEENCKYA FATTESINGH JAGTAP

Key dates

46 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Aug 2017
  • Promised completion30 Dec 2022
  • Revised completionRevised to 30 Dec 2022 (originally 30 Jun 2021)
  • Buildings6 building records
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A TYPE BUILDING BUILDING NO 19 20 21NA50000
A TYPE BUILDING BUILDING NO 16 17 18NA50000
A TYPE BUILDING BUILDING NO 10 11 12 13NA50000
A TYPE BUILDING BUILDING NO 6 7 8 9NA50000
A TYPE BUILDING BUILDING NO 1 2 3 4 5NA50000
B TYPE BUILDING BUILDING NO 14 15NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 13 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

48 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Installation of Lifts, at 90%.

A TYPE BUILDING BUILDING NO 19 20 2181%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
A TYPE BUILDING BUILDING NO 16 17 1881%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
A TYPE BUILDING BUILDING NO 10 11 12 1381%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
A TYPE BUILDING BUILDING NO 6 7 8 981%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
A TYPE BUILDING BUILDING NO 1 2 3 4 579%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
B TYPE BUILDING BUILDING NO 14 1582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes85%
Street LightingYes70%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes70%
Energy managemcntYes80%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes80%

Parking filed93

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots93
Open Space93
BuildingOpen SpaceTotal
A TYPE BUILDING BUILDING NO 19 20 211515
A TYPE BUILDING BUILDING NO 16 17 181313
A TYPE BUILDING BUILDING NO 10 11 12 131616
A TYPE BUILDING BUILDING NO 6 7 8 92222
A TYPE BUILDING BUILDING NO 1 2 3 4 52727

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,610 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
VANDANA PRAKASH PAWARPune (M Corp.)Pune

Approvals and building plan

Permissible FSI18457.52
Proposed, not sanctioned18,301 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 4,5,6, Ground Floor Sr No 8,1C Kharadi By Pass Road, Kharadi Pune 411014

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANDEEP HARDIKAR
EngineerDnyandeo Sutar
Chartered AccountantCHETAN CHAUDHARY
PartnerRole in project
TIRUUPATEE VASTU NIRMAN PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100010095Jun 2021 → Jun 2022

Reason as filed by the promoterDear Sir, We, M/s Tiruupatee Vastu Nirman Pvt. Ltd., are constructing the project 'BALAJI NISARG' at Shiraswadi, Pune vide MahaRERA reg. no. P52100006956. We have completed the project and only the construction work of the amenities is impending which is going on. We would like to request an extension of project completion. Since the marketing agency appointed at the commencement of the project have defrauded both us and the customers by taking cash from them against the booking and not reporting it to us. After a confrontation, they promised to pay back and still promising to date but haven’t

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000022947Balaji Nisarg CoOperative Housing SocietyAjeenckya Fattesingh Jagtap23/04/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Declaration of Commencement Certificate (Balaji Nisarg).pdf13 Oct 2021
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold : Booked Inventory (Building Wise) (compressed).pdf13 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 - Annual Report by CA 17-18.pdf13 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - Annual Report by CA 18-19.pdf13 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Annual Report by CA 19-20.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (Balaji Nisarg) Apr-Jun 20.pdf4 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (Balaji Nisarg) Jul-Sep 20.pdf4 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (Balaji Nisarg) Oct-Dec 20.pdf4 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (Balaji Nisarg) Jan-Mar 21.pdf4 Oct 2021
Copy of the legal title reportFile: search.pdf29 Jul 2017
Details of encumbrancesFile: no encumbrance.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: NA.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFACATE BUILDING 1 TO 5.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFACATE BUILDING 6 TO 9.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFACATE BUILDING 10 TO 13.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFACATE BUILDING 14 , 15.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFACATE BUILDING 16,17,18.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFACATE BUILDING 19,20,21.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFACATE BUILDING 16,17,18.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFACATE BUILDING 19,20,21.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFACATE BUILDING 14,15.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFACATE BUILDING 10,11,12,13.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFACATE BUILDING 6,7,8,9.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFACATE BUILDING 1 ,2 ,3,4,5.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for sale.pdf29 Jul 2017
Layout approvalFile: Layout.pdf28 Jul 2017
Building plan approvalFile: Plan1.pdf28 Jul 2017
Building plan approvalFile: Plan2.pdf28 Jul 2017
PAN CardFile: PANCARD.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plan1.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plan2.pdf28 Jul 2017
Declaration in FORM BFile: Form B.pdf28 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BALAJI NISARG on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kharadi13,700+ in Pune

2 kmBALAJI NISARGCompleted 1Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: TIRUUPATEE VASTU NIRMAN PVT LTD

TIRUUPATEE VASTU NIRMAN PVT LTD has 1 registration on MahaRERA, including BALAJI NISARG. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that BALAJI NISARG shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BALAJI NISARG is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BALAJI NISARG?

The registered promoter entity is TIRUUPATEE VASTU NIRMAN PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BALAJI NISARG?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BALAJI NISARG?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BALAJI NISARG?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BALAJI NISARG?

The professionals named in the filing: Architect: SANDEEP HARDIKAR; Engineer: Dnyandeo Sutar; Chartered Accountant: CHETAN CHAUDHARY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BALAJI NISARG?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BALAJI NISARG. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BALAJI NISARG to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.