Home / Browse projects / Nashik, Maharashtra / BAGE NASHEMAN CO. OP. HSG. SOCIETY

Registration lapsed No litigation declared Others project

BAGE NASHEMAN CO. OP. HSG. SOCIETY

By BAGENASHEMAN CO OP HOUSING SOCIETY LTD

RG-MH-07833 · RERA P51600012278 · Last updated on MahaRERA portal: 30 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
24 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

BAGE NASHEMAN CO. OP. HSG. SOCIETY is a Others project by BAGENASHEMAN CO OP HOUSING SOCIETY LTD in Nashik, Maharashtra, registered with MahaRERA as P51600012278 on 1 Sep 2017. Possession was promised by 28 Jun 2022 and is now 52 months past that date.

At a glance

Project

  • NameBAGE NASHEMAN CO. OP. HSG. SOCIETY
  • TypeOthers
  • Location
    • Deolali
    • Deolaligaon
    • Nashik
    • 422011
  • Pincode422011
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600012278
  • ReraGenie IDRG-MH-07833

Builder

  • NameBAGENASHEMAN CO OP HOUSING SOCIETY LTD
  • Entity typeSociety
  • ChairpersonMAHENADRABHAI KANJIBHAI POKAR PATEL
  • SecretoryJUMMAN FATEMOHAMMAD SHAIKH

Key dates

52 months past promisethis monthRegisteredSep 2017PromisedJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion28 Jun 2022
  • Revised completionNone
  • Buildings3 building records
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA70000
BNA80000
CNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 30 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 0%.

A73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 30 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
A11
B11
C11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,644 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2619.4
Proposed, not sanctioned2,619 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNASHIK

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMUZZAFFAR GAFUR MANSURI
EngineerBHANUVILAS PUNDLIK BHAWSAR
PartnerRole in project
BAGENASHEMAN CO OP HOUSING SOCIETY LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Nov 2024

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 FY 2023-2024 BAGENASHEMAN.pdf30 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 NEW.pdf9 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CONSENT_compressed.pdf9 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 NEW.pdf7 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: BAGE NASHEMAN NEW CC_compressed.pdf22 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 BAGENASHEMAN CO OP SCAN.PDF6 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION CERTIFICATE new.pdf21 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: BAGE NASHEMAN COMPLETION.pdf11 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5 CA CERTIFICATE BAGE NASHEMAN.PDF21 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA AUDIT BAGE NASIMAN CO OP OC FY 20-21 Scan.pdf26 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf18 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: BAGE NASHEMAN CO OP HSG SOC FORM NO-5 19-20 SCAN .pdf18 Mar 2021
Certificates of CA (Form 5)File: FORM 5 BAGENASHEMAN CO OP.PDF30 Sep 2019
Certificates of CA (Form 5)File: BAGE NASHEMAN.PDF29 Sep 2018
Building plan approvalFile: building plan.pdf31 Jul 2017
Layout approvalFile: layout 1.pdf31 Jul 2017
Layout approvalFile: layout.pdf31 Jul 2017
PAN CardFile: BAGESHYAM CO OP PAN CARD.pdf31 Jul 2017
Copy of the legal title reportFile: LEGAL REPORT.pdf31 Jul 2017
Details of encumbrancesFile: DESCRIPTION OF PROPERTY.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: layout 1.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: layout.pdf31 Jul 2017
Building Plan Approval (IOD)File: building plan.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: nashik muncipal corporation.pdf31 Jul 2017
Declaration in FORM BFile: FORM B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERT.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERT.pdf31 Jul 2017
Certificates of CA (Form 3)File: BAGE NASHEMAN CA CERT.pdf31 Jul 2017
Proforma of Allotment letterFile: Bage Naseman-Draft.pdf31 Jul 2017

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BAGE NASHEMAN CO. OP. HSG. SOCIETY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Deolali4,100+ in Nashik

Builder: BAGENASHEMAN CO OP HOUSING SOCIETY LTD

BAGENASHEMAN CO OP HOUSING SOCIETY LTD has 1 registration on MahaRERA, including BAGE NASHEMAN CO. OP. HSG. SOCIETY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that BAGE NASHEMAN CO. OP. HSG. SOCIETY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BAGE NASHEMAN CO. OP. HSG. SOCIETY is delayed beyond 28 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BAGE NASHEMAN CO. OP. HSG. SOCIETY?

The registered promoter entity is BAGENASHEMAN CO OP HOUSING SOCIETY LTD, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BAGE NASHEMAN CO. OP. HSG. SOCIETY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BAGE NASHEMAN CO. OP. HSG. SOCIETY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BAGE NASHEMAN CO. OP. HSG. SOCIETY?

The professionals named in the filing: Architect: MUZZAFFAR GAFUR MANSURI; Engineer: BHANUVILAS PUNDLIK BHAWSAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BAGE NASHEMAN CO. OP. HSG. SOCIETY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BAGE NASHEMAN CO. OP. HSG. SOCIETY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BAGE NASHEMAN CO. OP. HSG. SOCIETY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.