AVANEESH

By SUYASH DEVELOPERS

RG-MH-05138 · RERA P51600023817 · Last updated on MahaRERA portal: 4 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 33 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
8 of 11Construction stages donefurthest along: Installation of Lifts, 80%
7 of 30Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 189 documents Report an error

AVANEESH is a Others project by SUYASH DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600023817 on 6 Jan 2020. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 33 months from the original filing. 23 of the 30 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameAVANEESH
  • TypeOthers
  • Location
    • BANKAR CHOWK
    • KATHE GALLI DWARAKA
    • Nashik
    • 422011
  • Pincode422011
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600023817
  • ReraGenie IDRG-MH-05138

Builder

  • NameSUYASH DEVELOPERS
  • Entity typePartnership
  • PartnersDARSHAN RAMANLAL BUMB, SAMEER SITARAM SONAWANE
  • Other registrations4 more →
  • Completed2 of 5
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredJan 2020First promiseDec 2023Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Jan 2020
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 20 Dec 2023)
  • Buildings1 building record
  • Documents filed189 files

Current status

77%23 of 30 units booked
47.5%Work done, per cost certificate

Figures as on 4 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AVANEESHNA9826430

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 80%.

AVANEESH: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area925 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
Declared on20 May 2025
LandownerVillageDistrict
KEDARNATH PUNDLIK KATHENashikNashik
TARABAI KEDARNATH KATHENashikNashik
TEJASHREE RAJENDRA KATHENashikNashik

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI2325.56
Proposed, not sanctioned2,101 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHARANPUR ROAD NASHIK
Estimated costRs 6.06 cr
Cost incurredRs 2.88 cr
Work done47.47%
BuildingWingEstimatedIncurred
AVANEESHNARs 6.06 crRs 2.88 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNITIN JAYANT KUTE
EngineerSHAILESH PATIL
Chartered AccountantPARESH PRAKASH SABADRA
Chartered AccountantPrakash Sabadra
Chartered AccountantSuchita Pawar
PartnerRole in project
SUYASH DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600018979Dec 2023 → Dec 2024

Reason as filed by the promoterDue to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis

EA20052501193Dec 2023 → Dec 2025

Reason as filed by the promotera) As the entire country including Nashik District were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, we stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are s

EA29052621160Dec 2023 → Sep 2026

Reason as filed by the promotera) As the entire country including Nashik District were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, we stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are s

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed189

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 189 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A - March 25 .pdf4 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A - March 26 .pdf4 Jul 2026
Withdrawal Update Form 1File: AR - March 26 Final.pdf12 Jun 2026
Withdrawal Update Form 2File: ER - March 26 .pdf12 Jun 2026
Withdrawal Update Form 3File: CA-26.pdf12 Jun 2026
Withdrawal Update Form 1File: AR - Dec 25.pdf31 Mar 2026
Withdrawal Update Form 2File: ER - Dec 25.pdf31 Mar 2026
Withdrawal Update Form 3File: Form-3-Dec 25.pdf31 Mar 2026
Form 5 (FY 2024-2025)File: RERA Audit Report- FY 24-25.pdf6 Jan 2026
Withdrawal Update Form 1File: AR - June 25.pdf17 Dec 2025
Withdrawal Update Form 1File: AR - sept 25.pdf17 Dec 2025
Withdrawal Update Form 2File: ER - june 25.pdf17 Dec 2025
Withdrawal Update Form 2File: ER - sept 25.pdf17 Dec 2025
Withdrawal Update Form 3File: CA - june 25 final.pdf17 Dec 2025
Withdrawal Update Form 3File: CA - sept 25 final.pdf17 Dec 2025
Withdrawal Update Form 1File: AR - June 25.pdf16 Dec 2025
Withdrawal Update Form 2File: ER - june 25.pdf16 Dec 2025
Withdrawal Update Form 3File: CA - june 25 final.pdf16 Dec 2025
Form 1File: Architect certificate March 2025.pdf13 Aug 2025
Form 2File: ER March 2025.pdf13 Aug 2025
Form 3File: CA Certificate March 2025.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure March 25.pdf13 Aug 2025
Form 2A (FY 2024-2025)File: Form 2A F Y 24-25.pdf23 Jul 2025
Form 1File: AR March 24-min.pdf2 Jul 2025
Form 2File: 1 ER March 24-min.pdf2 Jul 2025
Form 3File: Final CA March 24-min.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 20250411003102.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 20250411003155.pdf2 Jul 2025
Form 1File: AR June 24-min.pdf2 Jul 2025
Form 2File: 2 ER June 24-min.pdf2 Jul 2025
Form 3File: Final CA june 24-min.pdf2 Jul 2025
Form 1File: AR Sept 24-min.pdf2 Jul 2025
Form 2File: 3 ER Sept 24-min.pdf2 Jul 2025
Form 3File: Final CA Sep 24-min.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 20250411003327.pdf2 Jul 2025
Form 1File: AR Dec 24-min.pdf2 Jul 2025
Form 2File: 4 ER Dec 24-min.pdf2 Jul 2025
Form 3File: Final CA Dec 24-min.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: 20250411003247.pdf2 Jul 2025
Form 2A (FY 2022-2023)File: Form 2A FY 22-23.pdf20 May 2025
Form 2A (FY 2021-2022)File: Form 2A FY 21-22.pdf20 May 2025
Form 2A (FY 2020-2021)File: Form 2A FY 19-20.pdf20 May 2025
Form 2A (FY 2019-2020)File: Form 2A FY 19-20.pdf20 May 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory-June 2023.pdf19 May 2025
Form 2File: 1 Disclosure of sold_ booked inventory-June 2023.pdf19 May 2025
Form 1File: 2 Disclosure of sold_ booked inventory-Sept 2023.pdf19 May 2025
Form 2File: 12 Form-1 30092023.pdf19 May 2025
Form 3File: 12 Form 2 30092023.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 12 CA Certificate 30092023.pdf19 May 2025
Form 1File: 12 Form 2 30092023.pdf19 May 2025
Form 2File: 1 Disclosure of sold_ booked inventory-June 2023.pdf19 May 2025
Form 3File: 12 CA Certificate 30092023.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 13 Form-1 31122023.pdf19 May 2025
Form 1File: 10 Form-1 31032023.pdf19 May 2025
Form 2File: 10 Form 2 31032023.pdf19 May 2025
Form 3File: 10 CA Certificate 31032023.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold booked inventory.pdf19 May 2025
Form 1File: 10 Form-1 31032023.pdf19 May 2025
Form 2File: 10 Form 2 31032023.pdf19 May 2025
Form 3File: 10 CA Certificate 31032023.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold booked inventory.pdf19 May 2025
Form 1File: 10 Form 2 31032023.pdf19 May 2025
Form 2File: 10 CA Certificate 31032023.pdf19 May 2025
Form 3File: 1 Disclosure of sold booked inventory.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 10 Form-1 31032023.pdf19 May 2025
Form 1File: 10 Form-1 31032023.pdf19 May 2025
Form 2File: 1 Disclosure of sold booked inventory.pdf19 May 2025
Form 3File: 10 CA Certificate 31032023.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 10 Form 2 31032023.pdf19 May 2025
Form 1File: 10 Form-1 31032023.pdf19 May 2025
Form 2File: 1 Disclosure of sold booked inventory.pdf19 May 2025
Form 3File: 10 Form 2 31032023.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 10 CA Certificate 31032023.pdf19 May 2025
Form 1File: 10 Form 2 31032023.pdf19 May 2025
Form 2File: 10 Form-1 31032023.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold booked inventory.pdf19 May 2025
Form 1File: 10 Form-1 31032023.pdf19 May 2025
Form 2File: 1 Disclosure of sold booked inventory.pdf19 May 2025
Form 3File: 10 CA Certificate 31032023.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: 3 Form-1 30092021.pdf19 May 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationRegisteredStatusPromisedDelivered
Suyash Trade TowerP51600033538Nashik Municipal Corporation, NashikFeb 2022OngoingDec 2026Not due yet

How this compares with Nashik

77%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 33 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AVANEESH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KATHE GALLI DWARAKA4,100+ in Nashik

2 kmAVANEESHCompleted 155Lapsed / revoked 39Other 98Dot size: filed unitsN

Filed coordinates, straight-line distance. 292 registered projects within 2 km.

Builder: SUYASH DEVELOPERS

Suyash Developers has 5 registrations on MahaRERA, including Atmaram Park and Suyash Mart. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if AVANEESH is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AVANEESH?

The registered promoter entity is SUYASH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AVANEESH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AVANEESH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AVANEESH?

The professionals named in the filing: Architect: NITIN JAYANT KUTE; Engineer: SHAILESH PATIL; Chartered Accountant: PARESH PRAKASH SABADRA; Chartered Accountant: Prakash Sabadra; Chartered Accountant: Suchita Pawar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AVANEESH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AVANEESH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AVANEESH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.