ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Aurigae Residency D Wing

Registered Litigation declared Residential / Group Housing project

Aurigae Residency D Wing

By Adinathay

RG-MH-70675 · RERA P51800019096 · Last updated on MahaRERA portal: 21 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • Completion date moved by 27 months
  • 1 extension taken
  • Rs 32.50 crore secured on the land, in favour of DMI Finance Private Limited
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 27 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
6 of 80Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

Aurigae Residency D Wing is a Residential / Group Housing project by Adinathay in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800019096 on 4 Jan 2019. Possession is promised by 31 Mar 2027. The completion date has moved by 27 months from the original filing. 74 of the 80 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameAurigae Residency D Wing
  • TypeResidential / Group Housing
  • Location
    • Thakur Complex
    • Kandivali East
    • Borivali
    • Mumbai Suburban
    • 400101
  • Pincode400101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800019096
  • ReraGenie IDRG-MH-70675

Builder

  • NameAdinathay
  • Entity typePartnership
  • PartnersAditya Ramdas Sangle, HARSHADA RAMDAS SANGLE, AMIT PANGAM, SIDDHESH PANGAM

Key dates

this monthRegisteredJan 2019First promiseDec 2024Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Jan 2019
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed74 files

Current status

92%74 of 80 units booked
96.7%Work done, per cost certificate

Figures as on 21 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AURIGAE RESIDENCY D WINGNA572080080

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

AURIGAE RESIDENCY D WING: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered33

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,429 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofDMI Finance Private Limited
Secured amountRs 32.50 crore
CERSAI search filedYes
Declared on8 May 2026

Approvals and building plan

Sanctioning authoritymunicipal corporation of greater mumbai
Permissible FSI6000.0
Proposed, not sanctioned462 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKANDIVALI EAST, THAKUR COMPLEX
Estimated costRs 21.42 cr
Cost incurredRs 20.72 cr
Work done96.71%
BuildingWingEstimatedIncurred
AURIGAE RESIDENCY D WINGNARs 21.42 crRs 20.72 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay V. Shah
ArchitectBipin More
EngineerAjay Mahale
EngineerKEVIN PATEL
Chartered AccountantKapure and Kapure
Chartered AccountantV C Shah and Co
PartnerRole in project
Adinathay-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20052621036Dec 2024 → Mar 2027

Reason as filed by the promoterThe current facts of the case are being explained hereunder. The construction work of the project has been completed in all respects. This is duly evidenced by Table A of Form 1, i.e., the Architect’s Certificate. The primary reason for the delay in completion of the project was the slow pace of sales during the initial phases. Although the number of units sold has improved over time, the earlier sluggish sales adversely impacted on the project’s cash flow, thereby contributing to the delay. Additionally, certain contractors appointed for execution of various works did not perform as expected,

Litigation declared2

CaseCourtStatus
Suit 90/2007/2007High Court of MumbaiPending
Suit 3291/2005/2005High Court of MumbaiPending

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Nov 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Signed Form 5_FY 2025-26.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 - June 2026.pdf6 Aug 2026
Withdrawal Update Form 2File: Form 2 - June 2026 - DSC.pdf6 Aug 2026
Withdrawal Update Form 3File: Form 3 June 26_compressed.pdf6 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A_MAR-2026 - DSC.pdf6 Aug 2026
Form 1File: Form 1 - Mar 2025.pdf29 Jul 2026
Form 2File: Mar 2025.pdf29 Jul 2026
Form 3File: Form 3- Aurigae- Mar 25_compressed.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - Mar 2025.pdf29 Jul 2026
Withdrawal Update Form 1File: Form 1 - June 2025.pdf29 Jul 2026
Withdrawal Update Form 1File: Form 1 - Sep 2025.pdf29 Jul 2026
Withdrawal Update Form 1File: Form 1 - Dec 2025.pdf29 Jul 2026
Withdrawal Update Form 1File: Form 1 March 26.pdf29 Jul 2026
Withdrawal Update Form 2File: June 2025.pdf29 Jul 2026
Withdrawal Update Form 2File: Sep 2025.pdf29 Jul 2026
Withdrawal Update Form 2File: Dec 2025.pdf29 Jul 2026
Withdrawal Update Form 2File: Form 2 - March 26.pdf29 Jul 2026
Withdrawal Update Form 3File: Form 3- Aurigae- June 25_compressed.pdf29 Jul 2026
Withdrawal Update Form 3File: Form 3- Aurigae- Sep 25_compressed.pdf29 Jul 2026
Withdrawal Update Form 3File: Form 3- Aurigae- Dec 25_compressed.pdf29 Jul 2026
Withdrawal Update Form 3File: Form 3 - March 26.pdf29 Jul 2026
Form 5 (FY 2021-2022)File: signed Form 5.pdf30 Jun 2026
Form 5 (FY 2022-2023)File: Form 5 - Adinathay Enterprises - 22-23.pdf30 Jun 2026
Form 5 (FY 2023-2024)File: Form 5 - Adinathay - 2023-24 - Final.pdf30 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 - Adinathay - 2024-25 - Final.pdf30 Jun 2026
Form 1File: Form 1 - Mar 2024.pdf11 Apr 2026
Form 2File: Mar 2024.pdf11 Apr 2026
Form 3File: Form 3- Aurigae- Mar 24_compressed.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - Mar 2024.pdf11 Apr 2026
Form 2A (FY 2020-2021)File: Form 2A_MAR-2021.pdf11 Apr 2026
Form 2A (FY 2021-2022)File: Form 2A_MAR-2022.pdf11 Apr 2026
Form 2A (FY 2022-2023)File: Form 2A_MAR-2023.pdf11 Apr 2026
Form 2A (FY 2023-2024)File: Form 2A_MAR-2024.pdf11 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A_MAR-2025.pdf11 Apr 2026
Form 5 (FY 2019-2020)File: Form 5 - 2019-2020.pdf11 Apr 2026
Form 5 (FY 2020-2021)File: Form 5 - 2020-2021.pdf11 Apr 2026
Form 1File: Form 1 - Mar 2024.pdf9 Apr 2026
Form 2File: Mar 2024.pdf9 Apr 2026
Form 3File: Form 3- Aurigae- Mar 24_compressed.pdf9 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - Mar 2024.pdf9 Apr 2026
Form 1File: Form 1 - Mar 2019.pdf8 Apr 2026
Form 2File: Mar 2019.pdf8 Apr 2026
Form 3File: Form 3- Aurigae- Mar 19.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - Mar 2019.pdf8 Apr 2026
Form 1File: Form 1 - Mar 2020.pdf8 Apr 2026
Form 2File: Mar 2020.pdf8 Apr 2026
Form 3File: Form 3- Aurigae- Mar 20.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - Mar 2020.pdf8 Apr 2026
Form 1File: Form 1 - Mar 2021.pdf8 Apr 2026
Form 3File: Form 3- Aurigae- Mar 21.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - Mar 2021.pdf8 Apr 2026
Form 2File: Mar 2021.pdf8 Apr 2026
Form 1File: Form 1 - Mar 2022.pdf8 Apr 2026
Form 2File: Mar 2022.pdf8 Apr 2026
Form 3File: Form 3- Aurigae- Mar 22_compressed.pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - Mar 2022.pdf8 Apr 2026
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Adinathay Form 2A March 19.pdf20 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Adinathay Form 2A- June 19.pdf20 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Adinathay Form 2A- September 19.pdf20 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Adinathay Form 2A-December 19.pdf20 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Adinathay Form 2A- MArch 2020.pdf20 May 2022
Declaration about Commencement CertificateFile: Adinathay_Declaration About CC.pdf5 Jan 2022
Disclosure of sold/ booked inventoryFile: Adinathay_Sold Unsold inventory_compressed.pdf5 Jan 2022
Details of encumbrancesFile: Encumbreance.pdf26 May 2021
Certificates of CA (Form 3)File: Adinathay Form3 till Sept'18.pdf18 Dec 2018
Details of encumbrancesFile: Adinathay Encumbrance Undertaking.pdf28 Nov 2018
Declaration in FORM BFile: Adinathay Form B RERA.pdf28 Nov 2018
Layout approvalFile: IOD PLAN.pdf24 Nov 2018
Building plan approvalFile: IOD Adinathay.pdf24 Nov 2018
Copy of the legal title reportFile: Title Certificate.pdf24 Nov 2018
Copy of Layout Approval (in case of layout)File: IOD PLAN.pdf24 Nov 2018
Building Plan Approval (IOD)File: IOD Adinathay.pdf24 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: CC Adinathay.pdf24 Nov 2018
Proforma of Allotment letterFile: RERA Agreement - Adinathay Enterprises.pdf24 Nov 2018

How this compares with Mumbai Suburban

92%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 27 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aurigae Residency D Wing on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kandivali East6,700+ in Mumbai Suburban

2 kmAurigae Residency D WingCompleted 26Lapsed / revoked 14Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 77 registered projects within 2 km.

Builder: Adinathay

Adinathay has 1 registration on MahaRERA, including Aurigae Residency D Wing. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Aurigae Residency D Wing is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aurigae Residency D Wing?

The registered promoter entity is Adinathay, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aurigae Residency D Wing?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aurigae Residency D Wing?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aurigae Residency D Wing?

The professionals named in the filing: Architect: Sanjay V. Shah; Architect: Bipin More; Engineer: Ajay Mahale; Engineer: KEVIN PATEL; Chartered Accountant: Kapure and Kapure; Chartered Accountant: V C Shah and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aurigae Residency D Wing?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aurigae Residency D Wing. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aurigae Residency D Wing to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.