Home / Browse projects / Pune, Maharashtra / AURA KOLLECTIVE

Registered No litigation declared Mixed project

AURA KOLLECTIVE

By GM RANAWAT VENTURES

RG-MH-04844 · RERA P52100021608 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 76 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2030Possession promisedmoved 76 months from the original
1 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 15%
25 of 34Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 185 documents Report an error

AURA KOLLECTIVE is a Mixed project by GM RANAWAT VENTURES in Pune, Maharashtra, registered with MahaRERA as P52100021608 on 15 Jul 2019. Possession is promised by 30 Apr 2030. The completion date has moved by 76 months from the original filing. 9 of the 34 units on this registration are recorded sold or booked, and 1 of 22 construction stages are filed complete.

At a glance

Project

  • NameAURA KOLLECTIVE
  • TypeMixed
  • Location
    • Lulla Nagar Bibwevadi Road
    • BIBWEWADI MUNJERI
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411037
  • Pincode411037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100021608
  • ReraGenie IDRG-MH-04844

Builder

  • NameGM RANAWAT VENTURES
  • Entity typePartnership
  • PartnersGhanshyam Gangaram Agarwal, Ajit Ghanshyam Shah, Narendra Ghanshyam Shah, Jagdish Ghanshyam Shah, INDRANEEL LANDMARKS LLP Through Authorised Partner Devendra Sarojbhai Shah

Key dates

this monthRegisteredJul 2019First promiseDec 2023Revised toApr 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jul 2019
  • Promised completion30 Apr 2030
  • Revised completionRevised to 30 Apr 2030 (originally 30 Dec 2023)
  • Buildings2 building records
  • Documents filed185 files

Current status

26%9 of 34 units booked
36.5%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AURA KOLLECTIVENA141029534
GAGAN GM AXIA - Proposed Fourth Floor to Tenth FloorNA66000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 15%.

AURA KOLLECTIVE10%
ActivityProgress
Excavation100%
Basement (if any)15%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GAGAN GM AXIA - Proposed Fourth Floor to Tenth Floor0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed133

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots133
Closed/Covered126
Open Space7

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,176 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Jun 2025

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI6678.0
Proposed, not sanctioned6,678 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, SHOP NO. 16, BUILDING - A, ASHWINI PARADISE, SR NO - 588/2C, CTS NO. 3817, NEAR GANGADHAM CHOWK, BIBEWADI LULLA NAGAR, PUNE - 411037, TOLL FREE NO. 18004194332
Estimated costRs 28.65 cr
Cost incurredRs 10.45 cr
Work done36.47%
BuildingWingEstimatedIncurred
AURA KOLLECTIVENARs 23.44 crRs 10.45 cr
GAGAN GM AXIA - Proposed Fourth Floor to Tenth FloorNARs 2.60 cr-
-NARs 2.60 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVikas Achalkar
ArchitectParvez Jamadar & Associates
EngineerR & J Consultants
Chartered AccountantSCT & Company
PartnerRole in project
GAGAN G M REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100021608/WarDec 2023 → Apr 2030

Reason as filed by the promoterNA

EXT52100028328Dec 2023 → Dec 2029

Reason as filed by the promoterDear Sir, The project Gagan GM Axia is registered with the RERA Authority under Registration no P52100021608 on 15/07/2019, wherein the date of completion of Gagan GM Axia is declared as 30th December 2023. We have not taken any bookings, not sold any units, also not given any allotment in the said project till date and propose to extend the completion date of the project to 31st December 2029. Therefore request you to grant us an extension under section 7(3) of RERA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Nov 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2030

Documents filed185

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 185 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Aura Collective Form 1.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2 Aura Kollective.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Aura Kollective.pdf30 Jul 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT FORM.pdf14 May 2026
Withdrawal Update Form 2File: Form 2.pdf14 May 2026
Withdrawal Update Form 3File: FORM 3 AURA KOLLECTIVE.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 Q3.pdf11 Feb 2026
Withdrawal Update Form 2File: Form 2 Q 3.pdf11 Feb 2026
Withdrawal Update Form 3File: FORM 3 Q3.pdf11 Feb 2026
Layout approvalFile: 1-8_11zon.pdf13 Nov 2025
Building plan approvalFile: 2-8_11zon.pdf13 Nov 2025
Building plan approvalFile: 3-8_11zon.pdf13 Nov 2025
Building plan approvalFile: 4-8_11zon.pdf13 Nov 2025
Building plan approvalFile: 5-8_11zon.pdf13 Nov 2025
Building plan approvalFile: 6-8_11zon.pdf13 Nov 2025
Building plan approvalFile: 7-8_11zon.pdf13 Nov 2025
Building plan approvalFile: 8-8_11zon.pdf13 Nov 2025
Commencement certificateFile: CC.pdf13 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf13 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf13 Nov 2025
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE_compressed.pdf13 Nov 2025
Withdrawal Update Form 1File: GMR Form 1.pdf18 Sep 2025
Withdrawal Update Form 1File: GMR Form 1.pdf18 Sep 2025
Withdrawal Update Form 1File: GMR Form 1.pdf18 Sep 2025
Withdrawal Update Form 2File: GMR Form 2 Engineering.pdf18 Sep 2025
Withdrawal Update Form 2File: GMR Form 2 Engineering.pdf18 Sep 2025
Withdrawal Update Form 2File: GMR Form 2 Engineering.pdf18 Sep 2025
Withdrawal Update Form 3File: GMR Form 3 CA Cert_compressed.pdf18 Sep 2025
Withdrawal Update Form 3File: GMR Form 3 CA Cert_compressed.pdf18 Sep 2025
Withdrawal Update Form 3File: GMR Form 3 CA Cert_compressed.pdf18 Sep 2025
Layout approvalFile: 1_compressed.pdf9 Sep 2025
Building plan approvalFile: 2_compressed.pdf9 Sep 2025
Building plan approvalFile: 3_compressed.pdf9 Sep 2025
Building plan approvalFile: 4_compressed.pdf9 Sep 2025
Building plan approvalFile: 5_compressed.pdf9 Sep 2025
Building plan approvalFile: 6_compressed.pdf9 Sep 2025
Building plan approvalFile: 7_compressed.pdf9 Sep 2025
Building plan approvalFile: 8_compressed.pdf9 Sep 2025
Layout approvalFile: 1_compressed.pdf9 Sep 2025
Building plan approvalFile: 2_compressed.pdf9 Sep 2025
Building plan approvalFile: 3_compressed.pdf9 Sep 2025
Building plan approvalFile: 4_compressed.pdf9 Sep 2025
Building plan approvalFile: 5_compressed.pdf9 Sep 2025
Building plan approvalFile: 6_compressed.pdf9 Sep 2025
Building plan approvalFile: 7_compressed.pdf9 Sep 2025
Building plan approvalFile: 8_compressed.pdf9 Sep 2025
Withdrawal Update Form 1File: GMR Form 1.pdf5 Sep 2025
Withdrawal Update Form 2File: GMR Form 2 Engineering.pdf5 Sep 2025
Withdrawal Update Form 3File: GMR Form 3 CA Cert_compressed.pdf5 Sep 2025
Commencement Certificates / NA Order for plotted developmentFile: CC_compressed.pdf19 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (5).pdf7 May 2025
Certificates of CA (Form 3)File: Form 3 FY 24-25 Q4_compressed_organized.pdf7 May 2025
Certificates of CA (Form 3)File: Form 3 FY 24-25 Q3_compressed.pdf6 May 2025
Certificates of CA (Form 3)File: Form 3 FY 24-25 Q4_compressed.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 22-23 Q2_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24-25 Q4.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24-25 Q3.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24-25 Q2.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24-25 Q1_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 23-24 Q4_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 23-24 Q3_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 23-24 Q2_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 23-24 Q1_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 22-23 Q4_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 22-23 Q3_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 19-20 Q4_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 22-23 Q1_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 21-22 Q4_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 21-22 Q3_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 21-22 Q2_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 21-22 Q1_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 20-21 Q4_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 20-21 Q3_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 20-21 Q2_organized.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 20-21 Q1.pdf2 May 2025
Declaration in FORM BFile: Form B.pdf1 May 2025
Certificates of CA (Form 3)File: FORM 3 FY 2024 25 Q4.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Sep 2019.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Sep 2019_organized.pdf1 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Aug 2020.pdf1 May 2025

How this compares with Pune

26%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 76 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AURA KOLLECTIVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BIBWEWADI MUNJERI13,700+ in Pune

Builder: GM RANAWAT VENTURES

GM RANAWAT VENTURES has 1 registration on MahaRERA, including AURA KOLLECTIVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AURA KOLLECTIVE is delayed beyond 30 Apr 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AURA KOLLECTIVE?

The registered promoter entity is GM RANAWAT VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AURA KOLLECTIVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AURA KOLLECTIVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AURA KOLLECTIVE?

The professionals named in the filing: Architect: Vikas Achalkar; Architect: Parvez Jamadar & Associates; Engineer: R & J Consultants; Chartered Accountant: SCT & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AURA KOLLECTIVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AURA KOLLECTIVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AURA KOLLECTIVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.